Monthly State Let Construction Report For Beaumont District As Of Nov 10, 2024 Page 4 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARDIN
HighwayCR
FromCR 101 AT FLAT CYPRESS CREEK
To(STR 201010AA0101001)
CSJ0920-03-081
Proj IDBR 2021(530)
Work TypeBRIDGE REPLACEMENT
 
775736.54683306.3488.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-23
Work Began01-08-24
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged86
Percent Time Used114
Contractor(s)
C. E. BARKER, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-081
TSTAR DRILLING & SAWING INC (2.83)
BARRICADES UNLIMITED (0.70)
HEMPHILL WBE PILE DRIVING CO. (9.59)
SEMARCK LANDSCAPE SERVICES, INC. (0.64)
GUERRA CONCRETE CONTRACTORS, LLC (12.18)
HAZMAT INTERNATIONAL, INC. (3.40)
HOUSTON SAWING & DRILLING (0.42)
A1 EROSION CONTROL (0.25)
Contract #10233023
Totals775736.540.00683306.3488.9

CountyHARDIN ETC
HighwayCR ETC
FromW.PINESHADOWS @ CLEMMONS GULLY
ToSTR# 201010AA1065001
CSJ0920-03-082
Proj IDBR 2022(836)
Work TypeBRIDGE REPLACEMENT
 
0.7803831475.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days234
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-082
AWP SAFETY (2.88)
AMERICAN REMEDIATION OPTIONS, INC. (8.66)
HB FARMER FOUNDATION, LLC (19.24)
LONG LEGACY ENTERPRISES, LLC (0.18)
PRIMATE CONSTRUCTION, LP (0.42)
J & M CONSTRUCTION COMPANY (8.80)
KINGZ INDUSTRIAL LLC (3.60)
RAGLE CONSTRUCTION, INC. (3.06)
HIGHWAY 1 LLC (0.35)
Contract #05243232
Totals3831475.530.000.000.0

CountyNEWTON
HighwayCR
FromAT PLUM CREEK
ToSTR#201760AA0237002
CSJ0920-06-037
Proj IDBR 2023(927)
Work TypeBRIDGE REPLACEMENT
 
0.063720839.50711993.7398.7
CountyNEWTON
HighwayCR
FromAT SWINDLER CREEK
ToSTR#201760AA0210001
CSJ0920-06-039
Proj IDBR 2023(960)
Work TypeBRIDGE REPLACEMENT
 
0.069776226.50766087.5998.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-23
Work Began10-19-23
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged107
Percent Time Used89
Contractor(s)
RAYFORD'S TRUCK & TRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-037
CAP RIVER LLC (0.42)
CARTHAGE DRILLING, LLC (8.21)
LONESTAR TRAFFIC SAFETY, LLC (0.46)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.87)
PENHALL COMPANY (0.40)
Contract #08233249
Totals1497066.000.001478081.3298.7

CountyJASPER
HighwayVA
FromON FM 2799 FROM MAIN ST.
ToPARK LANE
CSJ0920-12-047
Proj IDSTP 2021(242)SRS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1396803.751429496.0899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-27-23
Work Began05-08-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged114
Percent Time Used95
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-12-047
TRAFFIC SIGNS & LINES, LLC (3.82)
SETX PAVING, LLC (1.92)
Contract #11223017
Totals1396803.750.001429496.0899.9

CountyJASPER
HighwayCS
FromUS 190 (W. GIBSON STREET), NORTH
ToFM 2799 (W. HOUSTON STREET)
CSJ0920-12-048
Proj IDSTP 2022(737)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.934619481.50715801.2399.9
Work Order08-03-23
Work Began09-02-23
Work Completed
Time Computed09-02-23
Contract Working Days41
Addl Days Granted13
Working Days Charged54
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-12-048
CLASSIC TEJAS CONSTRUCTION, INC. (3.38)
Contract #06233637
Totals619481.500.00715801.2399.9

CountyTYLER
HighwayVA
FromUS HIGHWAY 190 TO DOGWOOD STREET, AND
ToUS 69 TO ALLAN SHIVERS LIBRARY AND MUSEU
CSJ0920-13-040
Proj IDSTP 2023(148)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
262629.95327428.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-09-23
Work Began01-04-24
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged9
Percent Time Used40
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-13-040
HIGHWAY 1 LLC (1.36)
FLEX SUPPLY, LLC (3.10)
Contract #06233254
Totals262629.951750.00327428.5899.9

CountyORANGE
HighwayCS
FromAT DRAINAGE DITCH
ToSTR#201810C01835003
CSJ0920-30-093
Proj IDBR 2023(124)
Work TypeBRIDGE REPLACEMENT
 
0.046601425.00644851.0999.9
Work Order04-26-23
Work Began05-26-23
Work Completed
Time Computed07-10-23
Contract Working Days46
Addl Days Granted0
Working Days Charged61
Percent Time Used132
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-093
ODUM SERVICES, LLC (2.37)
NEXAS SUPPLY LLC (14.39)
DCC CONSTRUCTION AND SERVICES, L.L.C. (1.66)
INTERSTATE BARRICADES & MARKINGS, INC. (2.09)
COWBOY ASPHALT SERVICES LLC (4.15)
Contract #03233037
Totals601425.000.00644851.0999.9

CountyJEFFERSON
HighwayCS
FromN 14TH STREET
ToMAIN STREET
CSJ0920-38-279
Proj IDSTP 2023(888)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.000373555.00437185.2599.9
CountyJEFFERSON
HighwayCS
FromEASTEX FREEWAY SB
ToBIGNER ROAD
CSJ0920-38-283
Proj IDSTP 2023(888)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.000181225.00144980.0080.0
CountyJEFFERSON
HighwayCS
FromELEVENTH STREET
ToMLK PARKWAY
CSJ0920-38-285
Proj IDSTP 2023(888)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.500362450.00326205.0090.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-23
Work Began11-27-23
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged33
Percent Time Used67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-279
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233031
Totals917230.000.00908370.2599.0

CountyJEFFERSON
HighwayFM 365
FromAT CENTRAL MALL DRIVE
To.
CSJ0932-01-118
Proj IDSTP 2023(582)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200320758.82324423.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-23
Work Began11-13-23
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0932-01-118
BARRICADES UNLIMITED (0.57)
Contract #04233237
Totals320758.820.00324423.1099.9

CountyJEFFERSON
HighwayFM 365
FromFM 1406, EAST
ToIH 10
CSJ0932-02-044
Proj IDF 2B23(154)
Work TypeWIDEN NON-FREEWAY
 
8.6097997540.617326815.6091.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began12-05-23
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged141
Percent Time Used94
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-044
CPAVE, INC. (1.28)
BATTERSON, LLP (2.11)
PROFESSIONAL TRAFFIC CONTROL LLC (0.23)
HIGHWAY 1 LLC (0.24)
ODUM SERVICES, LLC (1.78)
J & M CONTRACTING, COMPANY (4.74)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95)
Contract #08233223
Totals7997540.6159885.057326815.6091.6

CountyJEFFERSON
HighwayFM 365
FromAT PIGNUT GULLY
ToSTR 20-124-0-0932-02-003
CSJ0932-02-052
Proj IDBR 2021(293)
Work TypeBRIDGE REPLACEMENT
 
0.005959967.411006979.8999.9
CountyJEFFERSON
HighwayFM 365
FromAT DRAINAGE DITCH
ToSTR 20-124-0-0932-02-002
CSJ0932-02-056
Proj IDBR 2021(293)
Work TypeBRIDGE REPLACEMENT
 
0.005987344.681193339.5499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-23-22
Work Began04-25-22
Work Completed
Time Computed00-00-00
Contract Working Days195
Addl Days Granted0
Working Days Charged312
Percent Time Used160
Contractor(s)
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-052
TRAFFIC SIGNS & LINES, LLC (7.94)
HOLES-GOLDEN TRIANGLE LLC (2.69)
HERMANOS STEEL, LLC (0.57)
HOUSTON SAWING & DRILLING (0.26)
AMERICAN PARKING CONTROL (2.25)
AVILES CONSTRUCTION SERVICE, INC (6.11)
FITTZ & SHIPMAN (1.54)
TNT CRANE & RIGGING, INC. (0.76)
SEMARCK LANDSCAPE SERVICES, INC. (0.26)
GMJ PAVING COMPANY LLC (1.12)
Contract #02223217
Totals1947312.09222323.452200319.4399.9

CountyLIBERTY
HighwaySH 105
FromWEST END OF TRINITY RIVER BRIDGE, EAST
ToSH 146
CSJ0951-01-068
Proj IDF 2023(742)
Work TypeOVERLAY
 
4.2801980516.242278703.9799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-23
Work Began07-24-23
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted30
Working Days Charged79
Percent Time Used97
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0951-01-068
TRAFFIC SIGNS & LINES, LLC (0.32)
WILLOW CITY SIGN & RAIL, INC. (2.58)
USA AMTECH, INC. (0.43)
CEN TEX HYDROSEED, INC. (0.94)
SEMPER STRIPING LLC (1.65)
CPAVE, INC. (0.31)
Contract #05233027
Totals1980516.240.002278703.9799.9

CountyLIBERTY
HighwayFM 1008
FromARNOLD DRIVE(PARK ROAD), SOUTH
ToSH 321
CSJ0952-01-062
Proj IDF 2024(810)
Work TypeOVERLAY
 
2.7542261889.842096334.8492.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-11-24
Work Began05-06-24
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged68
Percent Time Used109
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0952-01-062
WILLOW CITY SIGN & RAIL, INC. (1.13)
SEMPER STRIPING LLC (3.83)
H J HENKE, LLC (2.62)
KINGZ INDUSTRIAL LLC (2.51)
PROFESSIONAL TRAFFIC CONTROL LLC (0.30)
A.J.J.A . TRUCKING, INC. (3.40)
Contract #03243213
Totals2261889.84144610.452096334.8492.9

CountyLIBERTY
HighwayFM 1008
From0.02 MI SOUTH OF CR 631, SOUTH
To0.05 MI SOUTH OF BOWIE CREEK
CSJ0952-01-064
Proj IDSTP 2B24(521)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.230246817.250.000.0
CountyLIBERTY
HighwayFM 1008
From0.3 MI N OF HILLCREST
To0.1 MI N OF HILLCREST
CSJ0952-01-069
Proj IDSTP 2025(090)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200149274.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-31-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0952-01-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243240
Totals396091.750.000.000.0

CountyCHAMBERS
HighwayFM 562
FromAT LONE OAK BAYOU
To(STR 200360102201006)
CSJ1022-01-034
Proj IDBR 2021(469)
Work TypeBRIDGE REPLACEMENT
 
0.0111598096.253560964.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-17-21
Work Began02-01-22
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted175
Working Days Charged359
Percent Time Used109
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1022-01-034
AREA WIDE PROTECTIVE, INC. (4.64)
TOM-MAC, INC. (12.39)
INTERSTATE BARRICADES & MARKINGS, INC. (1.77)
GMJ PAVING CO. (11.04)
HOUSTON SAWING & DRILLING (0.37)
Contract #10213012
Totals1598096.2554759.223560964.6299.9

CountyCHAMBERS
HighwayFM 1405
From0.10 MILES NORTH OF CEDAR BLVD., SOUTH
To0.10 MILES SOUTH OF CEDAR BLVD.
CSJ1024-02-049
Proj IDSTP 2022(441)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20059901.9472686.2899.9
CountyLIBERTY
HighwayFM 2797
FromAT FM 1008
To.
CSJ2780-01-010
Proj IDSTP 2022(441)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
41207.9453665.7299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-22
Work Began12-06-22
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged18
Percent Time Used72
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1024-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223026
Totals101109.886130.74126352.0099.9

CountyHARDIN
HighwayFM 770
FromFM 1003, SOUTH
ToLITTLE PINE ISLAND BAYOU
CSJ1096-01-068
Proj IDF 2024(036)
Work TypeOVERLAY
 
8.2354123742.902904087.5170.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-12-23
Work Began04-01-24
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged71
Percent Time Used80
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1096-01-068
MURRAY CONSTRUCTION (1.02)
PROFESSIONAL TRAFFIC CONTROL LLC (0.17)
J & M CONTRACTING, COMPANY (10.98)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.05)
SUPERIOR TRAFFIC CONTROL, LLC (0.20)
BATTERSON, LLP (4.93)
AWP SAFETY (0.08)
Contract #09233009
Totals4123742.9016263.502904087.5170.4

CountyLIBERTY
HighwayFM 770
FromAT LONG ISLAND CREEK
To(STR 201460109602014)
CSJ1096-02-051
Proj IDBR 2022(174)
Work TypeBRIDGE REPLACEMENT
 
0.1122189483.882051750.2699.9
CountyLIBERTY
HighwayFM 770
From@ WHITES BAYOU
To(STR 201460109602015)
CSJ1096-02-052
Proj IDBR 2022(175)
Work TypeBRIDGE REPLACEMENT
 
0.1212311039.82341835.7614.7
CountyLIBERTY
HighwayFM 770
From@ WEST END SLOUGH
ToSTR #201460109602013
CSJ1096-02-054
Proj IDBR 2022(176)
Work TypeBRIDGE REPLACEMENT
 
0.1221383007.761342617.0597.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-22
Work Began04-28-22
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted18
Working Days Charged387
Percent Time Used159
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1096-02-051
J & M CONSTRUCTION COMPANY (1.34)
HOUSTON SAWING & DRILLING (0.24)
DUSTROL, INC. (1.61)
BARRICADES UNLIMITED (3.05)
AMERICAN REMEDIATION OPTIONS, INC. (5.69)
TRP CONSTRUCTION GROUP, LLC (1.79)
HB FARMER FOUNDATION, LLC (16.33)
J & M CONTRACTING, COMPANY (1.34)
Contract #12213016
Totals5883531.46147679.023736203.0766.2

CountyJASPER
HighwayFM 777
From5 MILES S OF US 190 AT AIRPORT, NORTH
ToUS 190 AT AIRPORT
CSJ1109-01-022
Proj IDC 1109-1-22
Work TypeRESTORATION
 
5.0009949305.550.000.0
CountyJASPER
HighwayFM 777
From@ BIG WALNUT RUN
ToSTR#201220110901003
CSJ1109-01-026
Proj IDBR 2024(854)
Work TypeBRIDGE REPLACEMENT
 
0.0401543829.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-24
Work Began10-19-24
Work Completed
Time Computed00-00-00
Contract Working Days147
Addl Days Granted0
Working Days Charged5
Percent Time Used3
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1109-01-022
AMERICAN REMEDIATION OPTIONS, INC. (2.67)
HIGHWAY 1 LLC (1.21)
KINGZ INDUSTRIAL LLC (0.72)
LONG LEGACY ENTERPRISES, LLC (4.47)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.41)
NORMAN HIGHWAY CONSTRUCTORS, INC. (6.15)
PRIMATE CONSTRUCTION, LP (0.04)
PROFESSIONAL TRAFFIC CONTROL LLC (0.09)
Contract #04243207
Totals11493135.200.000.000.0

CountyLIBERTY
HighwayFM 834
FromSH 146, EAST
ToFM 770
CSJ1146-01-029
Proj IDSTP 2023(583)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.0354870507.635102358.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-23
Work Began06-19-23
Work Completed
Time Computed00-00-00
Contract Working Days188
Addl Days Granted0
Working Days Charged152
Percent Time Used80
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1146-01-029
TRAFFIC SIGNS & LINES, LLC (0.31)
AMERICAN REMEDIATION OPTIONS, INC. (4.82)
H J HENKE, LLC (2.19)
THIRD COAST SERVICES LLC (0.10)
USA AMTECH, INC. (0.35)
BATTERSON, LLP (1.49)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC (0.65)
Contract #04233214
Totals4870507.6344592.245102358.4099.9

page 1 | page 2 | page 3 | page 4 | page 5