Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | FAYETTE ETC |
Highway | US 90 ETC |
From | MARKET STREET(IN FLATONIA) |
To | 0.4 MI E OF ELM STREET |
CSJ | 0026-02-037 |
Proj ID | F 2021(544) |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 4.836 | 2774624.51 | | 1239545.05 | 47.5 |
Work Order | 01-20-22 |
Work Began | 02-06-23 |
Work Completed | |
Time Computed | 04-21-22 |
Contract Working Days | 210 |
Addl Days Granted | 0 |
Working Days Charged | 312 |
Percent Time Used | 148 |
Contractor(s) |
TREVWAY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-037 LONESTAR TRAFFIC SAFETY, LLC (0.58) STRIPE LINES, INC. (1.44)
|
Contract # | 12213211 |
| Totals | 2774624.51 | 68708.16 | 1239545.05 | 47.5 |
|
County | FAYETTE ETC |
Highway | US 90 ETC |
From | GONZALES C/L |
To | 0.12 MI W OF SH 95 |
CSJ | 0026-02-039 |
Proj ID | F 2024(332) |
Work Type | SEAL COAT |
|
| 314.385 | 19785795.69 | | 16505798.23 | 83.4 |
Work Order | 12-06-23 |
Work Began | 05-21-24 |
Work Completed | |
Time Computed | 06-01-24 |
Contract Working Days | 75 |
Addl Days Granted | 0 |
Working Days Charged | 75 |
Percent Time Used | 100 |
Contractor(s) |
RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-039 INTERSTATE BARRICADES & MARKINGS, INC. (3.15) VIZCAINO, L.P. (23.92)
|
Contract # | 11233204 |
| Totals | 19785795.69 | 76441.26 | 16505798.23 | 83.4 |
|
County | FAYETTE |
Highway | US 90 |
From | AT WEST NAVIDAD RIVER |
To | STR # 0026-03-034 |
CSJ | 0026-03-046 |
Proj ID | BR 2023(623) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.200 | 5073582.21 | | 4372396.95 | 85.6 |
County | FAYETTE |
Highway | US 90 |
From | AT FOSTER CREEK |
To | STR # 0026-03-035 |
CSJ | 0026-03-047 |
Proj ID | BR 2023(623) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.200 | 1981766.25 | | 1814910.60 | 91.5 |
Work Order | 05-25-23 |
Work Began | 08-18-23 |
Work Completed | |
Time Computed | 08-23-23 |
Contract Working Days | 240 |
Addl Days Granted | 0 |
Working Days Charged | 255 |
Percent Time Used | 106 |
Contractor(s) |
ACME BRIDGE COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-046 EGGEMEYER LAND CLEARING, LLC (0.58) TRP CONSTRUCTION GROUP, LLC (0.75) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50) HOUSTON SAWING & DRILLING (0.14) TEXAS MATERIALS GROUP, INC. (17.00) LONE STAR EROSION CONTROL (1.64) INTERSTATE BARRICADES & MARKINGS, INC. (0.23) CND CONTRACTING (1.20) TORO BRAVO CONSTRUCTION, LLC (0.24) TRAFFIC SIGNS & LINES, LLC (0.14) AARON CONCRETE CONTRACTORS, LLC (1.13) ROYAL REBAR (0.09)
|
Contract # | 04233210 |
| Totals | 7055348.46 | 539125.07 | 6187307.55 | 87.3 |
|
County | FAYETTE ETC |
Highway | US 90 ETC |
From | 0.130 MI E OF SCHULTZ |
To | COLORADO C/L |
CSJ | 0026-03-049 |
Proj ID | C 26-3-49 |
Work Type | SEAL COAT |
|
| 385.586 | 20248015.63 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 75 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-049 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11243204 |
| Totals | 20248015.63 | 0.00 | 0.00 | 0.0 |
|
County | COLORADO ETC |
Highway | US 90 ETC |
From | WEIMAR ISD |
To | N GROHMANN STREET |
CSJ | 0026-04-048 |
Proj ID | C 26-4-48 |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 5.564 | 2778932.60 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-16-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 01-14-25 |
Contract Working Days | 270 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0026-04-048 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09243218 |
| Totals | 2778932.60 | 0.00 | 0.00 | 0.0 |
|
County | COLORADO |
Highway | US 90 |
From | .02 MI WEST OF FRONT STREET |
To | 0.10 MI W. OF LEGION DR. |
CSJ | 0026-06-031 |
Proj ID | F 2023(670) |
Work Type | OVERLAY |
|
| 9.674 | 5565142.56 | | 4262610.17 | 77.7 |
Work Order | 06-28-23 |
Work Began | 06-18-24 |
Work Completed | |
Time Computed | 07-28-23 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 107 |
Percent Time Used | 178 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-031 D. I. J. CONSTRUCTION, INC. (3.01) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.50) CPAVE, INC. (0.53) RUCOBA & MAYA CONSTRUCTION, LLC (2.56) LONESTAR TRAFFIC SAFETY, LLC (0.24) A BROTHERS MILLING, LLC (1.43) WEST TEXAS ROCK RESOURCES, LLC (0.21) QUICK MATERIALS (2.89) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (41.51)
|
Contract # | 05233019 |
| Totals | 5565142.56 | 640175.80 | 4262610.17 | 77.7 |
|
County | COLORADO ETC |
Highway | US 90 ETC |
From | AT BS 71-F IN COLUMBUS |
To | . |
CSJ | 0026-06-032 |
Proj ID | F 2022(609) |
Work Type | TRAFFIC CONTROL DEVICES |
|
| 0.202 | 2805099.50 | | 2496956.03 | 89.1 |
Work Order | 09-28-22 |
Work Began | 02-09-23 |
Work Completed | |
Time Computed | 12-27-22 |
Contract Working Days | 270 |
Addl Days Granted | 0 |
Working Days Charged | 276 |
Percent Time Used | 102 |
Contractor(s) |
VACA UNDERGROUND UTILITIES INC |
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-032 FLASHER EQUIPMENT COMPANY (2.74)
|
Contract # | 06223225 |
| Totals | 2805099.50 | 15446.20 | 2496956.03 | 89.1 |
|
County | COLORADO |
Highway | US 90 |
From | FM 806 |
To | FRONT STREET |
CSJ | 0026-06-034 |
Proj ID | F 2022(489) |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 1.503 | 779897.20 | | 915354.15 | 99.9 |
County | MATAGORDA |
Highway | SH 35 |
From | BAYOU DRIVE |
To | 12 TH STREET |
CSJ | 0179-04-100 |
Proj ID | F 2022(490) |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 4.400 | 2077545.80 | | 2360628.11 | 99.9 |
Work Order | 06-09-22 |
Work Began | 01-04-23 |
Work Completed | |
Time Computed | 09-07-22 |
Contract Working Days | 240 |
Addl Days Granted | 0 |
Working Days Charged | 130 |
Percent Time Used | 54 |
Contractor(s) |
TI-ZACK CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-034 PBJ CONSTRUCTION (5.82) HIGHWAY 1 LLC (1.73) LONESTAR TRAFFIC SAFETY, LLC (0.60)
|
Contract # | 05223008 |
| Totals | 2857443.00 | 0.00 | 3275982.26 | 99.9 |
|
County | COLORADO |
Highway | US 90 |
From | AT COLORADO RIVER |
To | STR # 0027-01-001 |
CSJ | 0027-01-042 |
Proj ID | BR 2B24(201) |
Work Type | BRIDGE MAINTENANCE |
|
| 0.478 | 7530900.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 01-08-25 |
Contract Working Days | 150 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
CEKRA INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-042 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06243013 |
| Totals | 7530900.00 | 0.00 | 0.00 | 0.0 |
|
County | COLORADO |
Highway | US 90 |
From | AT COLORADO RIVER BRIDGE |
To | STR # 0027-01-001 |
CSJ | 0027-01-044 |
Proj ID | BR 2019(850) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.364 | 8244674.88 | | 11463983.30 | 99.9 |
Work Order | 06-13-19 |
Work Began | 08-05-19 |
Work Completed | |
Time Computed | 08-05-19 |
Contract Working Days | 405 |
Addl Days Granted | 0 |
Working Days Charged | 400 |
Percent Time Used | 98 |
Contractor(s) |
HARPER BROTHERS CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-044 SEMPER STRIPING LLC (0.02) HB FARMER FOUNDATION, LLC (12.51) MCL CONTRACTING, LLC (0.81) DORAN STEEL, INC. (0.93) A1 EROSION CONTROL (0.37) CHOCTAW ERECTORS, INC. (8.27) WILLOW CITY SIGN & RAIL, INC. (1.56) GMJ PAVING CO. (2.99) DORAN STEEL, INC. (0.54) EAST - TEX PIPE AND FAB LLC (0.56) PRIMATE CONSTRUCTION, LP (0.09) JB PINNACLE GROUP, LLC (0.79) PEREZ CONSTRUCTION CO. (0.48) BATTERSON, LLP (0.63) CRAIG & HEIDT, INC. (1.58)
|
Contract # | 05193010 |
| Totals | 8244674.88 | 0.00 | 11463983.30 | 99.9 |
|
County | COLORADO |
Highway | US 90A |
From | FM 102 IN EAGLE LAKE |
To | WHARTON COUNTY LINE |
CSJ | 0027-03-071 |
Proj ID | STP 1702(426) |
Work Type | CONSTRUCT SUPER 2 LANES |
|
| 5.028 | 4487326.99 | | 4879429.99 | 99.9 |
Work Order | 08-11-17 |
Work Began | 10-25-17 |
Work Completed | |
Time Computed | 11-09-17 |
Contract Working Days | 160 |
Addl Days Granted | 0 |
Working Days Charged | 159 |
Percent Time Used | 99 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071 AREA WIDE PROTECTIVE, INC. (0.26) D. I. J. CONSTRUCTION, INC. (1.88) D&S TEXAS ICON CONSTRUCTION (0.35) ENVIRONMENTAL SAFETY SERVICES, INC. (0.27) RIOS TRUCKING CO. (1.40) STRIPE-A-ZONE, INC. (0.27)
|
Contract # | 06173243 |
| Totals | 4487326.99 | 0.00 | 4879429.99 | 99.9 |
|
County | WHARTON |
Highway | UA 90 |
From | 2.58 MI W OF FM 1164 |
To | SH 60 |
CSJ | 0027-04-041 |
Proj ID | STP 1902(164)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 7.341 | 496857.15 | | 721721.31 | 99.9 |
County | WHARTON |
Highway | FM 640 |
From | FM 1161 |
To | FM 102 |
CSJ | 1260-03-013 |
Proj ID | STP 1902(168)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.014 | 527561.27 | | 477578.13 | 90.5 |
County | WHARTON |
Highway | FM 1161 |
From | FM 102 |
To | SH 60 |
CSJ | 1303-01-018 |
Proj ID | STP 1902(168)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 10.399 | 1138794.90 | | 1073137.73 | 94.2 |
County | MATAGORDA |
Highway | FM 2540 |
From | SH 35 |
To | FM 457 |
CSJ | 2525-01-017 |
Proj ID | STP 1902(168)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 4.301 | 448295.64 | | 374263.11 | 83.4 |
Work Order | 10-21-19 |
Work Began | 11-20-19 |
Work Completed | |
Time Computed | 01-19-20 |
Contract Working Days | 210 |
Addl Days Granted | 33 |
Working Days Charged | 243 |
Percent Time Used | 100 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-041 A K FUQUAY CONSTRUCTION (2.24) AREA WIDE PROTECTIVE, INC. (0.98) RUCOBA & MAYA CONSTRUCTION, LLC (62.13) TRAFFIC SIGNS & LINES, LLC (1.76)
|
Contract # | 09193204 |
| Totals | 2611508.96 | 0.00 | 2646700.28 | 99.9 |
|
County | WHARTON ETC |
Highway | US 90A ETC |
From | COLORADO C/L |
To | SH 60 |
CSJ | 0027-04-042 |
Proj ID | STP 2021(545)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 30.950 | 3775419.00 | | 3404941.41 | 94.9 |
Work Order | 09-29-21 |
Work Began | 03-31-22 |
Work Completed | |
Time Computed | 12-28-21 |
Contract Working Days | 300 |
Addl Days Granted | 0 |
Working Days Charged | 484 |
Percent Time Used | 161 |
Contractor(s) |
SJ&J CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-042 CONCAN SERVICES LLC (4.01) GV LANDSCAPE AND CONSTRUCTION LLC (7.38) JB PINNACLE GROUP, LLC (3.23) ROY LEE WALKER (1.74)
|
Contract # | 08213232 |
| Totals | 3775419.00 | 57513.93 | 3404941.41 | 94.9 |
|
County | VICTORIA |
Highway | US 59 |
From | 0.5 MI S OF FM 1686 |
To | SL 463 |
CSJ | 0088-05-085 |
Proj ID | C 88-5-85 |
Work Type | CONSTRUCT FRONTAGE ROADS |
|
| 2.769 | 27884764.50 | | 33910116.58 | 99.9 |
County | VICTORIA |
Highway | US 59 |
From | 0.5 MI S OF FM 1686 |
To | SL 463 |
CSJ | 0088-05-099 |
Proj ID | ROW 88-5-99 |
Work Type | UTILITY ONLY |
|
| 3.329 | 708858.20 | | 655277.20 | 92.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-19-18 |
Work Began | 09-17-18 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 600 |
Addl Days Granted | 205 |
Working Days Charged | 783 |
Percent Time Used | 97 |
Contractor(s) |
SER CONSTRUCTION PARTNERS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085 AREA WIDE PROTECTIVE, INC. (0.02) THIRD COAST SERVICES LLC (5.43) ANGEL BROTHERS HOLDINGS CORP. (28.20) ADCOCK 4 INVESTMENTS, LLC (4.34) M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.59) TITO"S TRUCKING & SONS, LLC (0.00) ROADWAY SPECIALTIES, INC. (1.60) INSITUFORM TECHNOLOGIES, LLC (0.68) MVA CONSTRUCTION LLC (0.00) AIMS COMPANIES (0.03) BORTUNCO (0.22) FARR FOUNDATION, INC. (0.30) HIGHWAY BARRICADES AND SERVICES, LLC (0.40) MONTALVO BRIDGE SYSTEMS, LLC (0.11) DUSTROL, INC. (1.14) WEBER-BALKE FOUNDATION COMPANY, INC (0.40) CURB PLANET INC. (0.05) AARON CONCRETE CONTRACTORS, L.P. (1.52) ROYAL REBAR (0.05) PRIMATE CONSTRUCTION, LP (0.02) TEXAS MATERIALS GROUP, INC. (0.87) ROADWAY CONSTRUCTION, LLC (0.63) WEST TEXAS ROCK RESOURCES, LLC (0.01)
|
Contract # | 05183003 |
| Totals | 28593622.70 | 0.00 | 34565393.78 | 99.9 |
|
County | VICTORIA |
Highway | US 59 |
From | BU 59-T |
To | BU 77S |
CSJ | 0088-05-096 |
Proj ID | F 2B23(079) |
Work Type | WIDEN NON-FREEWAY |
|
| 7.596 | 55933077.83 | | 37761636.66 | 67.5 |
Work Order | 09-19-23 |
Work Began | 11-20-23 |
Work Completed | |
Time Computed | 12-18-23 |
Contract Working Days | 354 |
Addl Days Granted | 2 |
Working Days Charged | 185 |
Percent Time Used | 51 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-096 HIGHWAY BARRICADES AND SERVICES, LLC (0.82) VACA UNDERGROUND UTILITIES INC (1.50) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.63) J&R CONTRACTING SERVICES, INC. (1.72) DEPENDABLE FENCE (1.14) MURRAY CONSTRUCTION (0.17) JB PINNACLE GROUP, LLC (1.67) SK CONCRETE SERVICES LLC (0.01) A. H. BECK FOUNDATION CO., INC. (1.10) TORO BRAVO CONSTRUCTION, LLC (0.06) CAT SKINNER, LLC (0.19) 4E TREE WORX LLC (0.18)
|
Contract # | 08233003 |
| Totals | 55933077.83 | 1855267.25 | 37761636.66 | 67.5 |
|
County | VICTORIA |
Highway | US 59 |
From | US 87 |
To | SH 185 |
CSJ | 0088-05-098 |
Proj ID | C 88-5-98 |
Work Type | FREEWAY OPERATIONAL IMPROVEMENTS |
|
| 1.136 | 13531313.25 | | 14201846.05 | 99.9 |
Work Order | 09-21-21 |
Work Began | 04-07-22 |
Work Completed | |
Time Computed | 12-20-21 |
Contract Working Days | 360 |
Addl Days Granted | 72 |
Working Days Charged | 416 |
Percent Time Used | 96 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-098 BEAVER CONTRACTORS, LLC (7.48) HB FARMER FOUNDATION, LLC (1.49) HIGHWAY BARRICADES AND SERVICES, LLC (1.61) ROADWAY SPECIALTIES, INC. (0.68) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.80) THIRD COAST SERVICES LLC (8.19) BARRICADES UNLIMITED (0.18) ANCORTEX, INC. (1.92) PBX BRIDGE COMPANY (1.07) TORO BRAVO CONSTRUCTION, LLC (0.00) TORO BRAVO CONSTRUCTION, LLC (0.07) PRIMATE CONSTRUCTION, LP (0.03) TECHNICAL STRUCTURAL REPAIR GROUP, LLC (2.77) NELSON INDUSTRIAL SERVICES, INC. (0.00) SURMAC, INC (0.00)
|
Contract # | 08213214 |
| Totals | 13531313.25 | 279319.82 | 14201846.05 | 99.9 |
|
County | VICTORIA ETC |
Highway | US 59 ETC |
From | AT SP 91 |
To | . |
CSJ | 0088-05-110 |
Proj ID | F 2024(584) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1666764.20 | | 497511.34 | 29.8 |
Work Order | 02-05-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 05-05-24 |
Contract Working Days | 75 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-110 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243229 |
| Totals | 1666764.20 | 0.00 | 497511.34 | 29.8 |
|
County | VICTORIA ETC |
Highway | US 59 |
From | 0.116 MILES SW OF TREASURE OAKS RD |
To | 0.209 MILES NE OF POST OAK CIRCLE |
CSJ | 0089-01-099 |
Proj ID | C 89-1-99 |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1868961.17 | | 52740.00 | 2.8 |
Work Order | 06-26-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 12-23-24 |
Contract Working Days | 117 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ALLSTATE SIGNAL & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0089-01-099 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243025 |
| Totals | 1868961.17 | 0.00 | 52740.00 | 2.8 |
|
County | JACKSON |
Highway | US 59 |
From | 0.020 MI N OF FM 710 |
To | 2.470 MI S OF FM 710 |
CSJ | 0089-04-082 |
Proj ID | STP 2B24(076)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.493 | 515002.77 | | 0.00 | 0.0 |
County | JACKSON |
Highway | US 59 |
From | 0.020 MI N OF FM 710 |
To | 1.445 MI N OF FM 710 |
CSJ | 0089-05-049 |
Proj ID | STP 2B24(113)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 1.502 | 250988.26 | | 0.00 | 0.0 |
County | DEWITT |
Highway | US 87 |
From | 2.291 MI S OF US 183 |
To | VICTORIA C/L |
CSJ | 0143-09-072 |
Proj ID | STP 2B24(115)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 10.154 | 1930390.96 | | 0.00 | 0.0 |
County | VICTORIA |
Highway | US 87 |
From | DE WITT C/L |
To | 0.390 MI N OF FM 447 |
CSJ | 0143-10-056 |
Proj ID | STP 2B24(114)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 4.505 | 735244.00 | | 0.00 | 0.0 |
Work Order | 07-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-08-24 |
Contract Working Days | 105 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MASSANA CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0089-04-082 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243217 |
| Totals | 3431625.99 | 0.00 | 0.00 | 0.0 |
|
County | WHARTON |
Highway | US 59 |
From | FM 1163 |
To | 900 FT N OF CR 355 |
CSJ | 0089-06-092 |
Proj ID | STP 2023(977)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 2.462 | 3220561.05 | | 797072.90 | 24.7 |
County | WHARTON |
Highway | US 59 |
From | FM 960 |
To | FM 1163 |
CSJ | 0089-07-164 |
Proj ID | STP 2023(977)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 4.464 | 2938497.09 | | 0.00 | 0.0 |
County | VICTORIA |
Highway | US 77 |
From | 750 FT N OF COLETO CREEK BRIDGE |
To | FLEMING PRAIRIE RD |
CSJ | 0371-01-093 |
Proj ID | STP 2023(977)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.808 | 960841.86 | | 543449.50 | 56.5 |
Work Order | 07-26-23 |
Work Began | 09-10-24 |
Work Completed | |
Time Computed | 10-24-23 |
Contract Working Days | 270 |
Addl Days Granted | 0 |
Working Days Charged | 34 |
Percent Time Used | 12 |
Contractor(s) |
WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-092 MTAM CORPORATION (1.16) QUALITY TURF FARMS, L.C. (0.65) LONESTAR TRAFFIC SAFETY, LLC (0.27) ROADWAY SPECIALTIES, INC. (0.76)
|
Contract # | 06233610 |
| Totals | 7119900.00 | 290867.00 | 1340522.40 | 18.8 |
|