Monthly State Let Construction Report For Wichita Falls District As Of Nov 10, 2024 Page 3 Of 3

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyYOUNG
HighwayFM 1287
FromBRAZOS RIVER BRIDGE
To0.81 MI SOUTH OF BERRY LN
CSJ1293-01-024
Proj IDSTP 2B24(219)HRR
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2173877.340.000.0
CountyYOUNG
HighwayFM 1287
From0.81 M S OF BERRY LANE
ToMOUNTAIN HOME ROAD
CSJ1293-01-025
Proj IDF 2B24(220)
Work TypeWIDEN NON-FREEWAY
 
2889788.170.000.0
CountyYOUNG
HighwayFM 1287
FromMOUNTAIN HOME ROAD
ToSTEPHENS COUNTY LINE
CSJ1293-01-026
Proj IDF 2B24(220)
Work TypeWIDEN NON-FREEWAY
 
1330352.340.000.0
Work Order08-14-24
Work Began00-00-00
Work Completed
Time Computed09-13-24
Contract Working Days386
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 1293-01-024
W. S. CONSTRUCTION COMPANY (17.71)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.53)
BARRICADES UNLIMITED (0.93)
DUSTROL, INC. (0.36)
TRP CONSTRUCTION GROUP, LLC (1.71)
HJC FARMS, INC. (1.82)
Contract #07243215
Totals6394017.850.000.000.0

CountyCOOKE
HighwayFM 1198
FromUS 82
ToFM 1630
CSJ1351-01-016
Proj IDF 2023(924)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.1137202957.374113222.4657.1
CountyCOOKE
HighwayFM 1198
FromFM 1630
ToFM 922
CSJ1351-02-007
Proj IDF 2023(924)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.5394904538.624518286.6092.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-23
Work Began10-16-23
Work Completed
Time Computed00-00-00
Contract Working Days407
Addl Days Granted15
Working Days Charged197
Percent Time Used50
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 1351-01-016
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.57)
SOUTHERN CROSS CONTRACTORS, LLC (1.56)
DALLAS LITE AND BARRICADE, INC. (0.44)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
JR WEST TEXAS CONCRETE LLC (15.65)
JOE"S TREE SERVICE (0.17)
TRP CONSTRUCTION GROUP, LLC (0.52)
Contract #06233208
Totals12107495.991063734.018631509.0671.2

CountyARCHER
HighwayFM 1954
FromUS 281
ToCLAY COUNTY LINE
CSJ1837-02-017
Proj IDF 2023(091)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.2727814963.769562823.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-22
Work Began01-16-23
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted74
Working Days Charged356
Percent Time Used120
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1837-02-017
W. S. CONSTRUCTION COMPANY (20.80)
LANCO TURF & SEEDING, INC. (1.66)
DUSTIN ALLEN, INC. (1.04)
BARRICADES UNLIMITED (0.26)
MARCOM"S MOWING SERVICE, LLC (0.63)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.85)
Contract #09223235
Totals7814963.76160376.429562823.2099.9