Detail Letting Schedule for Zavala County (FY 2010)

 
 
Last Update: Tuesday, November 2, 2010
Zavala County (FY 2010)

CCSJ: 0037-03-071

District: Laredo Let Date: OCT 2009
Highway: US 83 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0037-03-071
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: 2.33 MI S. OF FM 1025 Fund Cat: 1
Limits To: 0.32 MI N OF FM 1433 Estimate: $341,361
Length: 2.5 Miles Actual: $219,172
 
District: Laredo Let Date: OCT 2009
Highway: US 83 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0037-05-041
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: ZAVALA/DIMMIT CO.LINE Fund Cat: 1
Limits To: SH 85 Estimate: $415,787
Length: 8.7 Miles Actual: $401,439
 
District: Laredo Let Date: OCT 2009
Highway: US 83 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0038-01-061
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: 0.89 MI N. OF ESPEJO-MOLINA RD Fund Cat: 1
Limits To: ZAPATA/WEBB CO.LINE Estimate: $734,063
Length: 6.8 Miles Actual: $758,348
 
District: Laredo Let Date: OCT 2009
Highway: SH 359 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0086-02-022
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: 0.596 MI. W. OF RETAMA CREEK Fund Cat: 1
Limits To: 2.677 MI. E. OF RETAMA CREEK Estimate: $155,310
Length: 3.3 Miles Actual: $156,703
 
District: Laredo Let Date: OCT 2009
Highway: US 277 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0300-01-074
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: 0.63 MI E. OF US 57 Fund Cat: 1
Limits To: 1.546 MI E. OF LAMPASITAS CR Estimate: $414,861
Length: 9.1 Miles Actual: $418,446
 
District: Laredo Let Date: OCT 2009
Highway: RM 693 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 0876-01-015
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK Handling
Code:
 
Limits From: US 277 Fund Cat: 1
Limits To: 1.944 MI W. OF RR TRACKS Estimate: $219,492
Length: 9.1 Miles Actual: $222,140
 
District: Laredo Let Date: OCT 2009
Highway: FM 1025 Let Status: Actual
Project ID: STP 2009(237)ES CSJ: 1279-01-031
Description: FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK Handling
Code:
 
Limits From: 1.247 MI W. TORTUGA CR Fund Cat: 1
Limits To: FM 117 Estimate: $222,209
Length: 9.5 Miles Actual: $224,700
 
Back...

Totals for 0037-03-071
Length: 49.0 Miles
Estimate: $2,503,083
Actual: $2,400,948

CCSJ: 0922-48-003

District: Laredo Let Date: JUL 2010
Highway: CR Let Status: Actual
Project ID: BR 2010(934) CSJ: 0922-48-003
Description: FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN OFF - SYSTEM Handling
Code:
 
Limits From: 0.968 MI E OF US 83 Fund Cat: 6
Limits To: 1.032 MI E OF US 83 Estimate: $213,723
Length: 0.1 Miles Actual: $196,604
 
Back...

Totals for 0922-48-003
Length: 0.1 Miles
Estimate: $213,723
Actual: $196,604


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract