Detail Letting Schedule for Morris County (FY 2003)
Detail Letting Schedule for Morris County (FY 2003) | ||||
Last Update: Thursday, August 28, 2003 |
Morris County (FY 2003) |
CCSJ: 0010-08-046 | |||
District: | Atlanta | Let Date: | JUN 2003 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | C 10-8-46 | CSJ: | 0010-08-046 |
Description: | RECONSTRUCT PEDESTRIAN FACILITIES W / AESTHETIC TREATMENTS | Handling Code: |
|
Limits From: | SENTER STREET | Fund Cat: | 10 |
Limits To: | FM 144 (SOUTH) | Estimate: | $149,072 |
Length: | 0.1 Miles | Actual: | $154,622 |
Bid Tabulations Back... |
Totals for 0010-08-046 | ||
---|---|---|---|
Length: | 0.1 Miles | ||
Estimate: | $149,072 | ||
Actual: | $154,622 | ||
CCSJ: 0392-01-056 | |||
District: | Atlanta | Let Date: | NOV 2002 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2003(20)HES | CSJ: | 0392-01-056 |
Description: | INSTALL INTERSECTION FLASHING BEACON | Handling Code: |
|
Limits From: | AT FM 144 INTERSECTION IN LONE STAR | Fund Cat: | 8 |
Limits To: | . | Estimate: | $50,512 |
Length: | 0.1 Miles | Actual: | $26,578 |
District: | Atlanta | Let Date: | NOV 2002 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2003(20)HES | CSJ: | 0392-02-068 |
Description: | IMPROVE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT FM 450 INTERSECTION IN ORE CITY | Fund Cat: | 8 |
Limits To: | . | Estimate: | $59,450 |
Length: | 0.1 Miles | Actual: | $57,737 |
District: | Atlanta | Let Date: | NOV 2002 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2003(20)HES | CSJ: | 0392-02-069 |
Description: | IMPROVE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT SH 155 INTERSECTION | Fund Cat: | 8 |
Limits To: | . | Estimate: | $68,347 |
Length: | 0.1 Miles | Actual: | $67,803 |
District: | Atlanta | Let Date: | NOV 2002 |
Highway: | SH 154 | Let Status: | Actual |
Project ID: | STP 2003(20)HES | CSJ: | 0401-04-027 |
Description: | INSTALL INTERSECTION FLASHING BEACON | Handling Code: |
|
Limits From: | AT FM 1795 INTERSECTION | Fund Cat: | 8 |
Limits To: | . | Estimate: | $14,608 |
Length: | 0.1 Miles | Actual: | $11,858 |
District: | Atlanta | Let Date: | NOV 2002 |
Highway: | SH 300 | Let Status: | Actual |
Project ID: | STP 2003(20)HES | CSJ: | 1385-01-026 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT FM 1844 INTERSECTION | Fund Cat: | 8 |
Limits To: | NORTH OF LONGVIEW | Estimate: | $54,711 |
Length: | 0.1 Miles | Actual: | $53,479 |
Back... |
Totals for 0392-01-056 | ||
Length: | 0.5 Miles | ||
Estimate: | $247,628 | ||
Actual: | $217,455 | ||
CCSJ: 0610-04-030 | |||
District: | Atlanta | Let Date: | AUG 2003 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | C 610-4-30 | CSJ: | 0610-04-030 |
Description: | RESURFACE INTERSTATE MAINLANES | Handling Code: |
|
Limits From: | TITUS COUNTY LINE | Fund Cat: | 1 |
Limits To: | WEST END OF SULPHUR RIVER BRIDGE | Estimate: | $395,149 |
Length: | 7.3 Miles | Actual: | $398,373 |
Bid Tabulations Award Status Back... |
Totals for 0610-04-030 | ||
Length: | 7.3 Miles | ||
Estimate: | $395,149 | ||
Actual: | $398,373 |
|
|