Letting Schedule for February, 2001 (FY 2001)
![]() |
![]() |
![]() |
![]() |
![]() |
Letting Schedule for February, 2001 (FY 2001) | ||||
Last Update: Friday, August 31, 2001 | ||||
Updated from Design & Construction Information System (DCIS) on: August 31, 2001 | |
February, 2001 (FY 2001) | (see Links) |
SEP 2000 | OCT 2000 | NOV 2000 | DEC 2000 | JAN 2001 | FEB 2001 | MAR 2001 | APR 2001 | MAY 2001 | JUN 2001 | JUL 2001 | AUG 2001 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0894-01-017 | Angelina/ Lufkin |
SH 7 | Actual | $498,326 | 16B | HOT MIX OVERLAY |
0283-02-025 | Archer/ Wichita Falls |
SH 79 | Actual | $1,017,243 | 7 | ACP OVERLAY |
0915-12-274 | Bexar/ San Antonio |
CS | Actual | $790,881 | 4C | SCHOOL SAFETY PROGRAM ON FUNCT CLASS ROADWAYS |
2938-02-019 | Brazoria/ Houston |
FM 2917 | Actual | $2,755,165 | 14 | ACP OVERLAY, WIDEN SHOULDERS, WIDEN BRIDGES AND REPLACE CMP |
0039-06-034 | Cameron/ Pharr |
BU 83-S | Actual | $749,716 | 4A | INSTALL INTERSECTION FLASHING BEACON |
0039-07-185 | Cameron/ Pharr |
US 77 | Actual | $61,347,034 | 13B | WIDEN ROAD AND STRUCTURES TO 6-LANES |
3496-01-007 | Clay/ Wichita Falls |
FM 1954 | Actual | $782,515 | 8A | REHABILITATION OF EXISTING ROAD |
0047-04-019 | Collin/ Dallas |
SH 5 | Actual | $3,784,491 | 7 | ACP OVERLAY |
0047-14-049 | Collin/ Dallas |
US 75 | Actual | $7,441,610 | 3C | CONCRETE PAVEMENT REPAIR AND ACP OVERLAY |
0782-01-027 | Cooke/ Wichita Falls |
FM 678 | Actual | $34,520 | 4A | INSTALL REFLECTIVE PAVEMENT MARKERS |
0581-01-114 | Dallas/ Dallas |
LP 12 | Actual | $116,962 | 16S | LANDSCAPE DEVELOPMENT |
0918-45-302 | Dallas/ Dallas |
VA | Actual | $286,117 | 5 | 37 ON SYSTEM TRAFFIC SIGNAL UPGRADES |
0918-45-360 | Dallas/ Dallas |
VA | Actual | $27,500 | 5 | 7 ON SYSTEM TRAFFIC SIGNAL UPGRADES |
0918-45-361 | Dallas/ Dallas |
VA | Actual | $60,996 | 5 | PE FOR 18 ON SYSTEM TRAFFIC SIGNAL UPGRADES |
0918-45-384 | Dallas/ Dallas |
VA | Actual | $10,000 | 10B | UPGRADE PORTABLE CHANGEABLE MESSAGE SIGN |
0918-45-523 | Dallas/ Dallas |
VA | Actual | $3,522,702 | 5 | TRANSIT VEHICLES FOR DART - ALTERNATIVE FUEL |
0918-45-544 | Dallas/ Dallas |
VA | Actual | $500,000 | 4C | ARCHITECTUAL DESIGN OF THE DALLAS AREA TMC |
0918-45-545 | Dallas/ Dallas |
VA | Actual | $7,000,000 | 4C | IMPLEMENTATION OF SYSTEM REQUIREMENTSBY A SYSTEMS INTEGRATOR |
0918-45-546 | Dallas/ Dallas |
VA | Actual | $125,000 | 4C | DEVELOPMENT OF SYSTEM REQUIREMENTS |
0081-06-025 | Denton/ Dallas |
US 377 | Actual | $73,422 | 10A | TRAFFIC SIGNAL INSTALLATION |
2054-01-013 | Denton/ Dallas |
FM 2164 | Actual | $837,763 | 8A | OVERLAY BASE REPAIR., SEAL COAT & PAV |
0325-01-022 | Dewitt/ Yoakum |
SH 111 | Actual | $382,049 | 14 | RESURFACING ROADWAY AND RECONSTRUCT C & G |
0840-02-020 | Dewitt/ Yoakum |
FM 682 | Actual | $1,928,068 | 14 | RESTORE ROADWAY |
0913-00-055 | Dewitt/ Yoakum |
VA | Actual | $682,600 | 7 | PAINT BRIDGES |
0037-07-014 | Dimmit/ Laredo |
LP 225 | Actual | $1,707,392 | 14 | RECONSTRUCT ROADWAY |
0922-49-002 | Dimmit/ Laredo |
CR | Actual | $463,757 | 6B | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
0042-08-049 | Donley/ Childress |
US 287 | Actual | $170,280 | 7 | MICROSURFACE |
0572-01-051 | Ector/ Odessa |
SP 450 | Actual | $249,258 | 4A | INSTALL TRAFFIC SIGNAL |
0080-01-046 | Erath/ Fort Worth |
US 377 | Actual | $1,363,233 | 7 | ROTOMILL EXISTING PLANT MIX SEAL AND OVERLAY |
0188-09-027 | Fort Bend/ Houston |
FM 723 | Actual | $3,182,299 | 4G | RAILROAD GRADE SEPARATION AND APPROACHES |
0017-16-003 | Frio/ San Antonio |
BI 35-D | Actual | $2,173,599 | 7 | SEAL COAT & OVERLAY |
0367-06-053 | Galveston/ Houston |
SH 87 | Actual | $213,585 | 11 | PROVIDE CCTV SURVEILLANCE |
0912-73-062 | Galveston/ Houston |
CS | Actual | $320,997 | 13D | RECONSTRUCT ROADWAY |
0912-73-068 | Galveston/ Houston |
VA | Actual | $500,000 | 5 | PURCHASE 5 MID-SIZE LOW EMMISSION DIESEL TRANSIT VEHICLES |
0912-73-075 | Galveston/ Houston |
VA | Actual | $486,757 | 14 | REPLACE LIGHTING SYSTEM |
0912-73-095 | Galveston/ Houston |
VA | Actual | $187,500 | 5 | FY 2000 - ELECTRIC BUS DEMO: OPERATING ASSISTANCE FOR 2 BUSES |
0978-02-045 | Galveston/ Houston |
FM 517 | Actual | $5,718,760 | 15 | WIDEN FROM TWO LANES TO 4-LANE DIVIDED, CURB & GUTTER |
1562-04-011 | Grimes/ Bryan |
FM 2620 | Actual | $230,335 | 7 | CONSTRUCTION OF A SEAL COAT CONSISTING OF A ONE COURSE |
0042-09-105 | Hall/ Childress |
US 287 | Actual | $620,851 | 7 | MILL & IN-LAY |
0043-04-061 | Hardeman/ Childress |
US 287 | Actual | $9,269,000 | 4B | CONSTRUCT NEW SAFETY REST AREA |
0050-06-058 | Harris/ Houston |
US 290 | Actual | $8,721,051 | 11 | CONSTRUCT INTERIM GRADE SEPARATION |
0178-01-028 | Harris/ Houston |
SH 35 | Actual | $650,871 | 11 | JOINT AND CRACK SEAL FULL DEPTH PVMT REPAIR |
0271-14-199 | Harris/ Houston |
IH 610 | Actual | $255,689 | 10A | INSTALLATION OF A TRAFFIC SIGNAL AT EACH FRONTAGE ROAD |
0271-17-139 | Harris/ Houston |
IH 610 | Actual | $475,986 | 12 | INSTALL HIGH MAST LIGHTING |
0912-00-196 | Harris/ Houston |
VA | Actual | $1,514,634 | 11 | STRIPING |
0912-71-585 | Harris/ Houston |
VA | Actual | $75,000 | 10B | INVENTORY OF EXISTING COMMUNICATIONS CABLE |
0912-71-729 | Harris/ Houston |
VA | Actual | $669,330 | 11 | SMALL SIGN UPGRADE |
0912-71-730 | Harris/ Houston |
VA | Actual | $1,548,459 | 11 | STRIPING |
0980-02-016 | Harris/ Houston |
FM 526 | Actual | $1,048,386 | 7 | SPOT BASE REPAIR, ACP O /L & PAVEMENT MARKINGS |
1062-04-048 | Harris/ Houston |
FM 2100 | Actual | $2,106,042 | 7 | BASE REPAIR, MILLING, ACP OVERLAY AND PAVEMENT MARKS |
1685-01-079 | Harris/ Houston |
FM 1960 | Actual | $75,000 | 14 | INSTALLATION OF CHANGEABLE LANE ASSIGNMENT SYSTEM |
0495-08-074 | Harrison/ Atlanta |
IH 20 | Actual | $3,187,242 | 2 | REHABILITATE INTERSTATE MAINLANES AND RAMPS |
0108-04-030 | Henderson/ Tyler |
SH 19 | Actual | $645,729 | 7 | RESURFACE ROADWAY WITH ASPHALTIC CONCRETE |
0861-05-016 | Hidalgo/ Pharr |
FM 491 | Actual | $3,868,326 | 4C | RECONSTRUCT AND ADD SHOULDERS |
0921-02-085 | Hidalgo/ Pharr |
VA | Actual | $534,790 | 15 | CONSTRUCT ALTERNATE COMMERCIAL TRUCK BYPASS, ENLARGE CUSTOMS |
2831-01-006 | Hidalgo/ Pharr |
FM 2812 | Actual | $2,816,515 | 14 | RECONSTRUCT AND ADD SHOULDERS |
0080-04-073 | Hood/ Fort Worth |
US 377 | Actual | $389,580 | 4A | ADD LEFT TURN SIGNAL PHASE AND LEFT TURN LANE |
0385-04-027 | Hood/ Fort Worth |
SH 144 | Actual | $8,797,269 | 4F | WIDEN FROM 2 LANE TO 4 LANE DIVIDED |
0379-01-038 | Hutchinson/ Amarillo |
SH 136 | Actual | $679,953 | 6A | REPLACE EXISTING BRIDGE AND APPROACHES |
0391-06-019 | Jack/ Fort Worth |
SH 148 | Actual | $3,214,788 | 14 | ADDING SHOULDERS AND ESTENDING CULVERT STRUCTURES |
0173-02-033 | Kaufman/ Dallas |
SH 34 | Actual | $327,925 | 14 | HOT MIX, BASE WORK, SHOULDER WORK, AND PAVEMENT MARKINGS |
0495-01-048 | Kaufman/ Dallas |
IH 20 | Actual | $359,452 | 2 | GUIDE SIGN REFURBISHING |
0751-01-032 | Kaufman/ Dallas |
FM 148 | Actual | $457,212 | 4A | RECONSTRUCT INTERSECTION |
1690-01-097 | Lamar/ Paris |
US 82 | Actual | $230,337 | 4A | SAFETY LIGHTING |
0251-04-020 | Lampasas/ Brownwood |
US 281 | Actual | $325,463 | 7 | MICROSURFACE |
0601-04-010 | Liberty/ Beaumont |
FM 1009 | Actual | $346,208 | 8A | RESTORE EXISTING ROADWAY |
1146-01-023 | Liberty/ Beaumont |
FM 834 | Actual | $598,054 | 8A | WIDEN EXISTING LANES FROM 9' TO 12' AND ADD A 1' SHOULDER |
0348-11-010 | Live Oak/ Corpus Christi |
FM 99 | Actual | $1,826,572 | 11 | REHAB.EXIST PAVEMENT WITH CEMENT TREAT & TWO COURSE SURF TREAT |
0905-06-037 | Lubbock/ Lubbock |
CS | Actual | $326,392 | 4B | TRANSPORTATION ENHANCEMENT PROJECT |
0300-01-069 | Maverick/ Laredo |
US 277 | Actual | $3,407,856 | 7 | FOR THE CONSTRUCTION OF ASPHALTIC CONCRETE OVERLAY |
0922-10-018 | Maverick/ Laredo |
CR | Actual | $109,640 | 6B | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
1229-06-005 | Maverick/ Laredo |
FM 2030 | Actual | $258,064 | 6A | FOR CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING BRIDGE |
0463-02-057 | Midland/ Odessa |
SH 158 | Actual | $169,201 | 16S | LANDSCAPE DEVELOPMENT |
0013-04-015 | Montague/ Wichita Falls |
US 81 | Actual | $2,724,023 | 7 | EXTENDING STRUCTURES AND ASPHALTIC CONCRETE PAVEMENT OVERLAY |
0912-37-106 | Montgomery/ Houston |
CR | Actual | $7,927,228 | 4D | CONSTRUCT 4 LANES DIVIDED AND PANTHER CREEK BRIDGE |
0305-02-038 | Newton/ Beaumont |
SH 87 | Actual | $2,689,840 | 13B | REHABILITATE ROADWAY, WIDEN STRUCTURES AND ADD SHOULDERS |
0102-02-085 | Nueces/ Corpus Christi |
US 77 | Actual | $8,692,784 | 14 | REHABILITATE ROADWAY |
0177-01-085 | Polk/ Lufkin |
US 59 | Actual | $222,117 | 16B | EROSION CONTROL |
0911-04-031 | Polk/ Lufkin |
CR | Actual | $143,571 | 6B | REPLACE BRIDGE AND APPROACHES |
0904-00-075 | Potter/ Amarillo |
VA | Actual | $360,159 | 7 | MISC WORK |
0067-01-074 | Randall/ Amarillo |
US 87 | Actual | $1,198,369 | 7 | OVERLAY |
0738-01-048 | Refugio/ Corpus Christi |
FM 136 | Actual | $2,050,520 | 8A | OVERLAY |
3332-01-001 | San Augustine/ Lufkin |
FM 3229 | Actual | $1,429,681 | 8B | CONSTRUCT NEW FARM TO MARKET ROAD / EXTEND FARM TO MARKET |
0372-01-082 | San Patricio/ Corpus Christi |
US 77 | Actual | $191,541 | 6A | REPLACE BRIDGE CLASS CULVERT |
0123-08-009 | Shelby/ Lufkin |
FM 415 | Actual | $3,218,060 | 14 | WIDEN EXISTING ROADWAY |
0911-39-015 | Shelby/ Lufkin |
VA | Actual | $151,914 | 10A | INSTALL COUNTY ROAD SIGNS |
0008-14-097 | Tarrant/ Fort Worth |
IH 820 | Actual | $200,470 | 11 | INSTALL CONCRETE TRAFFIC BARRIER |
0008-14-099 | Tarrant/ Fort Worth |
IH 820 | Actual | $3,371,003 | 7 | OVERLAY |
0014-02-038 | Tarrant/ Fort Worth |
IH 35W | Actual | $1,452,800 | 2 | RELOCATE EXIT RAMP |
0014-15-027 | Tarrant/ Fort Worth |
US 287 | Actual | $3,285,708 | 7 | OVERLAY_MAIN LANES |
0747-03-073 | Tarrant/ Fort Worth |
FM 157 | Actual | $9,838,647 | 4C | CONSTRUCT 6 LANE DIVIDED ROADWAY |
0902-48-382 | Tarrant/ Fort Worth |
CS | Actual | $3,120,327 | 15 | WIDEN & EXTEND MEACHAM BOULEVARD AS A 4 LANE DIVIDED SECTION |
0902-48-383 | Tarrant/ Fort Worth |
CS | Actual | $633,137 | 6B | REPLACE BRIDGE AND APPROACHES |
2266-02-108 | Tarrant/ Fort Worth |
SH 360 | Actual | $253,157 | 5 | TRAFFIC SIGNALS INSTALL NEW AND SIGNAL TIMING OPTIMIZATION |
0015-13-286 | Travis/ Austin |
IH 35 | Actual | $479,056 | 2 | MILL SHOULDERS AND RELOCATE INLETS |
0914-00-165 | Travis/ Austin |
VA | Actual | $18,690 | 10A | TRAFFIC COUNTS |
0914-04-048 | Travis/ Austin |
VA | Actual | $803,500 | 4B | MOORE'S CROSSING BRIDGE_IN AUSTIN |
0914-04-159 | Travis/ Austin |
CS | Actual | $27,720 | 4C | DESIGN & CONST SIDEWALK ON WEST SIDE |
0520-05-035 | Upshur/ Atlanta |
SH 155 | Actual | $4,348,840 | 7 | RESURFACE EXISTING 2-LANE RURAL HIGHWAY |
0369-01-025 | Uvalde/ San Antonio |
SH 127 | Actual | $3,294,326 | 4F | REHABILITATE AND WIDEN NARROW PAVEMENT AND SHOULDER |
0022-04-018 | Val Verde/ Laredo |
US 90 | Actual | $3,492,843 | 7 | FOR THE CONSTRUCTION OF SEAL COAT TYPE WORK |
0109-09-051 | Walker/ Bryan |
SH 19 | Actual | $34,944 | 4A | MISCELLANEOUS WORK CONSISTING OF THE INSTALLATION OF |
0212-02-029 | Walker/ Bryan |
SH 30 | Actual | $4,746,791 | 15 | RECONSTRUCT INTERCHANGE TO INCLUDE U-TURNS, LEFT TURN |
0912-56-032 | Waller/ Houston |
VA | Actual | $924,450 | 11 | SMALL SIGN UPGRADE |
1687-01-013 | Waller/ Houston |
FM 1736 | Actual | $1,482,021 | 8A | BASE REPAIR, WIDEN SUBGRADE, PAVE SHOULDER AND ACP OVERLAY |
1405-04-016 | Washington/ Bryan |
FM 1155 | Actual | $1,298,185 | 14 | RESTORATION CONSISTING OF GRADING, BASE, SURFACE AND |
2830-02-008 | Washington/ Bryan |
FM 1697 | Actual | $1,262,046 | 14 | RESTORATION CONSISTING OF GRADING, BASE AND SURFACE TREAT |
0903-03-060 | Wichita/ Wichita Falls |
VA | Actual | $722,686 | 4B | HOLLIDAY CREEK PEDESTRIAN AND BICYCLE TRAIL (PHASE 2) |
0312-04-024 | Wise/ Fort Worth |
FM 730 | Actual | $888,140 | 6B | REPLACE BRIDGE AND APPROACHES |
0902-20-048 | Wise/ Fort Worth |
CR | Actual | $448,536 | 6B | REPLACE BRIDGE AND APPROACHES |
0878-01-009 | Zavala/ Laredo |
FM 393 | Actual | $731,494 | 8A | FOR THE CONSTRUCTION AND REHABILITTION OF AN EXISTING |
Top... Back... Letting Schedule Doing Business with TxDOT |