Monthly State Let Construction Report For Yoakum District As Of Nov 10, 2024 Page 8 Of 8

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVICTORIA
HighwaySL 463
FromBU 59T
ToLONE TREE ROAD
CSJ2350-01-060
Proj IDF 2022(146)
Work TypeWIDEN NON-FREEWAY
 
1.62013851977.6712374933.5389.3
Work Order02-14-23
Work Began03-27-23
Work Completed
Time Computed05-15-23
Contract Working Days360
Addl Days Granted0
Working Days Charged334
Percent Time Used92
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-060
A. H. BECK FOUNDATION CO., INC. (4.31)
DORAN STEEL, INC. (0.62)
EGGEMEYER LAND CLEARING, LLC (0.09)
FLASHER EQUIPMENT COMPANY (0.26)
HIGHWAY BARRICADES AND SERVICES, LLC (0.87)
JB PINNACLE GROUP, LLC (4.65)
LONE STAR EROSION CONTROL (0.31)
PRIMATE CONSTRUCTION, LP (0.07)
S&S BRIDGE PAINTING (0.48)
THIRD COAST SERVICES LLC (2.58)
TECHNICAL STRUCTURAL REPAIR GROUP, LLC (0.55)
DEPENDABLE FENCE (1.15)
TEXAS CUTTING & CORING GP, INC. (0.91)
Contract #10223006
Totals13851977.67375453.2612374933.5389.3

CountyMATAGORDA
HighwayFM 2611
FromFM 457
ToBRAZORIA C/L
CSJ2524-01-011
Proj IDSTP 2021(546)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.8972706168.982609218.6997.5
Work Order06-17-21
Work Began09-27-21
Work Completed
Time Computed07-17-21
Contract Working Days90
Addl Days Granted0
Working Days Charged128
Percent Time Used142
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2524-01-011
CEN TEX HYDROSEED, INC. (1.26)
PINNACLE GRINDING AND GROOVING LLC (0.22)
HIGHWAY BARRICADES AND SERVICES, LLC (1.28)
H J HENKE, LLC (0.14)
HIGHWAY 1 LLC (2.53)
J & M CONTRACTING, COMPANY (2.71)
PROFESSIONAL TRAFFIC CONTROL LLC (0.22)
Contract #05213019
Totals2706168.980.002609218.6997.5