Monthly State Let Construction Report For Beaumont District As Of Nov 10, 2024 Page 1 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayUS 90
FromAT FM 1413
To.
CSJ0028-03-107
Proj IDSTP 2021(525)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.80022054430.4031370419.8799.9
CountyLIBERTY
HighwayUS 90
FromHARRIS COUNTY LINE, EAST
ToUPRR
CSJ0028-03-108
Proj IDF 2021(524)
Work TypeOVERLAY
 
7.0002829816.542958107.3699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-21
Work Began03-10-22
Work Completed
Time Computed00-00-00
Contract Working Days574
Addl Days Granted75
Working Days Charged424
Percent Time Used65
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-107
TRAFFIC SIGNS & LINES, LLC (0.46)
MTAM CORPORATION (0.10)
WILLOW CITY SIGN & RAIL, INC. (1.25)
THIRD COAST SERVICES LLC (0.67)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
PRIMATE CONSTRUCTION, LP (0.17)
A&J REBAR LLC (1.89)
CPAVE, INC. (0.50)
ROCKIN C MILLING (0.62)
CEN TEX HYDROSEED, INC. (0.27)
CHAMPION FUEL SOLUTIONS (0.86)
BARRICADES UNLIMITED (0.36)
MEMCO STAFFING, LLC (0.00)
JB PINNACLE GROUP, LLC (0.33)
RAY"S THREADING AND FAB SHOP (0.09)
TEX-BRASKA, LLC (0.07)
HB FARMER FOUNDATION, LLC (12.77)
MARTIN MARIETTA MATERIALS, INC. (0.28)
CHERRY CRUSHED CONCRETE (0.38)
DORAN STEEL, INC. (0.13)
A&J REBAR LLC (0.00)
CURB PLANET INC. (0.02)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (12.24)
Contract #08213210
Totals24884246.941044146.3434328527.2399.9

CountyLIBERTY
HighwayUS 90
FromSH 146, EAST
ToS.COLBERT ST
CSJ0028-03-110
Proj IDSTP 2021(086)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.806336017.051006786.9299.9
CountyLIBERTY
HighwaySH 321
FromDAYTON HIGH SCHOOL, SOUTH
ToUS 90
CSJ0593-01-131
Proj IDSTP 2021(086)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.709758418.951081802.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began01-11-21
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted124
Working Days Charged177
Percent Time Used96
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-110
AREA WIDE PROTECTIVE, INC. (1.42)
DOUBLE OAK EROSION, INC. (1.38)
SOWELLS ENGINEERS & CONSTRUCTORS, LLC (38.68)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.13)
J. KRU LAND SERVICES, LLC. (0.40)
CRABTREE BARRICADE SYSTEMS, INC. (2.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.59)
MASTER CURB, LLC (0.22)
CHERRY DEMOLITION (3.01)
PIPE WHOLESALERS OF TEXAS, INC. (5.54)
LONESTAR DOCUMENTATION, LLC (0.35)
TRAFFIC SIGNS & LINES, LLC (1.42)
MEMCO (4.56)
K4 ENVIRONMENTAL LLC (0.18)
TRP CONSTRUCTION GROUP, LLC (2.20)
Contract #10203215
Totals1094436.000.002088589.9199.9

CountyLIBERTY
HighwayUS 90
FromAT UP RAILROAD
To.
CSJ0028-03-111
Proj IDCM 2025(216)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.76927266205.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days603
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-111
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243005
Totals27266205.500.000.000.0

CountyLIBERTY
HighwayUS 90
From0.42 MI EAST OF FM 1409
To1.65 MI WEST OF LP 227
CSJ0028-03-116
Proj IDSTP 2B24(203)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.6201654702.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243019
Totals1654702.800.000.000.0

CountyJEFFERSON ETC
HighwayUS 90 ETC
FromAT FM 364
To.
CSJ0028-06-083
Proj IDSTP 2021(526)HES
Work TypeTRAFFIC CONTROL DEVICES
 
4.0873878702.084517912.9499.9
Work Order06-22-21
Work Began10-18-21
Work Completed
Time Computed10-18-21
Contract Working Days320
Addl Days Granted97
Working Days Charged369
Percent Time Used88
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-06-083
717 CONSTRUCTION SERVICES, LLC (3.05)
SEMPER STRIPING LLC (2.26)
JH CONTRACT FIELD SERVICES, LLC (0.47)
HALL ENTERPRISES AND CONTRACTING LLC (1.03)
Contract #05213014
Totals3878702.08193720.354517912.9499.9

CountyJEFFERSON ETC
HighwayUS 90 ETC
FromMEEKER RD, EAST
ToFM 364
CSJ0028-06-087
Proj IDF 2024(034)
Work TypeSEAL COAT
 
130.38613998169.3512243562.4587.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-23
Work Began05-06-24
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged33
Percent Time Used44
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-06-087
INTERSTATE BARRICADES & MARKINGS, INC. (18.20)
Contract #09233004
Totals13998169.350.0012243562.4587.4

CountyJEFFERSON ETC
HighwayUS 90 ETC
FromLIBERTY COUNTY LINE
To0.38 MILES EAST OF FM 365(EB ONLY)
CSJ0028-06-088
Proj IDF 2025(102)
Work TypeSEAL COAT
 
90.8399870092.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-06-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243004
Totals9870092.800.000.000.0

CountyZERO COUNTIES
Highway
From
To
CSJ0028-11-210
Proj ID
Work Type
 
0.00307231.000.0
CountyORANGE
HighwayIH 10
FromAT LITTLE CYPRESS BAYOU
To(STR 002814069)AND(STR 002814068)
CSJ0028-14-100
Proj IDBR 2013(443)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1895064499.674796865.4594.7
CountyORANGE
HighwayIH 10
FromW OF ADAMS BAYOU, EAST
ToW OF SABINE RIVER BRIDGE
CSJ0028-14-108
Proj IDIM 0108(184)
Work TypeGR, STR, BS, PVMT, SIGN
 
3.66947282929.2547265377.8499.9
CountyORANGE
HighwayIH 10
FromAT SH 87 AND T&NO RR
To(STR 002814108 & 109)
CSJ0028-14-109
Proj IDBR 2013(226)
Work TypeGR, BS, PVMT & STR
 
0.32216093789.7832456510.9699.9
Work Order03-18-14
Work Began05-30-14
Work Completed
Time Computed04-03-14
Contract Working Days679
Addl Days Granted829
Working Days Charged1,061
Percent Time Used70
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-11-210
A-1 EROSION CONTROL, LLC (0.16)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.08)
AMERICAN REMEDIATION OPTIONS, INC. (0.16)
BORTUNCO (0.66)
DAVIS TREE EXPERTS (0.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.23)
MESA ROD BUSTERS, INC. (7.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.45)
SCOTT DERR PAINTING CO, LLC (0.05)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.80)
TRAF-TEX, INC. (0.97)
ROADWAY CONSTRUCTION, LLC (0.31)
C PAVE, INC. (0.01)
NORMAN HIGHWAY CONSTRUCTORS, INC. (0.46)
CRABTREE BARRICADE SYSTEMS, INC. (0.03)
JANCO (0.98)
ASHTON SAWING AND DRILLING LLC (0.05)
RAY"S THREADING AND FAB SHOP (0.71)
GULF COAST GROUTING, INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45)
URETEK USA, INC. (0.14)
SK CONCRETE SERVICES LLC (0.07)
BATTEN DRILLING, INC. (0.09)
Contract #02143032
Totals68441218.7017564.2684825985.2599.9

CountyJEFFERSON
HighwayIH 10
FromHOLLYWOOD OVERPASS, EAST
To7TH STREET
CSJ0028-13-135
Proj IDF 2024(979)
Work TypeWIDEN FREEWAY
 
2.456533247313.15105850272.7019.8
Work Order06-05-24
Work Began07-10-24
Work Completed
Time Computed07-10-24
Contract Working Days1,421
Addl Days Granted0
Working Days Charged25
Percent Time Used1
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-13-135
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.38)
AMERICAN REMEDIATION OPTIONS, INC. (0.35)
ROYAL REBAR (4.18)
BUYERS BARRICADES HOUSTON, LLC (0.15)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.08)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.43)
URETEK USA, INC. (0.01)
SK CONCRETE SERVICES LLC (0.09)
SCOTT DERR PAINTING CO, LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.45)
KAY SERVICES, INC. (0.01)
SWEEPING CORPORATION OF AMERICA, LLC (0.01)
TEXAS MATERIALS GROUP, INC. (0.00)
Contract #05243001
Totals533247313.15273572.70105850272.7019.8

CountyJEFFERSON
HighwayIH 10
FromUS 90, EAST
ToHOLLYWOOD OVERPASS
CSJ0028-13-139
Proj IDC 28-13-139
Work TypeWIDEN FREEWAY
 
0.4743040256.731404000.0046.1
CountyJEFFERSON
HighwayIH 10
FromCR 131 (WALDEN ROAD), EAST
ToUS 90
CSJ0739-02-140
Proj IDC 739-2-140
Work TypeWIDEN FREEWAY
 
2.455304203301.67122604276.5940.3
CountyZERO COUNTIES
Highway
From
To
CSJ0739-02-177
Proj ID
Work Type
 
0.003908774.520.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-22
Work Began04-14-22
Work Completed
Time Computed00-00-00
Contract Working Days1,569
Addl Days Granted273
Working Days Charged443
Percent Time Used24
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-13-139
LONG LEGACY ENTERPRISES, LLC (0.05)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.02)
FERGUSON WATERWORKS (0.15)
BUYERS BARRICADES HOUSTON, LLC (0.16)
AMERICAN REMEDIATION OPTIONS, INC. (0.22)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.65)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.87)
ROYAL REBAR (9.50)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.17)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
SCOTT DERR PAINTING CO, LLC (0.09)
BATTERSON, LLP (0.52)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.62)
BASE CONSTRUCTION L.L.P. (0.77)
SK CONCRETE SERVICES LLC (0.24)
TEXAS MATERIALS GROUP, INC. (0.03)
SUPERIOR GROUTING SERVICES, INC. (0.00)
Contract #03223001
Totals307243558.403521117.45127917051.1141.6

CountyORANGE
HighwayIH 10
From0.54 MILES EAST OF FM 3247
ToSABINE RIVER BRIDGE
CSJ0028-14-091
Proj IDNH 2020(966)
Work TypeWIDEN FREEWAY
 
4.18752363934.1740031628.5776.4
Work Order08-14-20
Work Began09-16-20
Work Completed
Time Computed09-16-20
Contract Working Days940
Addl Days Granted12
Working Days Charged691
Percent Time Used72
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-14-091
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.62)
MESA ROD BUSTERS, INC. (1.31)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.83)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
AREA WIDE PROTECTIVE, INC. (0.42)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.94)
AMERICAN REMEDIATION OPTIONS, INC. (0.44)
SCOTT DERR PAINTING CO, LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (1.44)
ADCOCK 4 INVESTMENTS, LLC (0.64)
RAY"S THREADING AND FAB SHOP (0.65)
LONG LEGACY ENTERPRISES, LLC (0.01)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.22)
SK CONCRETE SERVICES LLC (0.36)
BATTEN DRILLING, INC. (0.54)
TEXAS MATERIALS GROUP, INC. (0.06)
Contract #06203204
Totals52363934.17239399.4540031628.5776.4

CountyORANGE
HighwayIH 10
FromAT SABINE RIVER
To._(EAST BOUND)
CSJ0028-14-116
Proj IDBR 2022(535)
Work TypeBRIDGE MAINTENANCE
 
1.2312353381.87970785.2441.2
CountyORANGE
HighwayIH 10
FromAT SABINE RIVER
To. (WEST BOUND)
CSJ0028-14-117
Proj IDBR 2022(535)
Work TypeBRIDGE MAINTENANCE
 
1.2312388858.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-13-23
Work Began08-09-23
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged22
Percent Time Used21
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-14-116
TRP CONSTRUCTION GROUP, LLC (4.84)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (8.53)
BUYERS BARRICADES HOUSTON, LLC (0.65)
Contract #02233010
Totals4742240.620.00970785.2420.4

CountyHARDIN ETC
HighwayUS 96 ETC
FromAT BNSF RR (STR#20-101-0-0065-05-090)
To.(NORTHBOUND)
CSJ0065-05-156
Proj IDBR 2023(188)
Work TypeBRIDGE MAINTENANCE
 
1.1908587147.426703504.9578.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-12-23
Work Began05-15-23
Work Completed
Time Computed00-00-00
Contract Working Days343
Addl Days Granted0
Working Days Charged310
Percent Time Used90
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0065-05-156
FLYING C SERVICES (0.02)
TRAFFIC SIGNS & LINES, LLC (3.92)
ELEMENT REMEDIATION INC (6.48)
DUSTROL, INC. (0.34)
DEPENDABLE FENCE (2.36)
THE TRUESDELL CORPORATION (3.79)
RAILPROS FIELD SERVICES, INC. (0.03)
LEAH TRUCKING INCORPORATED (0.00)
Contract #11223005
Totals8587147.42229640.006703504.9578.0

CountyHARDIN ETC
HighwayUS 96 ETC
FromAT NERREN LN
To.
CSJ0065-05-158
Proj IDSTP 2024(953)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0961243703.57189735.1015.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-24
Work Began10-14-24
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged10
Percent Time Used8
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0065-05-158
SEMPER STRIPING LLC (1.40)
Contract #03243030
Totals1243703.57189735.10189735.1015.2

CountyHARDIN
HighwayUS 69
FromUS 69 Y IN LUMBERTON, SOUTH
ToJEFFERSON COUNTY LINE
CSJ0065-06-070
Proj IDC 65-6-70
Work TypeRESTORATION
 
2.8836064303.256506396.4099.9
CountyJEFFERSON
HighwayUS 69
FromJEFFERSON COUNTY LINE, SOUTH
ToTRAM ROAD
CSJ0065-07-070
Proj IDC 65-7-70
Work TypeRESTORATION
 
0.531814526.01862485.6299.9
CountyJEFFERSON
HighwayUS 69
FromLNVA CANAL, SOUTH
ToDELAWARE (NBFR & SBFR)
CSJ0200-11-099
Proj IDC 200-11-99
Work TypeOVERLAY
 
5616251.413721184.7766.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-26-23
Work Began05-29-23
Work Completed
Time Computed00-00-00
Contract Working Days131
Addl Days Granted0
Working Days Charged170
Percent Time Used129
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0065-06-070
BARRICADES UNLIMITED (0.24)
URETEK USA, INC. (0.40)
DUSTROL, INC. (0.58)
PENHALL COMPANY (6.61)
CPAVE, INC. (15.86)
TRP CONSTRUCTION GROUP, LLC (1.97)
THE TRUESDELL CORPORATION (12.38)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (6.52)
Contract #03233210
Totals12495080.671494779.1611090066.7989.1

CountyJEFFERSON
HighwayUS 69
FromTRAM ROAD, SOUTH
ToLNVA CANAL
CSJ0065-07-062
Proj IDNH 2019(818)
Work TypeWiden Freeway
 
2.27921735071.8524719394.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began07-16-19
Work Completed
Time Computed00-00-00
Contract Working Days412
Addl Days Granted241
Working Days Charged642
Percent Time Used98
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0065-07-062
CEN TEX HYDROSEED, INC. (0.36)
CRABTREE BARRICADE SYSTEMS, INC. (1.15)
AREA WIDE PROTECTIVE, INC. (0.22)
CREATIVE PAVING CONCEPTS, LLC (1.20)
INTECH CONTRACTING LLC (2.99)
THIRD COAST SERVICES LLC (3.87)
J & M CONTRACTING, COMPANY (5.63)
JOHN REED AND COMPANY, LLC (18.03)
MESA ROD BUSTERS, INC. (0.17)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.60)
MIK INDUSTRIAL, LLC (0.69)
TEXAS CUTTING & CORING GP, INC. (0.30)
CREACOM, INC. (0.38)
HOUSTON SAWING & DRILLING (0.01)
JB PINNACLE GROUP, LLC (0.17)
TEXAS MATERIALS GROUP, INC. (25.51)
HIGHWAY 1 LLC (0.11)
RAGLE CONSTRUCTION, INC. (1.87)
FARR FOUNDATION, INC. (0.32)
CPAVE, INC. (0.00)
PROFESSIONAL TRAFFIC CONTROL LLC (0.01)
Contract #04193009
Totals21735071.8577826.4524719394.1799.9

CountyLIBERTY
HighwayUS 59
FromSOUTH END OF CLEVELAND BYPASS
ToMONTGOMERY COUNTY LINE
CSJ0177-03-096
Proj IDNH 2012(594)
Work TypeGR, STR, BS, PVMT, SIGN, STRIPE
 
4.475100888506.74107185829.7799.9
CountyMONTGOMERY
HighwayIH 69
FromFOSTORIA ROAD, NORTH
ToLIBERTY COUNTY LINE
CSJ0177-05-113
Proj IDNH 2019(022)
Work TypeCONSTRUCT DETENTION POND
 
0.0811256328.451034482.2982.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began05-01-19
Work Completed
Time Computed00-00-00
Contract Working Days736
Addl Days Granted433
Working Days Charged1,125
Percent Time Used96
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0177-03-096
PRIMATE CONSTRUCTION, LP (0.25)
ATS DRILLING, INC. (4.05)
CREACOM, INC. (3.80)
J. H. ODEN CONTRACTING COMPANY (0.40)
DUSTROL, INC. (0.65)
WILLOW CITY SIGN & RAIL, INC. (0.66)
SCR CIVIL CONSTRUCTION, LLC (0.03)
BOWMAN ENGINEERING & CONSULTING, INC. (7.58)
PMI PAVEMENT MARKING, LLC (0.93)
SMITH & COMPANY (3.82)
EUBANK EXCAVATION, L.L.C. (0.22)
MCNORTON DEWATERING, INC. (0.05)
MEMCO (0.00)
TORO BRAVO CONSTRUCTION, LLC (6.89)
MTAM CORPORATION (0.06)
CURB PLANET INC. (0.00)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
CHERRY CRUSHED CONCRETE (0.21)
SCOTT DERR PAINTING CO, LLC (0.10)
SAPO ENGINEERING CONSULTANTS, LLC (0.22)
ANTIGO CONSTRUCTION, INC. (0.01)
WHITE STAR CONCRETE INC (0.01)
TEXAS WALL & LANDSCAPE (0.24)
A. H. BECK FOUNDATION CO., INC. (2.23)
TORO BRAVO CONSTRUCTION, LLC (0.18)
A.E.A. TRANSPORTATION (0.38)
B & D MAINTENANCE (0.90)
C.G. ANTHONY DELIVERIES, LLC (0.77)
BATTERSON, LLP (0.30)
AVILES CONSTRUCTION SERVICE, INC (0.19)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
AIMS COMPANIES (0.01)
Contract #09183201
Totals102144835.190.00108220312.0699.9

CountyTYLER
HighwayUS 69
From0.1 MI SOUTH OF BLACK CREEK
ToHARDIN COUNTY LINE
CSJ0200-08-049
Proj IDC 200-8-49
Work TypeWIDEN NON-FREEWAY
 
4.971198336383.1262223846.7131.3
CountyTYLER
HighwayUS 69
From0.1 MI SOUTH OF BLACK CREEK
ToHARDIN COUNTY LINE
CSJ0200-08-058
Proj IDROW 200-8-58
Work TypeRIGHT OF WAY
 
4220559.403208993.4476.0
CountyHARDIN
HighwayUS 69
FromTYLER COUNTY LINE
To0.75 MI SOUTH OF FM 1003
CSJ0200-09-075
Proj IDROW 200-9-75
Work TypeRIGHT OF WAY
 
4.9712859187.333623490.0099.9
Work Order10-25-23
Work Began12-19-23
Work Completed
Time Computed12-19-23
Contract Working Days705
Addl Days Granted0
Working Days Charged185
Percent Time Used26
Contractor(s)
PULICE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-08-049
LONG LEGACY ENTERPRISES, LLC (0.59)
G & T TRAFFIC SOLUTIONS, LLC (0.00)
PRIME TREES INC. (0.72)
CLEARVIEW CLEARING & SITE SERVICE, INC (0.21)
WAMPOLE MILLER, INC. (0.74)
EAS-TEX CONTRACTORS, INC. (0.00)
GEORGE MEEKS LANDPRO, INC. (0.00)
VALLEY PLACERS, LLC (0.12)
TEXAS STERLING CONSTRUCTION CO. (1.52)
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (0.12)
EAGLE CONSTRUCTION LLC (5.86)
QUALITY TURF FARMS, L.C. (0.73)
EASTEX UTILITY CONSTRUCTION, LLC (1.67)
WEBER-BALKE FOUNDATION COMPANY, INC (0.96)
ROYAL REBAR (0.75)
JOHN WRIGHT CONSTRUCTION (0.12)
EPCS ENVIRONMENTAL LLC (0.11)
C.E. YARBOROUGH, INC. (0.08)
Contract #09233001
Totals205416129.855825494.1669056330.1533.6

CountyJEFFERSON
HighwayUS 69
FromLNVA CANAL, SOUTH
ToIH 10
CSJ0200-11-095
Proj IDNH 1802(412)
Work TypeGR, BS, STR, PVMT
 
3.62431528539.2033758188.9199.9
Work Order08-15-18
Work Began10-14-18
Work Completed
Time Computed10-14-18
Contract Working Days652
Addl Days Granted45
Working Days Charged1,127
Percent Time Used161
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-11-095
HOUSTON SAWING & DRILLING (0.01)
APEX HIGHWAY SERVICES LLC (0.02)
DUSTROL, INC. (1.12)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.56)
CPAVE, INC. (0.69)
AMERICAN REMEDIATION OPTIONS, INC. (1.79)
NORMAN HIGHWAY CONSTRUCTORS, INC. (9.42)
WEBBER BARRIER SERVICES, LLC. (5.67)
W. W. FOUNDATION DRILLING, LTD. (1.61)
CRABTREE BARRICADE SYSTEMS, INC. (1.06)
(INACTIVE)MIRE TRUCKING & SERVICES (0.12)
HB FARMER FOUNDATION, LLC (1.61)
BREDA COMPANY, INC. (0.64)
AARON CONCRETE CONTRACTORS, L.P. (6.01)
ROYAL REBAR (0.30)
JOHN WRIGHT CONSTRUCTION (0.06)
BATTEN DRILLING, INC. (0.47)
TRICON PRECAST, LTD. (1.84)
PROFESSIONAL TRAFFIC CONTROL LLC (0.03)
Contract #07183004
Totals31528539.201423092.6733758188.9199.9

CountyJEFFERSON
HighwayUS 69
FromSS 93, SOUTH
ToSS 380
CSJ0200-14-093
Proj IDF 2022(893)
Work TypeREHABILITATION OF EXISTING ROAD
 
10175549.208188032.7180.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-22
Work Began11-21-22
Work Completed
Time Computed00-00-00
Contract Working Days279
Addl Days Granted52
Working Days Charged295
Percent Time Used89
Contractor(s)
ELITE CONTRACTORS AND EQUIPMENT LTD
SUBCONTRACTOR(S) FOR CCSJ: 0200-14-093
AMERICAN REMEDIATION OPTIONS, INC. (1.15)
PINNACLE GRINDING AND GROOVING LLC (0.80)
TEX-BRASKA, LLC (3.70)
AREA WIDE PROTECTIVE, INC. (1.11)
MASON CONSTRUCTION, LLC (0.58)
HOLES-GOLDEN TRIANGLE LLC (0.19)
TRP CONSTRUCTION GROUP, LLC (0.05)
HOLLIER CONSTRUCTION CO. (0.11)
Contract #08223214
Totals10175549.20308952.188188032.7180.6