Detail Letting Schedule for Goliad County (FY 2009)
|
Detail Letting Schedule for Goliad County (FY 2009) |
|
Last Update: Monday, November 9, 2009 |
CCSJ: 0155-02-024
|
District: |
Corpus Christi |
Let Date: |
FEB 2009 |
Highway: |
US 183 |
Let Status: |
Actual |
Project ID: |
STP 2009(273) |
CSJ: |
0155-02-024 |
Description: |
RESTORATION OF EXISTING ROADWAY |
Handling Code: |
|
Limits From: |
DEWITT COUNTY LINE |
Fund Cat: |
1 |
Limits To: |
SH 119 |
Estimate: |
$1,434,326 |
Length: |
7.1 Miles |
Actual: |
$924,170 |
|
District: |
Corpus Christi |
Let Date: |
FEB 2009 |
Highway: |
FM 673 |
Let Status: |
Actual |
Project ID: |
STP 2009(273) |
CSJ: |
1063-01-030 |
Description: |
RESTORATION OF EXISTING ROADWAY |
Handling Code: |
|
Limits From: |
INTERSECTION SH 72 |
Fund Cat: |
1 |
Limits To: |
FM 623 |
Estimate: |
$1,451,236 |
Length: |
11.7 Miles |
Actual: |
$921,071 |
|
Back...
|
Totals for 0155-02-024 |
Length: |
18.8 Miles |
Estimate: |
$2,885,562 |
Actual: |
$1,845,241 |
CCSJ: 0516-02-024
|
District: |
Corpus Christi |
Let Date: |
OCT 2008 |
Highway: |
SH 239 |
Let Status: |
Actual |
Project ID: |
STP 2008(486)HES |
CSJ: |
0516-02-024 |
Description: |
PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
Handling Code: |
|
Limits From: |
KARNES CO. LINE |
Fund Cat: |
1 |
Limits To: |
US 59 |
Estimate: |
$6,003,684 |
Length: |
17.8 Miles |
Actual: |
$4,486,038 |
|
Back...
|
Totals for 0516-02-024 |
Length: |
17.8 Miles |
Estimate: |
$6,003,684 |
Actual: |
$4,486,038 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|