Detail Letting Schedule for Howard County (FY 2009)
|
Detail Letting Schedule for Howard County (FY 2009) |
|
Last Update: Monday, November 9, 2009 |
CCSJ: 0005-05-101
|
District: |
Abilene |
Let Date: |
APR 2009 |
Highway: |
IH 20 |
Let Status: |
Actual |
Project ID: |
STP 2009(539)ES |
CSJ: |
0005-05-101 |
Description: |
FLEXIBLE PAVEMENT REPAIR & ACP OVERLAY |
Handling Code: |
|
Limits From: |
MARTIN COUNTY LINE |
Fund Cat: |
1 |
Limits To: |
BIG SPRING |
Estimate: |
$5,045,306 |
Length: |
10.3 Miles |
Actual: |
$4,997,460 |
|
Back...
|
Totals for 0005-05-101 |
Length: |
10.3 Miles |
Estimate: |
$5,045,306 |
Actual: |
$4,997,460 |
CCSJ: 0069-01-050
|
District: |
Abilene |
Let Date: |
FEB 2009 |
Highway: |
US 87 |
Let Status: |
Actual |
Project ID: |
NH 2009(007) |
CSJ: |
0069-01-050 |
Description: |
PLANING, ASPHALT CONCRETE PAVEMENT, CURB AND GUTTER, AND |
Handling Code: |
|
Limits From: |
4TH STREET IN BIG SPRING |
Fund Cat: |
1 |
Limits To: |
FM 700 |
Estimate: |
$5,741,269 |
Length: |
1.0 Miles |
Actual: |
$5,249,894 |
|
Back...
|
Totals for 0069-01-050 |
Length: |
1.0 Miles |
Estimate: |
$5,741,269 |
Actual: |
$5,249,894 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|