Detail Letting Schedule for Crane County (FY 2003)
| |
| Detail Letting Schedule for Crane County (FY 2003) |
| |
| Last Update: Thursday, August 28, 2003 |
CCSJ: 0600-03-019
|
| District: |
Odessa |
Let Date: |
AUG 2003 |
| Highway: |
SH 329 |
Let Status: |
Actual |
| Project ID: |
C 600-3-19 |
CSJ: |
0600-03-019 |
| Description: |
ROADWAY REHABILITATION |
Handling Code: |
|
| Limits From: |
0.6 MILES WEST OF US 385 |
Fund Cat: |
1 |
| Limits To: |
US 385 |
Estimate: |
$582,454 |
| Length: |
0.5 Miles |
Actual: |
$526,941 |
| |
| District: |
Odessa |
Let Date: |
AUG 2003 |
| Highway: |
SH 329 |
Let Status: |
Actual |
| Project ID: |
C 600-4-11 |
CSJ: |
0600-04-011 |
| Description: |
ROADWAY REHABILITATION |
Handling Code: |
|
| Limits From: |
US 385 |
Fund Cat: |
1 |
| Limits To: |
0.4 MILES EAST OF US 385 |
Estimate: |
$309,379 |
| Length: |
0.4 Miles |
Actual: |
$269,667 |
| |
Bid Tabulations Award Status Back...
|
Totals for 0600-03-019 |
| Length: |
0.9 Miles |
| Estimate: |
$891,833 |
| Actual: |
$796,608 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|