Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | GALVESTON |
Highway | SH0146 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6461-71-001 |
Proj ID | RMC - 646171001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 1490630.00 | | 431914.53 | 28.9 |
Work Order | 00-00-00 |
Work Began | 08-21-24 |
Work Completed | |
Time Computed | 05-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 117 |
Percent Time Used | 32 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6461-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244213 |
| Totals | 1490630.00 | 201877.76 | 431914.53 | 28.9 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN WALLER COUNTY |
To | VARIOUS HIGHWAYS IN WALLER COUNTY |
CSJ | 6461-95-001 |
Proj ID | RMC - 646195001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 289464.58 | | 202251.86 | 69.8 |
Work Order | 00-00-00 |
Work Began | 06-26-24 |
Work Completed | |
Time Computed | 06-17-24 |
Contract Working Days | 109 |
Addl Days Granted | 0 |
Working Days Charged | 47 |
Percent Time Used | 43 |
Contractor(s) |
BEN E. SMITH TRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6461-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244010 |
| Totals | 289464.58 | 0.00 | 202251.86 | 69.8 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN WALLER COUNTY |
To | VARIOUS HIGHWAYS IN WALLER COUNTY |
CSJ | 6462-04-001 |
Proj ID | RMC - 646204001 |
Work Type | BRIDGE DECK REPAIR |
|
| 0.010 | 622750.00 | | 147734.57 | 23.7 |
Work Order | 00-00-00 |
Work Began | 09-18-24 |
Work Completed | |
Time Computed | 08-26-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 61 |
Percent Time Used | 16 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6462-04-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244209 |
| Totals | 622750.00 | 98981.90 | 147734.57 | 23.7 |
|
County | HARRIS |
Highway | IH0610 |
From | US 90 |
To | HOMESTEAD |
CSJ | 6462-24-001 |
Proj ID | RMC - 646224001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 1357265.00 | | 928094.56 | 68.3 |
Work Order | 00-00-00 |
Work Began | 08-26-24 |
Work Completed | |
Time Computed | 08-26-24 |
Contract Working Days | 75 |
Addl Days Granted | 0 |
Working Days Charged | 52 |
Percent Time Used | 69 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6462-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244210 |
| Totals | 1357265.00 | 623799.27 | 928094.56 | 68.3 |
|
County | HARRIS |
Highway | IH0610 |
From | HUNTING BAYOU |
To | HUNTING BAYOU |
CSJ | 6462-28-001 |
Proj ID | RMC - 646228001 |
Work Type | DRAINAGE IMPROVEMENT AND/OR REPAIRS |
|
| 0.010 | 596282.00 | | 913133.45 | 99.9 |
Work Order | 00-00-00 |
Work Began | 09-16-24 |
Work Completed | |
Time Computed | 09-16-24 |
Contract Working Days | 45 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 51 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244014 |
| Totals | 596282.00 | 568545.97 | 913133.45 | 99.9 |
|
County | HARRIS |
Highway | IH0010 |
From | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
To | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
CSJ | 6462-29-001 |
Proj ID | RMC - 646229001 |
Work Type | CURB & GUTTER MAINT |
|
| 0.010 | 686400.00 | | 0.00 | 0.0 |
Work Order | 00-00-00 |
Work Began | 10-14-24 |
Work Completed | |
Time Computed | 08-08-24 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 49 |
Percent Time Used | 6 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244210 |
| Totals | 686400.00 | 0.00 | 0.00 | 0.0 |
|
County | FORT BEND |
Highway | US0059 |
From | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
To | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
CSJ | 6462-66-001 |
Proj ID | RMC - 646266001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 538200.00 | | 0.00 | 0.0 |
Work Order | 00-00-00 |
Work Began | 07-01-24 |
Work Completed | |
Time Computed | 07-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 117 |
Percent Time Used | 32 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-66-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244012 |
| Totals | 538200.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH0610 |
From | VARIOUS HIGHWAYS IN HOUSTON METRO AREA |
To | VARIOUS HIGHWAYS IN HOUSTON METRO AREA |
CSJ | 6462-86-001 |
Proj ID | RMC - 646286001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 2396729.64 | | 131917.93 | 5.5 |
Work Order | 00-00-00 |
Work Began | 09-01-24 |
Work Completed | |
Time Computed | 09-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 6 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-86-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244211 |
| Totals | 2396729.64 | 131917.93 | 131917.93 | 5.5 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN WALLER COUNTY |
To | VARIOUS HIGHWAYS IN WALLER COUNTY |
CSJ | 6462-91-001 |
Proj ID | RMC - 646291001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 496450.00 | | 0.00 | 0.0 |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 28 |
Percent Time Used | 7 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244031 |
| Totals | 496450.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SH0249 |
From | IH 249, ETC. VARIOUS LOCATIONS |
To | SH 249,. ETC. VARIOUS LOCATIONS |
CSJ | 6463-18-001 |
Proj ID | RMC - 646318001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 1277980.00 | | 362789.29 | 28.3 |
Work Order | 00-00-00 |
Work Began | 07-09-24 |
Work Completed | |
Time Computed | 07-09-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 109 |
Percent Time Used | 29 |
Contractor(s) |
RHINO EQUITY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244013 |
| Totals | 1277980.00 | 125612.04 | 362789.29 | 28.3 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN THE HOUSTON DISTRICT |
To | VARIOUS HIGHWAYS IN THE HOUSTON DISTRICT |
CSJ | 6463-29-001 |
Proj ID | RMC - 646329001 |
Work Type | HIGH EDGE REMOVAL |
|
| 0.010 | 510038.00 | | 640711.00 | 99.9 |
Work Order | 08-19-24 |
Work Began | 08-19-24 |
Work Completed | |
Time Computed | 08-19-24 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 68 |
Percent Time Used | 37 |
Contractor(s) |
JACKSON EXCAVATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244032 |
| Totals | 510038.00 | 5131.00 | 640711.00 | 99.9 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
To | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
CSJ | 6463-46-001 |
Proj ID | RMC - 646346001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 1883862.50 | | 67116.00 | 3.5 |
Work Order | 00-00-00 |
Work Began | 09-03-24 |
Work Completed | |
Time Computed | 08-14-24 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 3 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05244014 |
| Totals | 1883862.50 | 67116.00 | 67116.00 | 3.5 |
|
County | HARRIS |
Highway | IH0610 |
From | VARIOUS HWYS IN HOUSTON METRO AREA |
To | VARIOUS HWYS IN HOUSTON METRO AREA |
CSJ | 6463-51-001 |
Proj ID | RMC - 646351001 |
Work Type | TOTAL MAINTENANCE |
|
| 0.010 | 6910200.00 | | 762778.06 | 11.0 |
Work Order | 00-00-00 |
Work Began | 09-01-24 |
Work Completed | |
Time Computed | 09-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 55 |
Percent Time Used | 15 |
Contractor(s) |
HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6463-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244222 |
| Totals | 6910200.00 | 550606.26 | 762778.06 | 11.0 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS HIGHWAYS WITHIN BRAZORIA COUNTY |
To | VARIOUS HIGHWAYS WITHIN BRAZORIA COUNTY |
CSJ | 6463-63-001 |
Proj ID | RMC - 646363001 |
Work Type | CONCRETE STRUCTURE REPAIR |
|
| 0.010 | 1898800.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6463-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08244206 |
| Totals | 1898800.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH0610 |
From | VARIOUS HWYS IN HOUSTON METRO AREA |
To | VARIOUS HWYS IN HOUSTON METRO AREA |
CSJ | 6464-46-001 |
Proj ID | RMC - 646446001 |
Work Type | DRAINAGE SYSTEM CLEANING |
|
| 0.010 | 377550.00 | | 10730.00 | 2.8 |
Work Order | 00-00-00 |
Work Began | 09-01-24 |
Work Completed | |
Time Computed | 09-01-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 6 |
Contractor(s) |
AIMS COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 6464-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244223 |
| Totals | 377550.00 | 10730.00 | 10730.00 | 2.8 |
|
County | BRAZORIA |
Highway | SH0288 |
From | AT INTERCHANGE WITH SH 332/BS 288B |
To | . |
CSJ | 6464-62-001 |
Proj ID | RMC - 646462001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 621063.25 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-30-24 |
Work Completed | |
Time Computed | 09-30-24 |
Contract Working Days | 77 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6464-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06244225 |
| Totals | 621063.25 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | SL0336 |
From | SL 336 |
To | FM 1485 |
CSJ | 6465-34-001 |
Proj ID | RMC - 646534001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (LONG LINE) |
|
| 0.010 | 1238799.25 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 11-04-24 |
Work Began | 11-04-24 |
Work Completed | |
Time Computed | 11-04-24 |
Contract Working Days | 90 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRP INFRASTRUCTURE SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6465-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244025 |
| Totals | 1238799.25 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
To | VARIOUS HIGHWAYS IN SOUTHEAST HARRIS |
CSJ | 6465-56-001 |
Proj ID | RMC - 646556001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 3186825.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6465-56-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244026 |
| Totals | 3186825.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZORIA |
Highway | SH0288 |
From | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
To | VARIOUS LOCATIONS IN BRAZORIA COUNTY |
CSJ | 6465-70-001 |
Proj ID | RMC - 646570001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 505870.75 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 165 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BOEN LANDSCAPING & IRRIGATION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6465-70-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244027 |
| Totals | 505870.75 | 0.00 | 0.00 | 0.0 |
|
County | GALVESTON |
Highway | FM0517 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6465-81-001 |
Proj ID | RMC - 646581001 |
Work Type | DITCH CLEANING AND RESHAPING |
|
| 0.010 | 425000.00 | | 115747.14 | 27.2 |
Work Order | 00-00-00 |
Work Began | 08-26-24 |
Work Completed | |
Time Computed | 08-21-24 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 66 |
Percent Time Used | 18 |
Contractor(s) |
TEXAS DRAINAGE INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6465-81-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07244028 |
| Totals | 425000.00 | 87574.44 | 115747.14 | 27.2 |
|