Monthly State Let Maintenance Report For Beaumont District As Of Apr 14, 2021 Page 5 Of 5

Last Update: Wednesday, April 14, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJASPER
HighwayUS0190
FromJASPER AND NEWTON
ToMAINTENANCE YARDS
CSJ6372-34-001
Proj IDMMC - 637234001
Work TypeLIMESTONE ROCK ASPHALT MATERIALS ONLY
 
1.000549132.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6372-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214002
Totals549132.000.000.000.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6373-66-001
Proj IDRMC - 637366001
Work TypeDISTRICTWIDE SWEEPING_& DEBRIS REMOVAL
 
0.100626968.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SWEEPING CORPORATION OF AMERICA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214205
Totals626968.650.000.000.0

CountyCHAMBERS
HighwayFM1985
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6375-23-001
Proj IDRMC - 637523001
Work TypePAVEMENT MARKINGS
 
0.010486521.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214007
Totals486521.230.000.000.0

CountyHARDIN
HighwayFM1003
FromFM 1293
ToFM 770
CSJ6375-62-001
Proj IDMMC - 637562001
Work TypeHOT MIX (MATERIAL ONLY)
 
0.010763250.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214008
Totals763250.000.000.000.0

CountyJASPER
HighwayFM0082
FromEND OF MAINTENANCE
ToUS0096
CSJ6376-12-001
Proj IDRMC - 637612001
Work TypeRAISED PAVEMENT MARKINGS
 
0.0102271663.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days294
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04214003
Totals2271663.830.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5