|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | PARKER |
| Highway |
FM 3028 |
| From |
FM 3028 AT ROCKY CREEK |
| To |
. |
| CSJ |
2930-02-011 |
| Proj ID |
BR 1502(336) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.100 |
1561559.71 |
61333.92 |
697243.40 |
44.6 |
| Work Order |
08-13-15 |
| Work Began |
09-22-15 |
| Work Completed |
|
| Time Computed |
09-12-15 |
| Contract Working Days |
130 |
| Addl Days Granted |
0 |
| Working Days Charged |
92 |
| Percent Time Used |
70 |
| Contractor(s) |
| PIERCE CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2930-02-011 WOLFE CONSTRUCTION GROUP, INC. (0.47%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.95%) STORM WATER MANAGEMENT, INC. (0.55%) ALTUS TRAFFIC MANAGEMENT LLC (0.37%) PEACHTREE CONSTRUCTION, LTD. (3.78%) FORTSON CONTRACTING, INC.(2.02%) TEXOP CONSTRUCTION (0.47%) STRIPING TECHNOLOGY, L.P.(0.47%)
|
| Contract # |
06153053 |
|
Totals |
1561559.71 |
61333.92 |
697243.40 |
44.6 |
|
| County | JOHNSON |
| Highway |
FM 2738 |
| From |
TARRANT COUNTY LINE |
| To |
FM-2738 IN LILLIAN |
| CSJ |
3010-02-013 |
| Proj ID |
STP 2014(940) |
| Work Type |
SEAL COAT AND OVERLAY |
| |
|
5.196 |
1757389.22 |
0.00 |
1733198.02 |
100.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-13-14 |
| Work Began |
04-13-15 |
| Work Completed |
10-05-15 |
| Time Computed |
08-29-14 |
| Contract Working Days |
85 |
| Addl Days Granted |
0 |
| Working Days Charged |
88 |
| Percent Time Used |
103 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3010-02-013 DUSTROL, INC.(2.94%) STRIPING TECHNOLOGY, L.P.(3.59%) VANN/ELLI, INC.(3.26%) WOLFE CONSTRUCTION GROUP, INC. (0.20%) CROSSROADS, L.P. (0.56%)
|
| Contract # |
06143249 |
|
Totals |
1757389.22 |
0.00 |
1733198.02 |
100.0 |
|
| County | JOHNSON |
| Highway |
FM 3136 |
| From |
5.213 MILES EAST OF FM 4 |
| To |
10.343 MILES EAST OF FM 4 |
| CSJ |
3348-01-019 |
| Proj ID |
STP 1502(549)HES |
| Work Type |
GR, BS, DR, STR, & PAVT |
| |
|
5.192 |
6829235.17 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-28-16 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
384 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3348-01-019 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01163018 |
|
Totals |
6829235.17 |
0.00 |
0.00 |
0.0 |
|
| County | JOHNSON |
| Highway |
FM 3391 |
| From |
AT STONE ROAD |
| To |
IN BURLESON |
| CSJ |
3372-01-014 |
| Proj ID |
CC 3372-1-14 |
| Work Type |
TRAFFIC SIGNAL INSTALLATION |
| |
|
0.123 |
137750.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-16-16 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURABLE SPECIALTIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3372-01-014 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10153027 |
|
Totals |
137750.00 |
0.00 |
0.00 |
0.0 |
|
| County | PARKER |
| Highway |
FM 3325 |
| From |
IH 20 |
| To |
FM 1886 |
| CSJ |
3516-01-015 |
| Proj ID |
STP 2013(675) |
| Work Type |
GR, BS, DR, STRUC AND PAVEMENT |
| |
|
7.160 |
3283284.20 |
0.00 |
3220075.53 |
99.9 |
| Work Order |
01-06-14 |
| Work Began |
01-28-14 |
| Work Completed |
|
| Time Computed |
01-22-14 |
| Contract Working Days |
256 |
| Addl Days Granted |
64 |
| Working Days Charged |
381 |
| Percent Time Used |
119 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 3516-01-015 RAMBO CONTRACTING, INC.(1.36%) INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.40%) SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%) NORTHEASTERN PAVERS, INC.( 37.58%) STRIPING TECHNOLOGY, L.P.(1.71%) JM MATERIALS, INC. (2.37%) TEXAS ALTERNATIVE GRASSER, INC.(0.71%) ODUM SERVICES, L.P.(0.87%) ENVIRONMENTAL SAFETY SERVICES, INC.(0.91%)
|
| Contract # |
08133054 |
|
Totals |
3283284.20 |
0.00 |
3220075.53 |
99.9 |
|