Detail Letting Schedule for Reagan County (FY 2003)
| |
| Detail Letting Schedule for Reagan County (FY 2003) |
| |
| Last Update: Thursday, August 28, 2003 |
CCSJ: 0077-01-023
|
| District: |
San Angelo |
Let Date: |
AUG 2003 |
| Highway: |
US 67 |
Let Status: |
Actual |
| Project ID: |
C 77-1-23 |
CSJ: |
0077-01-023 |
| Description: |
REHABILITATE EXISTING ROADWAY |
Handling Code: |
|
| Limits From: |
THE IRION COUNTY LINE |
Fund Cat: |
1 |
| Limits To: |
1.1 MILES NORTH OF SH 137 |
Estimate: |
$1,331,157 |
| Length: |
10.8 Miles |
Actual: |
$2,006,031 |
| |
| District: |
San Angelo |
Let Date: |
AUG 2003 |
| Highway: |
US 67 |
Let Status: |
Actual |
| Project ID: |
C 77-2-29 |
CSJ: |
0077-02-029 |
| Description: |
REHABILITATE EXISTING ROADWAY |
Handling Code: |
|
| Limits From: |
4.1 MILES NORTH OF SH 163 |
Fund Cat: |
1 |
| Limits To: |
THE REAGAN COUNTY LINE |
Estimate: |
$1,345,787 |
| Length: |
10.5 Miles |
Actual: |
$1,681,894 |
| |
Bid Tabulations Award Status Back...
|
Totals for 0077-01-023 |
| Length: |
21.3 Miles |
| Estimate: |
$2,676,944 |
| Actual: |
$3,687,925 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|