Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 11 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayFM 865
From0.1 MI N OF WILMINGTON ST
To0.1 MI S OF WILMINGTON ST
CSJ0976-01-045
Proj IDSTP 2022(931)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.400518221.94436356.4184.2
Work Order09-15-22
Work Began08-08-24
Work Completed
Time Computed01-13-23
Contract Working Days60
Addl Days Granted0
Working Days Charged46
Percent Time Used76
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-045
LONESTAR TRAFFIC SAFETY, LLC (0.28)
MULHOLLAND ENERGY SERVICES, LLC (0.49)
Contract #08223246
Totals518221.9488778.80436356.4184.2

CountyBRAZORIA
HighwayFM 518
FromAT LIBERTY DRIVE
To.
CSJ0976-02-095
Proj IDSTP 2021(839)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200246128.62256068.8999.9
Work Order09-20-21
Work Began03-28-24
Work Completed
Time Computed01-18-22
Contract Working Days54
Addl Days Granted0
Working Days Charged21
Percent Time Used38
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-02-095
HYDROMAX, LLC (4.19)
Contract #08213060
Totals246128.620.00256068.8999.9

CountyGALVESTON
HighwayFM 518
FromIH 45
ToFM 270
CSJ0976-03-105
Proj IDC 976-3-105
Work TypeOVERLAY
 
2.7615323154.934029994.0276.1
Work Order10-06-21
Work Began03-28-22
Work Completed
Time Computed01-04-22
Contract Working Days150
Addl Days Granted0
Working Days Charged172
Percent Time Used114
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-105
STRIPE LINES, INC. (2.53)
THIRD COAST SERVICES LLC (15.28)
Contract #03213208
Totals5323154.9350921.664029994.0276.1

CountyGALVESTON
HighwayFM 518
FromPALOMINO LANE
ToWILLIAMSPORT STREET
CSJ0976-03-109
Proj IDCM 2023(589)
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
15447120.447863321.6250.9
Work Order02-15-24
Work Began03-08-24
Work Completed
Time Computed03-16-24
Contract Working Days315
Addl Days Granted0
Working Days Charged106
Percent Time Used33
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-109
D. SOLIS TRUCKING, INC. (0.67)
THIRD COAST SERVICES LLC (0.85)
A. SANCHEZ TRUCKING (0.51)
C & C TRAFFIC CONTROL (0.14)
PRV SERVICES, INC. (0.16)
STRIPE LINES, INC. (2.39)
MONTALVO BRIDGE SYSTEMS, LLC (0.12)
SPECIALTY DRILLING, LLC (1.07)
SEMARCK LANDSCAPE SERVICES, INC. (0.61)
SPECIALIZED MAINTENANCE SERVICES, INC. (0.03)
WILLOW CITY SIGN & RAIL, INC. (0.29)
Contract #01243005
Totals15447120.4452146.227863321.6250.9

CountyGALVESTON
HighwayFM 518
FromFM 2351
ToS OF WHISPERING PINES
CSJ0976-03-111
Proj IDSTP 2021(344)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.3752774405.082964262.7399.9
CountyGALVESTON
HighwayFM 518
FromFM 2351
ToS OF WHISPERING PINES
CSJ0976-03-114
Proj IDROW 976-3-111
Work TypeRIGHT OF WAY
 
1.3753570.001200.0033.6
Work Order03-12-21
Work Began07-29-21
Work Completed
Time Computed04-11-21
Contract Working Days180
Addl Days Granted48
Working Days Charged201
Percent Time Used88
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-111
BROCK CONSTRUCTION, LLC (0.87)
CITYLYNX, INC. (42.71)
PBJ CONSTRUCTION (0.00)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
STRIPE LINES, INC. (1.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.09)
W.A. ROBBINS CONSTRUCTION CO., INC. (4.72)
PAVELOC INDUSTRIES LLC (4.09)
TOMMY"S UTILITY SERVICES (2.51)
SELRICO COMMUNICATIONS (0.50)
Contract #02213211
Totals2777975.080.002965462.7399.9

CountyGALVESTON ETC
HighwayFM 518 ETC
FromRIVERSIDE DRIVE
ToEAGLE LAKES DRIVE
CSJ0976-03-116
Proj IDC 976-3-116
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
19.5853312178.672317353.7869.9
Work Order07-26-23
Work Began01-30-24
Work Completed
Time Computed08-25-23
Contract Working Days105
Addl Days Granted4
Working Days Charged104
Percent Time Used95
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-116
D. L. MEACHAM CONSTRUCTION CO. (23.83)
ALL ACCESS TRAFFIX LIMITED LIABILITY COMPANY (1.49)
R & A DIRECTIONAL BORING (0.71)
HARDMAN SIGNS, LP (9.33)
FRANK FIFER ENTERPRISES INC. (0.23)
BILL HOUSTON CONCRETE CONSTRUCTION, INC. (0.94)
PFEIFFER & SON LTD. (1.94)
ZAMCO DIRECTIONAL DRILLING LLC (0.17)
Contract #06233628
Totals3312178.6749992.312317353.7869.9

CountyGALVESTON
HighwaySH 96
FromE OF SH 3
ToSH 146
CSJ0976-07-016
Proj IDC 976-7-16
Work TypeOVERLAY
 
4.4787736540.026469739.0183.6
Work Order03-08-23
Work Began05-15-23
Work Completed
Time Computed05-01-23
Contract Working Days211
Addl Days Granted0
Working Days Charged116
Percent Time Used54
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-07-016
INTERSTATE BARRICADES & MARKINGS, INC. (0.18)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.32)
THIRD COAST SERVICES LLC (1.23)
PROFESSIONAL TRAFFIC CONTROL LLC (0.07)
TRAFFIC SIGNS & LINES, LLC (0.14)
STRIPE LINES, INC. (5.08)
Contract #02233213
Totals7736540.020.006469739.0183.6

CountyGALVESTON
HighwaySH 96 ETC
FromIH 45
ToSH 146
CSJ0976-07-018
Proj IDF 2023(751)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
12.6312212100.331677929.6375.8
Work Order06-14-23
Work Began08-04-23
Work Completed
Time Computed07-14-23
Contract Working Days105
Addl Days Granted0
Working Days Charged94
Percent Time Used89
Contractor(s)
GREEN SAGE SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0976-07-018
R & A DIRECTIONAL BORING (4.14)
TRAFFIC SIGNS & LINES, LLC (0.58)
SPECIALTY DRILLING, LLC (7.54)
Contract #05233035
Totals2212100.330.001677929.6375.8

CountyGALVESTON
HighwayFM 517
FromFM 646
ToIH 45
CSJ0978-01-039
Proj IDC 978-1-39
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.880519798.14470264.5090.4
Work Order01-04-24
Work Began01-31-24
Work Completed
Time Computed02-03-24
Contract Working Days120
Addl Days Granted0
Working Days Charged84
Percent Time Used70
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-01-039
CURB PLANET INC. (1.43)
PROFESSIONAL TRAFFIC CONTROL LLC (10.13)
AWP SAFETY (0.97)
Contract #12233212
Totals519798.140.00470264.5090.4

CountyGALVESTON
HighwayFM 519
FromALONG FM 519, FROM IH 45
ToSH 3
CSJ0979-01-027
Proj IDSTP 2B23(207)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.7353290125.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed10-30-24
Contract Working Days158
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0979-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243231
Totals3290125.340.000.000.0

CountyGALVESTON
HighwayFM 519
FromIH 45
ToSH 3
CSJ0979-01-029
Proj IDSTP 2024(521)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.033411474.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed12-17-24
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0979-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243034
Totals411474.510.000.000.0

CountyHARRIS
HighwayFM 2100
FromHUFFMAN-CLEVELAND RD (NORTH)
ToFM 1960
CSJ1062-02-009
Proj IDF 2021(840)
Work TypeWIDEN NON-FREEWAY
 
4.42854799229.7834654965.0863.2
Work Order09-16-21
Work Began02-07-22
Work Completed
Time Computed12-15-21
Contract Working Days651
Addl Days Granted507
Working Days Charged677
Percent Time Used58
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-009
BUYERS BARRICADES, INC. (0.00)
WILLIAMS ROAD, LLC (0.20)
CITYLYNX, INC. (1.63)
GMJ PAVING COMPANY LLC (2.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.45)
GMJ PAVING CO. (2.05)
PROFESSIONAL TRAFFIC CONTROL LLC (0.32)
BUYERS BARRICADES HOUSTON, LLC (0.04)
CURB PLANET INC. (0.11)
SCOTT DERR PAINTING CO, LLC (0.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.25)
WASTE PARTNERS OF TEXAS, INC (0.05)
HERMANOS STEEL, LLC (5.00)
HB FARMER FOUNDATION, LLC (3.64)
PRIMATE CONSTRUCTION, LP (0.15)
JB PINNACLE GROUP, LLC (2.43)
BTM SERVICES, LLC (0.29)
MESA ROD BUSTERS, INC. (0.25)
THOMAS TRACTOR WORKS, INC. (0.67)
J & D TEX SERV, INCORPORATED (0.27)
Contract #08213203
Totals54799229.78641375.8334654965.0863.2

CountyHARRIS
HighwayFM 2100
From0.23 MI S OF ANTELOPE DR
ToFM 1960
CSJ1062-04-058
Proj IDNH 1902(182)
Work TypeWNF
 
2.94925495057.2632243097.3299.9
Work Order10-25-19
Work Began01-13-20
Work Completed
Time Computed01-23-20
Contract Working Days331
Addl Days Granted180
Working Days Charged321
Percent Time Used62
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-058
CLEARVIEW CLEARING & SITE SERVICE, INC (0.37)
GMJ PAVING CO. (4.35)
PRV SERVICES, INC. (0.19)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.67)
D. SOLIS TRUCKING, INC. (0.09)
PROFESSIONAL TRAFFIC CONTROL LLC (1.18)
MONTALVO BRIDGE SYSTEMS, LLC (0.95)
THIRD COAST SERVICES LLC (4.03)
CURB PLANET INC. (0.06)
HIGHWAY 1 LLC (0.21)
C & C TRAFFIC CONTROL (0.03)
TEXOP CONSTRUCTION (0.03)
MORAN CONSTRUCTION, LLC (0.87)
BELLA PAVING, INC. (0.29)
WILLOW CITY SIGN & RAIL, INC. (0.35)
RAILPROS FIELD SERVICES, INC. (0.03)
MASTERPIECE GRINDING & GROOVING, LLC (0.26)
TRAFFIC SIGNS & LINES, LLC (0.03)
SEMARCK LANDSCAPE SERVICES, INC. (0.32)
MAIN LANE INDUSTRIES LTD. (0.03)
RAC INDUSTRIES, LLC (0.18)
Contract #07193004
Totals25495057.26866645.5932243097.3299.9

CountyHARRIS
HighwayFM 1093
FromSOUTH KIRKWOOD ROAD
ToWESTERLAND DRIVE
CSJ1258-04-065
Proj IDSTP 2017(976)TP
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
3.56412691072.7911733187.1692.4
Work Order11-04-19
Work Began02-24-20
Work Completed
Time Computed03-03-20
Contract Working Days850
Addl Days Granted0
Working Days Charged838
Percent Time Used98
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-065
GEORGE MEEKS LANDPRO, INC. (6.25)
RAY"S THREADING AND FAB SHOP (0.70)
PROFESSIONAL TRAFFIC CONTROL LLC (2.29)
TEXAS WALL & LANDSCAPE (14.79)
THIRD COAST SERVICES LLC (30.90)
DOUBLE OAK EROSION, INC. (0.76)
CHERRY CRUSHED CONCRETE (0.59)
MVA CONSTRUCTION LLC (0.74)
BOOT CONSTRUCTION, LLC (0.16)
717 CONSTRUCTION SERVICES, LLC (5.32)
ZAMCO DIRECTIONAL DRILLING LLC (0.33)
MICKIE SERVICE, INC. (0.24)
GMJ PAVING COMPANY LLC (0.52)
Contract #09193206
Totals12691072.7924746.0411733187.1692.4

CountyMONTGOMERY
HighwayFM 1097
FromLAKE CONROE HILLS
ToANDERSON ROAD
CSJ1259-01-043
Proj IDSTP 2020(790)
Work TypeWIDEN NON-FREEWAY
 
2.00014690168.2816644644.2799.9
Work Order12-04-20
Work Began02-02-21
Work Completed
Time Computed02-02-21
Contract Working Days334
Addl Days Granted124
Working Days Charged394
Percent Time Used86
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-043
TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.41)
LONESTAR TRAFFIC SAFETY, LLC (0.17)
WILLOW CITY SIGN & RAIL, INC. (0.61)
CEN TEX HYDROSEED, INC. (0.49)
HIGHWAY 1 LLC (1.11)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.82)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33)
DUSTROL, INC. (1.22)
MESA ROD BUSTERS, INC. (5.80)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.11)
ROSALES TRUCKING (5.12)
ANCORTEX, INC. (0.45)
B & D MAINTENANCE (4.24)
AVILES CONSTRUCTION SERVICE, INC (2.56)
SOUTHEAST GRINDING AND GROOVING LLC (0.10)
CURB PLANET INC. (0.02)
CEDAR HILL SERVICES, LLC (0.01)
BUYERS BARRICADES HOUSTON, LLC (0.12)
Contract #10203003
Totals14690168.280.0016644644.2799.9

CountyMONTGOMERY
HighwayFM 1097
FromWEST OF BLUEBERRY HILLS RD
ToLAKE CONROE HILLS DR
CSJ1259-01-044
Proj IDF 2021(653)
Work TypeWIDEN NON-FREEWAY
 
1.52416095270.6613137755.6381.6
Work Order09-21-21
Work Began01-19-22
Work Completed
Time Computed01-19-22
Contract Working Days328
Addl Days Granted68
Working Days Charged395
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-044
CEN TEX HYDROSEED, INC. (0.54)
LONESTAR TRAFFIC SAFETY, LLC (0.16)
WILLOW CITY SIGN & RAIL, INC. (0.74)
MESA ROD BUSTERS, INC. (6.99)
J KRU LAND SERVICES, LLC (0.03)
SARVICUS LLC (2.18)
DUSTROL, INC. (0.86)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.08)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26)
HIGHWAY 1 LLC (0.98)
BUYERS BARRICADES, INC. (0.00)
BUYERS BARRICADES HOUSTON, LLC (0.09)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.97)
PRIMATE CONSTRUCTION, LP (0.40)
TOM-MAC, INC. (2.77)
AVILES CONSTRUCTION SERVICE, INC (1.35)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (2.84)
BATTEN DRILLING, INC. (0.95)
Contract #08213010
Totals16095270.66583350.7513137755.6381.6

CountyMONTGOMERY
HighwayFM 1774
FromFM 1488
ToFM 149
CSJ1400-04-040
Proj IDSTP 2022(697)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0531870035.502044198.5999.9
Work Order09-15-22
Work Began04-27-23
Work Completed
Time Computed10-15-22
Contract Working Days260
Addl Days Granted0
Working Days Charged154
Percent Time Used59
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223021
Totals1870035.503180.002044198.5999.9

CountyMONTGOMERY
HighwayFM 1375
FromFM 149
ToWALKER C/L
CSJ1402-03-012
Proj IDF 2023(339)
Work TypeOVERLAY
 
5.9592012093.412499507.7999.9
Work Order09-07-23
Work Began10-20-23
Work Completed
Time Computed10-20-23
Contract Working Days58
Addl Days Granted0
Working Days Charged58
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1402-03-012
HIGHWAY 1 LLC (8.41)
WILLOW CITY SIGN & RAIL, INC. (3.79)
Contract #08233208
Totals2012093.410.002499507.7999.9

CountyBRAZORIA
HighwayFM 1459
FromRURAL LANE
ToEARLEY STREET
CSJ1413-01-019
Proj IDSTP 2B24(116)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
134455.00127705.0094.9
Work Order08-01-24
Work Began00-00-00
Work Completed
Time Computed08-31-24
Contract Working Days51
Addl Days Granted0
Working Days Charged7
Percent Time Used13
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1413-01-019
LONESTAR TRAFFIC SAFETY, LLC (1.18)
Contract #06243256
Totals134455.00127705.00127705.0094.9

CountyGALVESTON
HighwayFM 528
FromBRAZORIA COUNTY LINE
ToFALCON RIDGE BLVD
CSJ1414-01-021
Proj IDF 2024(141)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
656556.335914.100.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1414-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233020
Totals656556.330.005914.100.9