Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 8 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTGOMERY
HighwayIH 45
FromLEAGUE LINE ROAD
ToWALKER COUNTY LINE
CSJ0675-08-111
Proj IDNH 2020(596)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
10.1512147330.782410015.4199.9
Work Order06-09-20
Work Began04-12-21
Work Completed
Time Computed07-09-20
Contract Working Days270
Addl Days Granted0
Working Days Charged269
Percent Time Used99
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-111
USA AMTECH, INC. (11.35)
ODUM SERVICES, LLC (3.80)
THIRD COAST SERVICES LLC (2.12)
MCA COMMUNICATIONS, INC. (4.32)
GROUND HOG FOUNDATION DRILLING (1.80)
Contract #04203231
Totals2147330.780.002410015.4199.9

CountyMONTGOMERY
HighwayIH 45
FromFM 830
ToSHEPARD HILL BLVD
CSJ0675-08-118
Proj IDSTP 2024(820)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.0301445627.5017920.001.2
Work Order07-24-24
Work Began00-00-00
Work Completed
Time Computed11-21-24
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DECO CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-118
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243038
Totals1445627.500.0017920.001.2

CountyMONTGOMERY
HighwayIH 45
FromN OF FM 830
ToS OF FM 1097
CSJ0675-08-120
Proj IDCC 675-8-120
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.5233167865.711629292.6251.4
Work Order04-18-24
Work Began06-17-24
Work Completed
Time Computed05-18-24
Contract Working Days151
Addl Days Granted0
Working Days Charged88
Percent Time Used58
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-120
CEN TEX HYDROSEED, INC. (1.01)
HIGHWAY 1 LLC (1.37)
QUALITY TURF FARMS, L.C. (2.84)
SCOTT DERR PAINTING CO, LLC (0.02)
TEXOP CONSTRUCTION (0.27)
PRIMATE CONSTRUCTION, LP (0.59)
B & D MAINTENANCE LLC (1.36)
DECO CONTRACTORS, INC. (10.59)
WILLOW CITY SIGN & RAIL, INC. (3.68)
SUPERIOR TRAFFIC CONTROL, LLC (0.19)
STRUCTURAL INTEGRITY GROUP LLC (1.44)
TEXAS CURB CUT (0.43)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (6.69)
TEXAS MATERIALS GROUP, INC. (0.64)
SHAW DRILLING, LLC (0.43)
MESA ROD BUSTERS, INC. (0.42)
BORTUNCO (2.99)
Contract #02243226
Totals3167865.71334141.791629292.6251.4

CountyGALVESTON
HighwayFM 1765
FromFM 2004
ToSH 146
CSJ0686-02-032
Proj IDSTP 2B24(175)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1024065.570.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-24-24
Work Began00-00-00
Work Completed
Time Computed12-23-24
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0686-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243016
Totals1024065.570.000.000.0

CountyHARRIS ETC
HighwaySH 249 ETC
FromSPRING CYPRESS
ToGRANT/SCHROEDER
CSJ0720-03-143
Proj IDSTP 1802(437)HES
Work TypeINTERCONNECT SIGNALS
 
17.9453528350.324166931.8199.9
Work Order01-11-19
Work Began06-06-19
Work Completed
Time Computed04-11-19
Contract Working Days362
Addl Days Granted90
Working Days Charged448
Percent Time Used99
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-143
LONESTAR TRAFFIC SAFETY, LLC (1.14)
TCH DIRECTIONAL DRILLING (13.68)
CHIRON COMMUNICATION SERVICES, LLC (6.11)
Contract #08183016
Totals3528350.320.004166931.8199.9

CountyHARRIS
HighwaySH 249
FromIH 45
ToSL 8
CSJ0720-03-147
Proj IDC 720-3-147
Work TypeTRAFFIC CONTROL DEVICES
 
7.380464642.33107672.3923.1
Work Order09-06-24
Work Began10-06-24
Work Completed
Time Computed10-06-24
Contract Working Days68
Addl Days Granted0
Working Days Charged15
Percent Time Used22
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-147
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243022
Totals464642.33107672.39107672.3923.1

CountyHARRIS
HighwaySH 249
From0.2 MILES NORTH OF HOLLISTER ROAD
To0.46 MILES NORTH OF GREGSON ROAD
CSJ0720-03-152
Proj IDF 2B24(464)
Work TypeTRAFFIC CONTROL DEVICES
 
8.8517878085.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed11-22-24
Contract Working Days195
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243013
Totals7878085.960.000.000.0

CountyHARRIS
HighwaySH 249
FromAT ALICE ROAD
To.
CSJ0720-06-002
Proj IDSTP 2022(209)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200375697.38405850.7199.9
Work Order02-15-22
Work Began06-15-22
Work Completed
Time Computed06-15-22
Contract Working Days78
Addl Days Granted0
Working Days Charged67
Percent Time Used85
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0720-06-002
LONESTAR TRAFFIC SAFETY, LLC (0.63)
HIGHWAY 1 LLC (4.26)
Contract #01223030
Totals375697.380.00405850.7199.9

CountyBRAZORIA
HighwayFM 521
FromAT OYSTER CREEK
To.
CSJ0847-06-012
Proj IDBR 2B24(052)
Work TypeBRIDGE REPLACEMENT
 
0.1523244910.210.000.0
Work Order08-22-24
Work Began10-21-24
Work Completed
Time Computed10-21-24
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRICE CONSTRUCTION AND DESIGN LLC
SUBCONTRACTOR(S) FOR CCSJ: 0847-06-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243009
Totals3244910.210.000.000.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-511
Proj IDSTP 2017(158)
Work TypeNEW TRAFFIC SIGNALS
 
0.5081718929.722399324.4399.9
Work Order01-04-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days199
Addl Days Granted190
Working Days Charged305
Percent Time Used78
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-511
GLOBE ELECTRIC SUPPLY COMPANY, INC. (5.90)
STRIPE LINES, INC. (1.74)
MENADE, INC. (12.49)
ALLY GENERAL SOLUTIONS, LLC (0.34)
Contract #10163215
Totals1718929.720.002399324.4399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-523
Proj IDNH 2018(110)
Work TypeINST TS
 
0.0011468618.082014410.1999.9
Work Order01-10-18
Work Began03-19-18
Work Completed
Time Computed04-10-18
Contract Working Days260
Addl Days Granted0
Working Days Charged240
Percent Time Used92
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-523
AAA ASPHALT PAVING, INC. (4.43)
HIGHWAY 1 LLC (5.13)
Contract #12173014
Totals1468618.080.002014410.1999.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-526
Proj IDC 912-00-526
Work TypeTRAFFIC CONTROL DEVICES
 
0.002291372.001350077.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began08-17-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged111
Percent Time Used92
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-526
BATTEN DRILLING, INC. (6.52)
Contract #10203013
Totals291372.000.001350077.5599.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-531
Proj IDC 912-0-531
Work TypeINSTALL NEW TRAFFIC SIGNALS
 
0.0011999535.002081910.7799.9
Work Order08-16-18
Work Began01-18-19
Work Completed
Time Computed12-14-18
Contract Working Days160
Addl Days Granted200
Working Days Charged353
Percent Time Used98
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-531
SPECIALTY DRILLING, LLC (0.45)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (2.24)
STRIPE LINES, INC. (1.97)
MLH CONCRETE (0.67)
SEMPER STRIPING LLC (1.18)
Contract #07183028
Totals1999535.000.002081910.7799.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-532
Proj IDC 912-00-532
Work TypeINSTALL NEW TRAFFIC SIGNALS
 
0.0011896973.002007325.4599.9
Work Order01-07-19
Work Began05-07-19
Work Completed
Time Computed05-07-19
Contract Working Days167
Addl Days Granted220
Working Days Charged313
Percent Time Used80
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-532
AAA ASPHALT PAVING, INC. (7.43)
STRIPE LINES, INC. (1.51)
Contract #12183218
Totals1896973.005316.462007325.4599.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-577
Proj IDSTP 2020(504)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011438222.501679865.4399.9
Work Order02-13-20
Work Began09-20-21
Work Completed
Time Computed06-12-20
Contract Working Days201
Addl Days Granted0
Working Days Charged170
Percent Time Used84
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-577
STRIPE LINES, INC. (1.65)
L&M INFRASTRUCTURE, LLC. (7.30)
BATTERSON, LLP (36.50)
SPARTAN SPECIALTY COMPANIES, LLC (3.47)
Contract #01203020
Totals1438222.500.001679865.4399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-578
Proj IDSTP 2020(597)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011780190.001899908.2699.9
Work Order03-11-20
Work Began10-18-21
Work Completed
Time Computed07-09-20
Contract Working Days216
Addl Days Granted0
Working Days Charged105
Percent Time Used48
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-578
STRIPE LINES, INC. (1.97)
L&M INFRASTRUCTURE, LLC. (5.90)
BATTERSON, LLP (0.56)
HIGHWAY 1 LLC (0.79)
Contract #02203018
Totals1780190.000.001899908.2699.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-587
Proj IDF 2022(143)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012915576.65539787.6518.5
Work Order01-12-22
Work Began08-07-24
Work Completed
Time Computed05-12-22
Contract Working Days418
Addl Days Granted0
Working Days Charged13
Percent Time Used3
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-587
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12213217
Totals2915576.6559821.35539787.6518.5

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-588
Proj IDC 912-00-588
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011328813.90295680.0022.2
Work Order03-24-22
Work Began00-00-00
Work Completed
Time Computed07-30-22
Contract Working Days213
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-588
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02223013
Totals1328813.9077370.00295680.0022.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To,
CSJ0912-00-590
Proj IDC 912-00-590
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012193801.201735143.5279.0
Work Order01-08-21
Work Began07-18-22
Work Completed
Time Computed05-08-21
Contract Working Days236
Addl Days Granted0
Working Days Charged106
Percent Time Used44
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-590
SAFETEX,INC. (1.16)
Contract #11203020
Totals2193801.2010750.201735143.5279.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-591
Proj IDC 912-00-591
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012517991.801209433.2348.0
Work Order10-21-20
Work Began08-30-21
Work Completed
Time Computed02-18-21
Contract Working Days280
Addl Days Granted0
Working Days Charged255
Percent Time Used91
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-591
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203015
Totals2517991.800.001209433.2348.0