Detail Letting Schedule for Kendall County (FY 2010)
| |
| Detail Letting Schedule for Kendall County (FY 2010) |
| |
| Last Update: Tuesday, November 2, 2010 |
CCSJ: 3212-03-017
|
| District: |
San Antonio |
Let Date: |
AUG 2010 |
| Highway: |
FM 3351 |
Let Status: |
Actual |
| Project ID: |
STP 2011(002)SB |
CSJ: |
3212-03-016 |
| Description: |
WIDEN EXISTING ROADWAY TO ADD SHOULDERS |
Handling Code: |
|
| Limits From: |
0.072 MI N OF WHITE WATER |
Fund Cat: |
8 |
| Limits To: |
SH 46 |
Estimate: |
$1,710,044 |
| Length: |
5.0 Miles |
Actual: |
$1,032,740 |
| |
| District: |
San Antonio |
Let Date: |
AUG 2010 |
| Highway: |
FM 3351 |
Let Status: |
Actual |
| Project ID: |
STP 2010(999)HRR |
CSJ: |
3212-03-017 |
| Description: |
SAFETY TREAT FIXED OBJECTS |
Handling Code: |
|
| Limits From: |
RM 473 |
Fund Cat: |
8 |
| Limits To: |
SH 46 |
Estimate: |
$187,568 |
| Length: |
11.7 Miles |
Actual: |
$205,345 |
| |
Project Addenda Bid Tabulations Back...
|
Totals for 3212-03-017 |
| Length: |
16.7 Miles |
| Estimate: |
$1,897,612 |
| Actual: |
$1,238,085 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|