Monthly State Let Construction Report For Wichita Falls District As Of Nov 10, 2024 Page 1 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromWAGONSELLER RD
To0.25 MI S OF SS 511
CSJ0013-05-065
Proj IDSTP 2B23(131)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2243728.651987896.3588.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began11-20-23
Work Completed
Time Computed00-00-00
Contract Working Days193
Addl Days Granted0
Working Days Charged115
Percent Time Used59
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-065
FC TRAFFIC CONTROL, INC. (0.99)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.11)
Contract #08233239
Totals2243728.652370.001987896.3588.5

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromNEAR WAGGONSELLER RD
ToWISE CL (FRONTAGE ROADS ONLY)
CSJ0013-05-066
Proj IDF 2025(158)
Work TypeSEAL COAT
 
11361820.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243013
Totals11361820.190.000.000.0

CountyWILBARGER ETC
HighwayUS 70 ETC
FromUS 287 SB
ToAT VERNON ACCESS O-PASS
CSJ0043-06-098
Proj IDBR 2B24(022)
Work TypeBRIDGE MAINTENANCE
 
4708397.65986494.4920.9
Work Order06-06-24
Work Began10-01-24
Work Completed
Time Computed07-08-24
Contract Working Days170
Addl Days Granted0
Working Days Charged21
Percent Time Used12
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-098
JR WEST TEXAS CONCRETE LLC (15.14)
IBCTX, LLC (6.93)
S & S BRIDGE PAINTING, INC. (3.34)
MORRIS COUNTY CONTRACTORS, L.L.C. (3.27)
DUSTROL, INC. (1.81)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.68)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.16)
LANCO TURF & SEEDING, INC. (0.40)
SOUTHEAST GRINDING AND GROOVING LLC (0.25)
NELSON INDUSTRIAL SERVICES, INC. (0.17)
SYNERGY SIGNS & SERVICES LLC (0.54)
Contract #05243214
Totals4708397.65953575.49986494.4920.9

CountyWICHITA
HighwayUS 287
FromHARMONY RD
ToQUAIL VALLEY RD
CSJ0043-08-088
Proj IDSTP 2024(778)TP
Work TypeRESTORATION
 
5428567.961709866.0931.4
Work Order04-18-24
Work Began00-00-00
Work Completed
Time Computed05-20-24
Contract Working Days136
Addl Days Granted0
Working Days Charged66
Percent Time Used48
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-088
MARCOM"S MOWING SERVICE, LLC (0.38)
W. S. CONSTRUCTION COMPANY (37.47)
LANCO TURF & SEEDING, INC. (0.66)
BARRICADES UNLIMITED (0.36)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.65)
MICA CORPORATION (10.11)
Contract #03243018
Totals5428567.96530454.731709866.0931.4

CountyWICHITA
HighwayUS 287
FromNEAR JOHNSON RD
ToIH 44
CSJ0043-09-146
Proj IDF 2B24(125)
Work TypeOVERLAY
 
7338061.320.000.0
Work Order07-24-24
Work Began00-00-00
Work Completed
Time Computed07-23-24
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243220
Totals7338061.320.000.000.0

CountyWICHITA
HighwayBU 287J
FromFM 368
ToSL 11
CSJ0043-17-031
Proj IDF 2023(458)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9919386786.815210321.8356.1
Work Order06-22-23
Work Began07-31-23
Work Completed
Time Computed07-24-23
Contract Working Days200
Addl Days Granted0
Working Days Charged243
Percent Time Used121
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-031
W. S. CONSTRUCTION COMPANY (21.59)
FC TRAFFIC CONTROL, INC. (0.32)
HJC FARMS, INC. (3.84)
TRP CONSTRUCTION GROUP, LLC (1.90)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.60)
DUSTROL, INC. (0.04)
COTHRAN TRUCKING, LLC (1.38)
Contract #02233211
Totals9386786.81133539.625210321.8356.1

CountyWICHITA
HighwayBU 287J
FromSL 11
ToIH 44
CSJ0043-17-035
Proj IDF 2B24(023)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1028500.80586868.7057.0
Work Order06-06-24
Work Began00-00-00
Work Completed
Time Computed07-08-24
Contract Working Days167
Addl Days Granted0
Working Days Charged44
Percent Time Used26
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-035
KING GEORGE TRAFFIC SOLUTIONS LLC (0.81)
AWP SAFETY (2.72)
VACA UNDERGROUND UTILITIES INC (10.42)
LONE STAR PRODUCTS (WICHITA FALLS) (2.21)
Contract #05243233
Totals1028500.80255977.96586868.7057.0

CountyWICHITA ETC
HighwayUS 82 ETC
FromWINDTHORST RD
ToFISHER RD (INTERCHANGE AREA FR/RAMPS)
CSJ0044-01-110
Proj IDF 2024(337)
Work TypeSEAL COAT
 
11122261.6010667172.6495.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged68
Percent Time Used100
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-110
BARRICADES PLUS, LLC (1.60)
CENTERLINE TECHNOLOGIES, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
RED SIXTEEN CONSTRUCTION, INC (0.88)
Contract #11233205
Totals11122261.602634.0010667172.6495.9

CountyMONTAGUE
HighwayUS 82
FromSH 175 / MONTAGUE STREET
ToNEAR FM 1816
CSJ0044-04-047
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
6.10027683391.0529244748.1599.9
CountyMONTAGUE
HighwayUS 82
From0.5 MI EAST OF US 81
ToNEAR FM 1816
CSJ0044-04-049
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
5.82920779023.0421666422.3299.9
Work Order08-19-21
Work Began10-25-21
Work Completed
Time Computed09-20-21
Contract Working Days719
Addl Days Granted0
Working Days Charged668
Percent Time Used92
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-047
STRAIGHT LINE SAWING & SEALING, INC. (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.03)
JR WEST TEXAS CONCRETE LLC (3.18)
AREA WIDE PROTECTIVE, INC. (0.25)
DUSTROL, INC. (0.25)
HAMMETT EXCAVATION, INC. (24.22)
STRIPING TECHNOLOGY, L.P. (0.97)
TEXAS SHAFTS, INC. (0.86)
L&H ELECTRICAL, LLC (0.70)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.84)
WITHERS CONSTRUCTION, LLC (0.86)
HERMANOS STEEL, LLC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.15)
FARR FOUNDATION, INC. (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC (0.92)
DUSTIN ALLEN, INC. (0.28)
SOUTHEAST GRINDING AND GROOVING LLC (0.02)
RAMBO CONTRACTING, INC. (0.19)
PANIOLO CONSTRUCTION SERVICES, LLC (0.06)
FGA CONSTRUCTION LLC (0.03)
DALLAS LITE AND BARRICADE, INC. (0.05)
HILBASH INVESTMENT LLC (0.31)
PROFESSIONAL TRAFFIC CONTROL LLC (0.04)
Contract #07213001
Totals48462414.0973005.0650911170.4799.9

CountyMONTAGUE
HighwayUS 82
FromCLAY COUNTY LINE
ToAPPROX 0.5 MI. E OF US 81 (RINGGOLD)
CSJ0044-04-048
Proj IDF 2024(766)
Work TypeWIDEN NON-FREEWAY
 
38961339.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days481
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-048
BARRICADES UNLIMITED (0.23)
J. H. ODEN CONTRACTING COMPANY (1.53)
Contract #06243205
Totals38961339.010.000.000.0

CountyMONTAGUE
HighwayUS 82
From1.25 MI E OF FM 103
To0.25 MI W OF SH 59
CSJ0044-06-077
Proj IDSTP 2B24(222)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2018680.081199799.0359.4
CountyMONTAGUE
HighwayUS 82
From0.50 MI E OF FM 677
ToCOOKE COUNTY LINE
CSJ0044-06-078
Proj IDSTP 2B24(222)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
322111.10600.000.1
CountyCOOKE
HighwayUS 82
FromMONTAGUE COUNTY LINE
To0.65 MI W OF FM 373
CSJ0044-07-075
Proj IDSTP 2B24(222)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
942876.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-24
Work Began09-10-24
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged36
Percent Time Used15
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243007
Totals3283667.33498056.861200399.0336.5

CountyCOOKE
HighwayUS 82
FromASH STREET
ToMAPLE STREET
CSJ0044-07-074
Proj IDF 2022(503)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
53300.000.000.0
Work Order07-18-24
Work Began00-00-00
Work Completed
Time Computed08-19-24
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-07-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243044
Totals53300.000.000.000.0

CountyWICHITA
HighwayBU 287J
FromSS 213 (PETROLIA RD)
ToCLAY COUNTY LINE
CSJ0044-11-004
Proj IDF 2025(074)
Work TypeOVERLAY
 
1444298.220.000.0
CountyCLAY
HighwayBU 287J
FromWICHITA COUNTY LINE
ToUS 82/287
CSJ0044-12-003
Proj IDF 2025(237)
Work TypeOVERLAY
 
1111418.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-11-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243019
Totals2555716.290.000.000.0

CountyWILBARGER
HighwayUS 283
FromFM 925
ToFM 924
CSJ0124-02-035
Proj IDF 2B24(221)
Work TypeOVERLAY
 
5113470.440.000.0
CountyWILBARGER
HighwayUS 283
FromPEASE RIVER
ToFM 925
CSJ0124-03-066
Proj IDF 2B24(221)
Work TypeOVERLAY
 
530194.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OVERLAND CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0124-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243209
Totals5643664.870.000.000.0

CountyBAYLOR
HighwayUS 183
FromUS 277
ToTHROCKMORTON CL
CSJ0125-01-034
Proj IDF 2023(090)
Work TypeREHABILITATION OF EXISTING ROAD
 
7724536.698059977.3699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began04-17-23
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged215
Percent Time Used102
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0125-01-034
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.99)
CHEROKEE SERVICES (0.23)
CONTRACTORS SERVICE, LTD. (0.77)
HJC FARMS, INC. (2.00)
JR WEST TEXAS CONCRETE LLC (2.15)
LANCO TURF & SEEDING, INC. (2.91)
Contract #09223234
Totals7724536.69100.008059977.3699.9

CountyBAYLOR
HighwayUS 82
FromKNOX COUNTY LINE
ToBU 183B
CSJ0133-04-042
Proj IDF 2022(303)
Work TypeSUPER-2 HIGHWAY
 
12.57915938381.2616402289.5799.9
Work Order01-05-22
Work Began03-21-22
Work Completed
Time Computed02-04-22
Contract Working Days377
Addl Days Granted46
Working Days Charged496
Percent Time Used117
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-04-042
DUSTIN ALLEN, INC. (0.42)
MARCOM"S MOWING SERVICE, LLC (0.75)
TRP CONSTRUCTION GROUP, LLC (1.11)
W. S. CONSTRUCTION COMPANY (12.80)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.49)
CONTRACTORS SERVICE, LTD. (0.56)
Contract #12213023
Totals15938381.260.0016402289.5799.9

CountyYOUNG
HighwaySH 251
FromSH 79
ToFM 926 (NEWCASTLE)
CSJ0134-01-027
Proj IDF 2B24(287)
Work TypeOVERLAY
 
4490409.690.000.0
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed10-06-25
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243009
Totals4490409.690.000.000.0

CountyWICHITA
HighwaySH 25
FromFM 1811
ToARCHER COUNTY LINE
CSJ0137-03-085
Proj IDF 2B24(122)
Work TypeWIDEN NON-FREEWAY
 
20570032.281215530.015.9
Work Order07-17-24
Work Began08-29-24
Work Completed
Time Computed10-16-24
Contract Working Days601
Addl Days Granted0
Working Days Charged42
Percent Time Used6
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0137-03-085
FLAT LINE, INC. (0.91)
W. S. CONSTRUCTION COMPANY (11.17)
DUSTIN ALLEN, INC. (0.49)
LANCO TURF & SEEDING, INC. (1.28)
MARCOMS CONSTRUCTION LLC (0.60)
FC TRAFFIC CONTROL, INC. (0.17)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.21)
Contract #06243008
Totals20570032.28238493.391215530.015.9

CountyWICHITA
HighwaySH 240
FromIH 44
ToNEAR ROBINSON ROAD
CSJ0156-02-033
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
701607.84931627.4899.9
CountyWICHITA
HighwaySH 240
FromNEAR ROBINSON ROAD
To2ND STREET
CSJ0156-03-049
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1128031.001689805.8399.9
Work Order08-25-21
Work Began07-11-22
Work Completed
Time Computed09-24-21
Contract Working Days152
Addl Days Granted117
Working Days Charged252
Percent Time Used93
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-02-033
GARRET SHIELDS INFRASTRUCTURE (103.09)
WEST TEXAS ROCK RESOURCES, LLC (0.72)
WG ENGINEERING & CONSTRUCTION, LLC (16.02)
STRIPE-A-ZONE, LLC (6.13)
MEDELLIN HDD LLC (0.39)
ARBOR RESOURCES, LLC (1.55)
LINEAR TRAFFIC MARKINGS LLC (5.92)
WATTS ENTERPRISES, LLC (0.59)
BROTHERS RDC PAVING, LLC (1.55)
Contract #07213019
Totals1829638.8439983.132621433.3199.9

CountyWICHITA
HighwayUS 82 ETC
FromUS 82 EB (KELL)
ToAT KEMP BLVD
CSJ0156-04-120
Proj IDBR 2024(686)
Work TypeBRIDGE MAINTENANCE
 
1.9962856132.081013712.5735.4
Work Order06-06-24
Work Began07-15-24
Work Completed
Time Computed07-08-24
Contract Working Days442
Addl Days Granted0
Working Days Charged74
Percent Time Used16
Contractor(s)
TALBERT COMPANIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-04-120
SOUTHERN CROSS CONTRACTORS, LLC (2.81)
DALLAS LITE AND BARRICADE, INC. (3.07)
TUCAN CONTRACTING, LLC (29.54)
KING GEORGE TRAFFIC SOLUTIONS LLC (2.92)
AWP SAFETY (0.45)
Contract #02243229
Totals2856132.08282912.151013712.5735.4

page 1 | page 2 | page 3