Detail Letting Schedule for Archer County (FY 2001)

Texas Department of Transportation Logo (Registered Trademark)
 
 
Last Update: Friday, August 31, 2001
 
Updated from Design & Construction Information System (DCIS) on: August 31, 2001
Archer County (FY 2001)

CCSJ: 0283-02-025

District: Wichita Falls Let Date: FEB 2001
Highway: SH 79 Let Status: Actual
Project ID: CPM 283-2-25 CSJ: 0283-02-025
Description: ACP OVERLAY Handling
Code:
 
Limits From: FM 2224 Fund Cat: 7
Limits To: 1.8 MILES SOUTH Estimate: $254,451
Length: 1.8 Miles Actual: $178,446
 
District: Wichita Falls Let Date: FEB 2001
Highway: SH 79 Let Status: Actual
Project ID: CPM 283-3-16 CSJ: 0283-03-016
Description: ACP OVERLAY Handling
Code:
 
Limits From: 1.8 MILES SOUTH OF FM 2224 Fund Cat: 7
Limits To: SH 25 Estimate: $789,901
Length: 9.3 Miles Actual: $838,797
 
Back...

Totals for 0283-02-025
Length: 11.1 Miles
Estimate: $1,044,352
Actual: $1,017,243

CCSJ: 0903-29-011

District: Wichita Falls Let Date: MAR 2001
Highway: CR Let Status: Actual
Project ID: BR 2000(774)OX CSJ: 0903-29-011
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: CR 156 AT DRAW Fund Cat: 6B
Limits To: . Estimate: $69,277
Length: 0.1 Miles Actual: $70,047
 
District: Wichita Falls Let Date: MAR 2001
Highway: CR Let Status: Actual
Project ID: BR 2000(773)OX CSJ: 0903-29-012
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: CR 189 AT MESQUITE CREEK Fund Cat: 6B
Limits To: . Estimate: $52,265
Length: 0.1 Miles Actual: $53,317
 
Back...

Totals for 0903-29-011
Length: 0.2 Miles
Estimate: $121,542
Actual: $123,364


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project