Detail Letting Schedule for Wheeler County (FY 2010)
| |
| Detail Letting Schedule for Wheeler County (FY 2010) |
| |
| Last Update: Tuesday, November 2, 2010 |
CCSJ: 1235-02-018
|
| District: |
Childress |
Let Date: |
AUG 2010 |
| Highway: |
FM 1046 |
Let Status: |
Actual |
| Project ID: |
STP 2011(366) |
CSJ: |
1235-02-018 |
| Description: |
REHABILITATION OF EXISTING ROADWAY |
Handling Code: |
|
| Limits From: |
US 83, E |
Fund Cat: |
1 |
| Limits To: |
HEMPHILL C/L |
Estimate: |
$5,331,820 |
| Length: |
13.3 Miles |
Actual: |
$5,270,932 |
| |
Project Addenda Bid Tabulations Back...
|
Totals for 1235-02-018 |
| Length: |
13.3 Miles |
| Estimate: |
$5,331,820 |
| Actual: |
$5,270,932 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|