Monthly State Let Maintenance Report For Houston District As Of Nov 10, 2024 Page 2 Of 8

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0069
FromIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
ToIH 69 ETC. VARIOUS ROADWAYS IN N. HARRIS
CSJ6392-48-001
Proj IDRMC - 639248001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0102509840.002337231.77100.0
Work Order00-00-00
Work Began04-04-22
Work Completed08-02-24
Time Computed04-04-22
Contract Working Days730
Addl Days Granted122
Working Days Charged844
Percent Time Used99
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224015
Totals2509840.0067150.002337231.77100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6393-43-001
Proj IDRMC - 639343001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101763985.005256908.1799.9
Work Order00-00-00
Work Began04-11-22
Work Completed
Time Computed04-11-22
Contract Working Days730
Addl Days Granted730
Working Days Charged929
Percent Time Used63
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224217
Totals1763985.0046965.965256908.1799.9

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-51-001
Proj IDRMC - 639351001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101157658.96818395.5870.6
Work Order00-00-00
Work Began10-31-22
Work Completed
Time Computed10-31-22
Contract Working Days314
Addl Days Granted0
Working Days Charged147
Percent Time Used46
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224215
Totals1157658.960.00818395.5870.6

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6393-86-001
Proj IDRMC - 639386001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101743010.002075423.7199.9
Work Order00-00-00
Work Began04-15-22
Work Completed
Time Computed04-15-22
Contract Working Days730
Addl Days Granted0
Working Days Charged711
Percent Time Used97
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6393-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224216
Totals1743010.0052534.722075423.7199.9

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
ToVARIOUS HIGHWAYS IN WEST HARRIS COUNTY
CSJ6395-26-001
Proj IDRMC - 639526001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101176491.002108739.5299.9
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted731
Working Days Charged786
Percent Time Used53
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224010
Totals1176491.00127205.942108739.5299.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN S BRAZORIA COUNTY
To.
CSJ6395-76-001
Proj IDRMC - 639576001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010744554.461045255.7099.9
Work Order00-00-00
Work Began06-06-22
Work Completed
Time Computed06-06-22
Contract Working Days232
Addl Days Granted232
Working Days Charged197
Percent Time Used42
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224216
Totals744554.4676971.561045255.7099.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6396-50-001
Proj IDRMC - 639650001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0101719552.501783241.2299.9
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224220
Totals1719552.500.001783241.2299.9

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6396-68-001
Proj IDRMC - 639668001
Work TypeBRIDGE DECK REPAIR
 
0.010821200.00814376.44100.0
Work Order00-00-00
Work Began10-03-22
Work Completed09-26-24
Time Computed09-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224017
Totals821200.004772.25814376.44100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN METRO HOUSTON AREA
ToVARIOUS HWYS IN METRO HOUSTON AREA
CSJ6397-62-001
Proj IDRMC - 639762001
Work TypeASPHALT PAVEMENT REPAIR
 
2633600.004316942.07100.0
Work Order00-00-00
Work Began12-03-22
Work Completed07-27-24
Time Computed12-03-22
Contract Working Days365
Addl Days Granted183
Working Days Charged537
Percent Time Used97
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6397-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224208
Totals2633600.000.004316942.07100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6399-21-001
Proj IDRMC - 639921001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010406463.63876227.1199.9
Work Order00-00-00
Work Began08-08-22
Work Completed
Time Computed08-08-22
Contract Working Days185
Addl Days Granted185
Working Days Charged252
Percent Time Used68
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224009
Totals406463.6364750.86876227.1199.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6399-26-001
Proj IDRMC - 639926001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101085050.001647650.12100.0
Work Order11-01-22
Work Began11-01-22
Work Completed09-26-24
Time Computed11-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224209
Totals1085050.000.001647650.12100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6400-07-001
Proj IDRMC - 640007001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.010999743.95999743.55100.0
Work Order08-29-22
Work Began09-01-22
Work Completed08-28-24
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged694
Percent Time Used95
Contractor(s)
SOUTHWEST SIGNAL SUPPLY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6400-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224210
Totals999743.9560819.55999743.55100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HIGHWAYS IN HOUSTON DISTRICT
ToVARIOUS HIGHWAYS IN HOUSTON DISTRICT
CSJ6400-67-001
Proj IDRMC - 640067001
Work TypeILLUMINATION MAINTENANCE
 
0.0102230105.002113320.2594.7
Work Order08-29-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged664
Percent Time Used90
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6400-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224608
Totals2230105.0086280.002113320.2594.7

CountyHARRIS
HighwayIH0610
FromMARKET ST
ToMCCARTY ST
CSJ6401-70-001
Proj IDRMC - 640170001
Work TypeROADSIGN ASSEMBLIES
 
0.010597485.50761163.4799.9
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed02-01-23
Contract Working Days40
Addl Days Granted0
Working Days Charged38
Percent Time Used95
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224011
Totals597485.500.00761163.4799.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6403-88-001
Proj IDRMC - 640388001
Work TypeDRAINAGE IMPROVEMENT AND/OR REPAIRS
 
0.010713974.001128402.00100.0
Work Order05-15-23
Work Began05-15-23
Work Completed06-24-24
Time Computed05-15-23
Contract Working Days90
Addl Days Granted45
Working Days Charged87
Percent Time Used64
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6403-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234022
Totals713974.000.001128402.00100.0

CountyHARRIS
HighwayIH0045
FromSOUTHERN STREET
ToSH 87
CSJ6404-39-001
Proj IDRMC - 640439001
Work TypeTOTAL MAINTENANCE
 
0.0104333798.053643905.2184.0
Work Order00-00-00
Work Began04-03-23
Work Completed
Time Computed04-03-23
Contract Working Days730
Addl Days Granted0
Working Days Charged572
Percent Time Used78
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6404-39-001
XTREME PRO CLEANING LLC (0.00)
XTREME PRO CLEANING LLC (0.00)
Contract #02234005
Totals4333798.05274424.643643905.2184.0

CountyBRAZORIA
HighwayFM0521
FromAT SAN BERNARD RIVER
To.
CSJ6408-53-001
Proj IDRMC - 640853001
Work TypeEROSION REPAIR
 
0.010928042.51749618.23100.0
Work Order00-00-00
Work Began04-03-23
Work Completed09-23-24
Time Computed04-03-23
Contract Working Days69
Addl Days Granted3
Working Days Charged71
Percent Time Used98
Contractor(s)
ENVIRONMENTAL ALLIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6408-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234007
Totals928042.510.00749618.23100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6410-33-001
Proj IDRMC - 641033001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0102490400.004685023.2299.9
Work Order00-00-00
Work Began01-23-23
Work Completed
Time Computed12-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged695
Percent Time Used95
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6410-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10224012
Totals2490400.00699.604685023.2299.9

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6415-98-001
Proj IDRMC - 641598001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.0102447150.002700506.10100.0
Work Order00-00-00
Work Began01-26-23
Work Completed09-10-24
Time Computed01-26-23
Contract Working Days731
Addl Days Granted0
Working Days Charged584
Percent Time Used79
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6415-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224008
Totals2447150.00511000.002700506.10100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6418-41-001
Proj IDRMC - 641841001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010504220.001162581.9999.9
Work Order00-00-00
Work Began01-10-23
Work Completed
Time Computed01-10-23
Contract Working Days365
Addl Days Granted365
Working Days Charged655
Percent Time Used89
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6418-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224209
Totals504220.0077764.091162581.9999.9