Detail Letting Schedule for Comal County (FY 2006)
| Detail Letting Schedule for Comal County (FY 2006) | ||||
| Last Update: Monday, August 28, 2006 | 
| Comal County (FY 2006) | 
| CCSJ: 0016-05-102 | |||
| District: | San Antonio | Let Date: | SEP 2005 | 
| Highway: | IH 35 | Let Status: | Actual | 
| Project ID: | CL 16-5-102 | CSJ: | 0016-05-102 | 
| Description: | INSTALL IRRIGATION AND LANDSCAPING | Handling Code: | |
| Limits From: | 0.189 MI S OF SCHMIDT STREET | Fund Cat: | 10 | 
| Limits To: | 0.093 MI NORTH OF FM 725 | Estimate: | $380,810 | 
| Length: | 2.3 Miles | Actual: | $457,580 | 
| Back... | Totals for 0016-05-102 | ||
|---|---|---|---|
| Length: | 2.3 Miles | ||
| Estimate: | $380,810 | ||
| Actual: | $457,580 | ||
| CCSJ: 0016-19-020 | |||
| District: | San Antonio | Let Date: | JUN 2006 | 
| Highway: | FM 482 | Let Status: | Actual | 
| Project ID: | SFT 16-19-20 | CSJ: | 0016-19-020 | 
| Description: | WIDEN NARROW ROADWAY AND ADD SHOULDERS | Handling Code: | |
| Limits From: | 0.4 MI W OF CR 723 (KRUEGER CANYON) | Fund Cat: | 1 | 
| Limits To: | 0.2 MI W OF CR 724 (SOLMS RD) | Estimate: | $1,464,188 | 
| Length: | 1.4 Miles | Actual: | $1,548,908 | 
| Bid Tabulations Back... | Totals for 0016-19-020 | ||
| Length: | 1.4 Miles | ||
| Estimate: | $1,464,188 | ||
| Actual: | $1,548,908 | ||
| CCSJ: 0470-03-017 | |||
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | FM 1863 | Let Status: | Actual | 
| Project ID: | STP 2005(730) | CSJ: | 0470-01-016 | 
| Description: | REHABING EXISTING ROADWAY AND WIDEN SHOULDERS | Handling Code: | |
| Limits From: | 2.7 MI W OF SH 46 (MISSION VALLEY R | Fund Cat: | 1 | 
| Limits To: | BEXAR C/L | Estimate: | $5,046,989 | 
| Length: | 8.7 Miles | Actual: | $5,182,664 | 
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | FM 1863 | Let Status: | Actual | 
| Project ID: | STP 2005(730) | CSJ: | 0470-02-011 | 
| Description: | REHABING EXISTING ROADWAY AND WIDEN SHOULDERS | Handling Code: | |
| Limits From: | COMAL/BEXAR C/L (E) | Fund Cat: | 1 | 
| Limits To: | BEXAR/COMAL C/L (W) | Estimate: | $241,718 | 
| Length: | 0.5 Miles | Actual: | $253,259 | 
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | FM 1863 | Let Status: | Actual | 
| Project ID: | STP 2005(730) | CSJ: | 0470-03-015 | 
| Description: | REHAB, WIDEN NARROW ROADWAY & ADD SHOULDERS | Handling Code: | |
| Limits From: | US 281 | Fund Cat: | 11 | 
| Limits To: | BEXAR COUNTY LINE | Estimate: | $1,877,494 | 
| Length: | 0.0 Miles | Actual: | $1,680,008 | 
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | FM 1863 | Let Status: | Actual | 
| Project ID: | STP 2005(729)SFT | CSJ: | 0470-03-017 | 
| Description: | WIDEN NARROW ROADWAY AND ADD SHOULDERS | Handling Code: | |
| Limits From: | US 281 | Fund Cat: | 1 | 
| Limits To: | BEXAR COUNTY LINE | Estimate: | $1,458,245 | 
| Length: | 5.2 Miles | Actual: | $1,937,873 | 
| Back... | Totals for 0470-03-017 | ||
| Length: | 14.4 Miles | ||
| Estimate: | $8,624,446 | ||
| Actual: | $9,053,804 | ||
| CCSJ: 0857-01-022 | |||
| District: | San Antonio | Let Date: | DEC 2005 | 
| Highway: | FM 306 | Let Status: | Actual | 
| Project ID: | STP 2006(080) | CSJ: | 0857-01-022 | 
| Description: | RECONFIGURE INTERSECTION | Handling Code: | |
| Limits From: | AT FM 3424 | Fund Cat: | 1 | 
| Limits To: | . | Estimate: | $2,494,831 | 
| Length: | 0.6 Miles | Actual: | $2,495,587 | 
| Back... | Totals for 0857-01-022 | ||
| Length: | 0.6 Miles | ||
| Estimate: | $2,494,831 | ||
| Actual: | $2,495,587 | ||
| CCSJ: 1273-01-028 | |||
| District: | San Antonio | Let Date: | JUN 2006 | 
| Highway: | FM 1102 | Let Status: | Actual | 
| Project ID: | SFT 1273-1-28 | CSJ: | 1273-01-028 | 
| Description: | WIDEN NARROW ROADWAY AND ADD SHOULDERS | Handling Code: | |
| Limits From: | FM 2439 | Fund Cat: | 1 | 
| Limits To: | 0.2 MI W OF FM 2439 | Estimate: | $1,465,871 | 
| Length: | 0.9 Miles | Actual: | $1,421,277 | 
| Bid Tabulations Back... | Totals for 1273-01-028 | ||
| Length: | 0.9 Miles | ||
| Estimate: | $1,465,871 | ||
| Actual: | $1,421,277 | ||
| CCSJ: 1728-01-005 | |||
| District: | San Antonio | Let Date: | OCT 2005 | 
| Highway: | FM 3424 | Let Status: | Actual | 
| Project ID: | C 1728-1-5 | CSJ: | 1728-01-005 | 
| Description: | REHAB & WIDEN NARROW PAVEMENT & SHOULDERS | Handling Code: | |
| Limits From: | 0.056 MI NORTH OF FM 306 | Fund Cat: | 1 | 
| Limits To: | RM 32 | Estimate: | $2,183,084 | 
| Length: | 1.3 Miles | Actual: | $2,516,876 | 
| Back... | Totals for 1728-01-005 | ||
| Length: | 1.3 Miles | ||
| Estimate: | $2,183,084 | ||
| Actual: | $2,516,876 | ||
| CCSJ: 2021-01-011 | |||
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | FM 1044 | Let Status: | Actual | 
| Project ID: | STP 2006(024) | CSJ: | 2021-01-011 | 
| Description: | WIDEN NARROW ROADWAY AND ADD SHOULDERS | Handling Code: | |
| Limits From: | GUADALUPE/COMAL COUNTY LINE | Fund Cat: | 1 | 
| Limits To: | IH 35 | Estimate: | $914,306 | 
| Length: | 1.4 Miles | Actual: | $962,431 | 
| Back... | Totals for 2021-01-011 | ||
| Length: | 1.4 Miles | ||
| Estimate: | $914,306 | ||
| Actual: | $962,431 | ||
| CCSJ: 8403-15-001 | |||
| District: | San Antonio | Let Date: | NOV 2005 | 
| Highway: | MH | Let Status: | Actual | 
| Project ID: | BH 96(344)OX | CSJ: | 8403-15-001 | 
| Description: | REPLACING BRIDGE & APPROACHES | Handling Code: | |
| Limits From: | IN NEW BRAUNFELS ON LANDA PARK DRIV | Fund Cat: | 6 | 
| Limits To: | AT COMAL RIVER | Estimate: | $309,311 | 
| Length: | 0.0 Miles | Actual: | $493,023 | 
| Back... | Totals for 8403-15-001 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $309,311 | ||
| Actual: | $493,023 | ||
| 
 
 | 
|  |