Detail Letting Schedule for Howard County (FY 2009)

 
 
Last Update: Monday, November 9, 2009
Howard County (FY 2009)

CCSJ: 0005-05-101

District: Abilene Let Date: APR 2009
Highway: IH 20 Let Status: Actual
Project ID: STP 2009(539)ES CSJ: 0005-05-101
Description: FLEXIBLE PAVEMENT REPAIR & ACP OVERLAY Handling
Code:
 
Limits From: MARTIN COUNTY LINE Fund Cat: 1
Limits To: BIG SPRING Estimate: $5,045,306
Length: 10.3 Miles Actual: $4,997,460
 
Back...

Totals for 0005-05-101
Length: 10.3 Miles
Estimate: $5,045,306
Actual: $4,997,460

CCSJ: 0069-01-050

District: Abilene Let Date: FEB 2009
Highway: US 87 Let Status: Actual
Project ID: NH 2009(007) CSJ: 0069-01-050
Description: PLANING, ASPHALT CONCRETE PAVEMENT, CURB AND GUTTER, AND Handling
Code:
 
Limits From: 4TH STREET IN BIG SPRING Fund Cat: 1
Limits To: FM 700 Estimate: $5,741,269
Length: 1.0 Miles Actual: $5,249,894
 
Back...

Totals for 0069-01-050
Length: 1.0 Miles
Estimate: $5,741,269
Actual: $5,249,894


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract