Monthly Local Let Maintenance Report For Bryan District As Of Sep 15, 2016 Page 11 Of 11
Last Update: Thursday, September 15, 2016
|
|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | WASHINGTON |
| Highway |
SH0105 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6309-25-001 |
| Proj ID |
SUP - 630925001 |
| Work Type |
REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES |
| |
|
0.010 |
72981.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-13-16 |
| Work Began |
09-13-16 |
| Work Completed |
|
| Time Computed |
09-13-16 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08161734 |
|
Totals |
72981.00 |
0.00 |
0.00 |
0.0 |
|
| County | BURLESON |
| Highway |
FM0050 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6309-26-001 |
| Proj ID |
SUP - 630926001 |
| Work Type |
PICNIC / CAR POOL MAINT IN BURLESON COUNTY |
| |
|
0.001 |
32332.32 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-02-16 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-02-16 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08161735 |
|
Totals |
32332.32 |
0.00 |
0.00 |
0.0 |
|
| County | LEON |
| Highway |
US0079 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6309-27-001 |
| Proj ID |
SUP - 630927001 |
| Work Type |
PICNIC AREA MAINTENANCE FOR LEON COUNTY |
| |
|
0.001 |
38028.24 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-02-16 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-02-16 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08161736 |
|
Totals |
38028.24 |
0.00 |
0.00 |
0.0 |
|