| CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | 
|---|---|---|---|---|---|---|
| 0911-00-045 | Angelina/ Lufkin | VA | Actual | $1,610,185 | 9 | RENOVATE RAILROAD DEPOT | 
| 0133-07-023 | Archer/ Wichita Falls | SH 114 | Actual | $9,693,312 | 1 | SEAL COAT | 
| 0042-05-029 | Armstrong/ Amarillo | US 287 | Actual | $13,942,852 | 1 | REHABILITATE EXISTING ROADWAY | 
| 0016-08-027 | Bexar/ San Antonio | LP 368 | Actual | $1,958,596 | 1 | INSTALL RAISED MEDIAN & BRIDGE RAIL RETROFIT @ HARRY | 
| 0017-02-064 | Bexar/ San Antonio | IH 35 | Actual | $1,650,643 | 1 | SIGN REFURBISHMENT | 
| 0017-10-224 | Bexar/ San Antonio | IH 35 | Actual | $630,932 | 1 | BRIDGE RAIL RETROFIT @ RITTIMAN, EISENHAUER & WALZEM | 
| 0072-07-054 | Bexar/ San Antonio | IH 10 | Actual | $122,508 | 10 | LANDSCAPING AND IRRIGATION | 
| 0072-12-176 | Bexar/ San Antonio | IH 10 | Actual | $1,103,155 | 1 | RECONFIGURING INTERSECTION (N'BD RT TURN LN & S'BD ACCEL LN | 
| 0521-01-043 | Bexar/ San Antonio | LP 13 | Actual | $2,406,452 | 1 | BASE REPAIR, PLANING, SEALCOAT, OVERLAY & PAV MARK, MEDIANS | 
| 0521-06-124 | Bexar/ San Antonio | IH 410 | Actual | $12,388,367 | 1 | REHAB EXISTING MAINLANES AND RECONSTRUCT SHOULDERS | 
| 0915-12-363 | Bexar/ San Antonio | CS | Actual | $4,108,413 | ROW | REHAB & WIDEN NARROW PAVEMENT (CURB, SDWK, DRAINAGE) | 
| 0049-09-064 | Brazos/ Bryan | BS 6-R | Actual | $9,696,259 | 1 | SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT AND | 
| 0116-04-091 | Brazos/ Bryan | SH 21 | Actual | $259,963 | 10 | MISCELLANEOUS WORK CONSISTING OF CONCRETE REMOVAL, CONCRETE | 
| 0255-03-032 | Brooks/ Pharr | US 281 | Actual | $593,638 | 1 | ADD LEFT TURN LANE | 
| 0923-00-047 | Brown/ Brownwood | VA | Actual | $596,826 | 1 | THERMOPLASTIC STRIPING | 
| 0753-02-020 | Carson/ Amarillo | FM 293 | Actual | $4,997,336 | 1 | OVERLAY | 
| 0010-10-024 | Cass/ Atlanta | US 67 | Actual | $8,348,610 | 1 | SEAL COAT | 
| 0218-03-079 | Cass/ Atlanta | US 59 | Actual | $630,252 | 8 | SAFETY TREAT FIXED OBJECTS, INSTALL PROTECTION & MODERNIZE | 
| 3132-01-008 | Collin/ Dallas | FM 3038 | Actual | $184,223 | 10 | LANDSCAPE DEVELOPMENT | 
| 0271-01-072 | Colorado/ Yoakum | IH 10 | Actual | $2,810,000 | 1 | ASPHALTIC CONCRETE PAVEMENT | 
| 1728-01-005 | Comal/ San Antonio | FM 3424 | Actual | $2,516,876 | 1 | REHAB & WIDEN NARROW PAVEMENT & SHOULDERS | 
| 0288-01-032 | Comanche/ Brownwood | SH 16 | Actual | $1,010,307 | 11 | CURB AND GUTTER, SIDEWALK, PLANE, ACP OVERLAY, AND SIGNAL | 
| 0009-03-042 | Dallas/ Dallas | SH 66 | Actual | $191,725 | 10 | LANDSCAPE DEVELOPMENT | 
| 0918-00-073 | Dallas/ Dallas | VA | Actual | $4,044,643 | 1 | SEALCOAT | 
| 0918-00-135 | Dallas/ Dallas | VA | Actual | $6,440,011 | 1 | SEALCOAT | 
| 0918-45-415 | Dallas/ Dallas | CR | Actual | $513,529 | 6 | REPLACE BR & APPRS | 
| 0918-45-528 | Dallas/ Dallas | VA | Actual | $1,257,618 | 9 | BEAUTIFYING & HUMANIZING THE US 75 / DART RAIL GREENVILLE AVE | 
| 0918-45-730 | Dallas/ Dallas | VA | Actual | $721,256 | 7 | CONSTRUCTION OF ENTRANCE TO DALLAS AREA TRANSPORTATION | 
| 1068-04-136 | Dallas/ Dallas | IH 30 | Actual | $590,520 | 10 | DALLAS - FORT WORTH REGION VALUE PRICING DEPLOYMENT PLAN IH 30 | 
| 2374-02-110 | Dallas/ Dallas | IH 635 | Actual | $45,942,288 | ROW | CONSTRUCT I / C @ TOWN EAST BLVD, REPLACE BRIDGE, ADD A | 
| 0918-46-108 | Denton/ Dallas | VA | Actual | $1,268,018 | 10 | REBUILD MAIN PARK ROAD ACCESS FACILITIES BELOW DAM APPROX 1, | 
| 0715-03-012 | Dewitt/ Yoakum | FM 108 | Actual | $3,473,359 | 1 | RESTORE ROADWAY | 
| 0001-02-046 | El Paso/ El Paso | SH 20 | Actual | $1,234,271 | 10 | LANDSCAPE WORK | 
| 0924-06-166 | El Paso/ El Paso | CS | Actual | $8,922,000 | 10 | REHABILITATION OF INTERNATIONAL BRIDGES - SIB LOAN | 
| 0924-06-191 | El Paso/ El Paso | CS | Actual | $11,704,122 | 7 | RECONSTRUCT 6 DOWNTOWN STREETS | 
| 0924-06-258 | El Paso/ El Paso | CS | Actual | $25,608,709 | 10 | CONSTRUCT INTERSECTION IMPROVEMENTS BETWEEN BIGGS ARMY | 
| 0250-04-039 | Erath/ Fort Worth | US 281 | Actual | $6,522,936 | 1 | SEAL COAT | 
| 0848-02-007 | Frio/ San Antonio | FM 462 | Actual | $2,222,149 | 1 | WIDEN NARROW RDWY & ADD SHOULDERS | 
| 0914-19-010 | Gillespie/ Austin | CS | Actual | $3,834,228 | 6 | ADD LEFT TURN LANE & SHOULDERS | 
| 0088-03-030 | Goliad/ Corpus Christi | US 59 | Actual | $49,412,254 | 1 | CONSTRUCT ADDITIONAL 2 LANES | 
| 1196-03-013 | Goliad/ Corpus Christi | FM 884 | Actual | $1,487,916 | 1 | REHABILITATE ROADWAY | 
| 1843-01-017 | Goliad/ Corpus Christi | FM 1961 | Actual | $819,250 | 6 | REPLACE BRIDGE AND APPROACHES | 
| 0913-22-025 | Gonzales/ Yoakum | CR | Actual | $606,047 | 6 | REPLACE BRIDGE AND APPROACHES | 
| 0275-05-040 | Gray/ Amarillo | IH 40 | Actual | $5,572,481 | 11 | OVERLAY | 
| 0643-05-038 | Grimes/ Bryan | FM 3090 | Actual | $100,905 | 8 | MISCELLANEOUS WORK CONSISTING OF THE SAFETY TREATMENT OF | 
| 1272-03-009 | Guadalupe/ San Antonio | FM 3353 | Actual | $5,136,861 | 1 | REHAB & WIDEN NARROW PAVEMENT & SHOULDER | 
| 2651-01-009 | Guadalupe/ San Antonio | FM 2438 | Actual | $5,160,394 | 1 | REHAB NARROW PVM'T & WIDEN SHOULDERS | 
| 0912-00-291 | Harris/ Houston | VA | Actual | $1,436,838 | 1 | DYNAMIC MESSAGE SIGN UPGRADES | 
| 0912-00-304 | Harris/ Houston | VA | Actual | $1,750,000 | 7 | FY 2005 REGIONAL VANPOOL PROGRAM | 
| 0912-00-306 | Harris/ Houston | VA | Actual | $1,905,700 | 5 | FY 2005 REGIONAL COMMUTE ALTERNATIVES PROGRAM - MARKETING | 
| 0912-71-885 | Harris/ Houston | VA | Actual | $4,649,908 | 5 | COMMUTE SOLUTIONS (FY 2005) | 
| 0912-71-892 | Harris/ Houston | VA | Actual | $5,893,315 | 1 | SHOULDER EDGE REPAIR AND LONGITUDINAL JOINT REPAIR, JOINT | 
| 0912-72-012 | Harris/ Houston | VA | Actual | $3,080,213 | 5 | COMMUTE SOLUTIONS (FY 2006) | 
| 0912-72-026 | Harris/ Houston | VA | Actual | $80,000 | 11 | CONGESTION MITIGATION ANALYSIS BY HGAC FOR NEPA PROCESS | 
| 0912-72-060 | Harris/ Houston | VA | Actual | $575,000 | 10 | ITS DEVELOP HOT LANE NETWORK PLAN IN HARRIS COUNTY | 
| 0495-08-084 | Harrison/ Atlanta | IH 20 | Actual | $2,241,386 | 1 | CONCRETE PAVEMENT REPAIR, FOG SEAL, REMOVE AND REPLACE CHAIN | 
| 0041-01-039 | Hartley/ Amarillo | US 87 | Actual | $15,743,885 | 1 | SEAL COAT | 
| 0366-01-058 | Hays/ Austin | SH 123 | Actual | $1,338,549 | 10 | ADD LTL & CONSTRUCT PAVED SHOULDERS (5' OR GREATER) | 
| 1754-02-010 | Hays/ Austin | RM 1826 | Actual | $261,244 | 10 | ADD LEFT TURN LANE | 
| 0921-00-061 | Hidalgo/ Pharr | VA | Actual | $939,283 | 1 | NON - SITE SPECIFIC TRAFFIC SIGNALS | 
| 1803-02-019 | Hidalgo/ Pharr | FM 1925 | Actual | $8,559,503 | 7 | WIDEN TO 4 LANE DIVIDED | 
| 0048-09-027 | Hill/ Waco | IH 35E | Actual | $1,289,354 | 1 | INSTALL MEDIAN BARRIER | 
| 0969-02-004 | Hockley/ Lubbock | FM 597 | Actual | $10,306,081 | 1 | RESTORATION OF EXISTING ROADWAY | 
| 0931-01-027 | Houston/ Lufkin | FM 230 | Actual | $2,291,991 | 11 | REPLACE BRIDGES AND APPROACHES | 
| 0200-11-089 | Jefferson/ Beaumont | US 69 | Actual | $418,855 | 1 | INSTALL CABLE BARRIER SYSTEM | 
| 8366-15-001 | Kerr/ San Antonio | MH | Actual | $9,584,021 | ROW | RECONSTRUCT EXISTING AND CONSTRUCTION ON NEW LOCATION | 
| 0136-08-038 | Lamar/ Paris | US 271 | Actual | $2,998,251 | 1 | REHABILITATION OF EXISTING FACILITY (NORTHBOUND LANES AND | 
| 0749-02-018 | Lamar/ Paris | FM 38 | Actual | $1,459,609 | 1 | RESTORE BASE | 
| 0389-01-037 | Liberty/ Beaumont | SH 146 | Actual | $1,111,526 | 1 | SAFETY TREAT FIXED OBJECTS | 
| 0290-01-036 | Llano/ Austin | SH 16 | Actual | $2,984,913 | 6 | REHABILITATE BRIDGE & APPROACHES | 
| 0014-09-094 | McLennan/ Waco | BU 77-L | Actual | $284,820 | 1 | FULL DEPTH CONCRETE PAVEMENT REPAIR | 
| 0833-03-039 | McLennan/ Waco | FM 1637 | Actual | $2,024,146 | 1 | SAFETY TREAT FIXED OBJECTS | 
| 0849-02-034 | Medina/ San Antonio | FM 471 | Actual | $5,835,237 | 8 | REHAB EXISTING ROADWAY AND ADD SHOULDERS | 
| 1436-01-017 | Medina/ San Antonio | FM 1343 | Actual | $6,982,287 | 1 | REHAB EXISTING ROADWAY AND WIDEN SHOULDERS | 
| 0005-15-074 | Midland/ Odessa | IH 20 | Actual | $379,470 | 1 | MISCELLANEOUS CONSTRUCTION | 
| 0013-05-053 | Montague/ Wichita Falls | US 81 | Actual | $2,345,025 | 1 | HOT MIX OVERLAY | 
| 0912-37-117 | Montgomery/ Houston | CR | Actual | $1,717,340 | 6 | REPLACE BRIDGE | 
| 0059-01-054 | Nacogdoches/ Lufkin | SH 7 | Actual | $6,956,682 | 1 | SEAL COAT | 
| 0074-06-206 | Nueces/ Corpus Christi | IH 37 | Actual | $1,256,454 | 1 | INSTALLATION OF SAFETY LIGHTING | 
| 0171-03-059 | Parker/ Fort Worth | SH 199 | Actual | $97,400 | 1 | INSTALL TRAFFIC SIGNAL | 
| 0275-01-144 | Potter/ Amarillo | IH 40 | Actual | $6,995,447 | 1 | OVERLAY | 
| 0904-00-111 | Potter/ Amarillo | VA | Actual | $124,802 | 11 | ADA MODIFICATION | 
| 0064-10-020 | Sabine/ Lufkin | FM 1 | Actual | $1,495,680 | 1 | SEAL COAT | 
| 0074-11-007 | San Patricio/ Corpus Christi | FM 3024 | Actual | $4,734,056 | 1 | SEAL COAT ROADWAY (LOW CSJ FOR 2006 SEAL COAT PROGRAM) | 
| 0507-02-045 | San Patricio/ Corpus Christi | FM 631 | Actual | $3,629,948 | 8 | REHABILITATE ROADWAY | 
| 0916-28-044 | San Patricio/ Corpus Christi | CS | Actual | $629,413 | 7 | CONSTRUCT 2 LANES URBAN STREET WITH C & G AND PARKING LANES | 
| 0910-00-064 | Smith/ Tyler | VA | Actual | $544,980 | 1 | ADA UPGRADE PROGRAM | 
| 0141-04-033 | Sutton/ San Angelo | IH 10 | Actual | $1,038,531 | 1 | MILLING AND MICROSURFACING | 
| 0033-08-034 | Taylor/ Abilene | BU 83-D | Actual | $1,493,435 | 1 | MILLING AND ASPHALTIC CONCRETE PAVEMENT OVERLAY | 
| 0088-05-083 | Victoria/ Yoakum | US 59 | Actual | $7,909,835 | 1 | SEAL COAT | 
| 0043-14-022 | Wichita/ Wichita Falls | LP 11 | Actual | $583,748 | 1 | UPGRADE GUARDRAIL AND SGT'S | 
| 0156-03-042 | Wichita/ Wichita Falls | SH 240 | Actual | $2,478,743 | 1 | HOT MIX OVERLAY | 
| 0015-09-144 | Williamson/ Austin | IH 35 | Actual | $2,801,892 | 1 | OVERLAY FRONTAGE ROADS AND REPLACE NORTHBOUND AND SOUTHBOUND | 
| 0204-01-049 | Williamson/ Austin | US 79 | Actual | $9,351,883 | 10 | UPGRADE TO 4 - LANE DIVIDED SECTION | 
| 0215-11-018 | Wilson/ San Antonio | FM 1681 | Actual | $3,523,948 | 1 | REHAB EXISTING ROADWAY AND WIDEN SHOULDERS | 
| 0850-02-006 | Wilson/ San Antonio | FM 775 | Actual | $1,632,388 | 6 | REHABILITATE BRIDGE AND APPROACHES | 
| 1009-01-032 | Wilson/ San Antonio | FM 536 | Actual | $1,650,797 | 1 | REHAB AND WIDEN EXISTING ROADWAY | 
| 
 | 
|  |