Letting Schedule for October, 2009 (FY 2010)
Letting Schedule for October, 2009 (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
October, 2009 (FY 2010) | (see Links) |
SEP 2009 | OCT 2009 | NOV 2009 | DEC 2009 | JAN 2010 | FEB 2010 | MAR 2010 | APR 2010 | MAY 2010 | JUN 2010 | JUL 2010 | AUG 2010 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0156-05-051 | Archer/ Wichita Falls |
US 277 | Actual | $5,228,051 | 8 | CONSTRUCT GRADE SEPARATION |
0124-05-028 | Baylor/ Wichita Falls |
US 183 | Actual | $5,840,056 | 1 | SEAL COAT |
0836-02-063 | Bell/ Waco |
SH 195 | Actual | $100,295 | 8 | INSTALL TRAFFIC SIGNAL |
0915-00-147 | Bexar/ San Antonio |
VA | Actual | $753,306 | 11 | DISTRICTWIDE TRAFFIC CONTROL DEVICE FY 2010 (PROJECT 1) |
0915-00-148 | Bexar/ San Antonio |
VA | Actual | $687,330 | 11 | DISTRICTWIDE TRAFFIC CONTROL DEVICE FY 2010 (PROJECT 2) |
0046-03-036 | Bowie/ Atlanta |
US 82 | Actual | $5,236,456 | 1 | SEAL COAT |
0912-31-168 | Brazoria/ Houston |
CR | Actual | $253,436 | 6 | REPLACE BRIDGE (NBI# 12020AA0649001) |
0912-31-226 | Brazoria/ Houston |
VA | Actual | $124,120 | 1 | LANDSCAPE DEVELOPMENT |
0144-06-025 | Calhoun/ Yoakum |
SH 185 | Actual | $3,520,178 | 1 | SEAL COAT |
0220-04-041 | Cameron/ Pharr |
US 281 | Actual | $486,309 | 1 | UPGRADE DRAINAGE CULVERT AND RAISE ROAD |
3304-01-002 | Cameron/ Pharr |
FM 3195 | Actual | $696,970 | 11 | CONSTRUCT NOISE WALLS |
0242-03-069 | Chambers/ Beaumont |
SH 61 | Actual | $577,605 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0508-03-089 | Chambers/ Beaumont |
IH 10 | Actual | $186,355 | 1 | CONVERT TWO WAY FRONTAGE ROADS TO ONE WAY |
3294-01-005 | Cherokee/ Tyler |
FM 2972 | Actual | $676,874 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0043-01-077 | Childress/ Childress |
US 287 | Actual | $3,220,553 | 1 | 2010 DISTRICTWIDE SEALCOAT |
0055-06-030 | Coryell/ Waco |
US 84 | Actual | $7,908,291 | 1 | SEAL COAT |
0008-08-068 | Dallas/ Dallas |
SH 180 | Actual | $24,996 | 1 | REPLACE DAMAGED SAFETY BARRIER AND REPLACE HEADWALL |
0047-07-213 | Dallas/ Dallas |
US 75 | Actual | $112,294 | 7 | INTERSECTION IMPROVEMENTS - DUAL RIGHTS NB TO EB_AND |
0918-00-155 | Dallas/ Dallas |
VA | Actual | $225,700 | 7 | TRUCK LANE RESETRICTION SIGNING WITHIN MPA BOUNDARY |
0918-00-157 | Dallas/ Dallas |
VA | Actual | $1,208,758 | 1 | NON - SITE SPECIFIC TRAFFIC SIGNAL INSTALLATION |
0918-46-054 | Denton/ Dallas |
CR | Actual | $715,915 | 6 | REPLACE EXISTING BRIDGE AND APPROACHES |
1982-01-018 | Duval/ Laredo |
FM 1329 | Actual | $1,132,163 | 8 | RESTORATION OF EXISTING ROAD AND ADD SHOULDERS |
2224-01-076 | Ector/ Odessa |
LP 338 | Actual | $516,227 | 8 | INSTALL LEFT TURN LANE |
3571-01-005 | Ector/ Odessa |
SP 588 | Actual | $1,135,080 | 3 | ROADWAY REHABILITATION |
0665-01-008 | El Paso/ El Paso |
FM 3255 | Actual | $586,167 | 1 | OVERLAY |
0924-00-074 | El Paso/ El Paso |
VA | Actual | $437,501 | 11 | CLEAN AND / OR REPAIR BRIDGE JOINTS (BREWSTER, JEFF DAVIS, |
2121-01-078 | El Paso/ El Paso |
IH 10 | Actual | $433,993 | 11 | CABLE BARRIER SYSTEM IN MEDIAN ON IH 10 |
0172-08-050 | Ellis/ Dallas |
US 287 | Actual | $34,654,760 | 10 | WIDEN 2 - LANE UNDIVIDED HIGHWAY TO 4 - LANE DIVIDED HIGHWAY |
2578-01-022 | Erath/ Fort Worth |
FM 2481 | Actual | $644,754 | 8 | PROVIDE ADDITIONAL PAVED SURFACE BY WIDENING TRAVEL LANES BY |
0913-28-054 | Fayette/ Yoakum |
CR | Actual | $239,159 | 6 | REPLACE BRIDGE AND APPROACHES |
0913-28-062 | Fayette/ Yoakum |
CR | Actual | $16,281 | 6 | REPLACE BRIDGE AND APPROACHES |
1257-01-044 | Fort Bend/ Houston |
FM 1092 | Actual | $2,691,529 | 10 | RECONFIGURE AND UPGRADE TRAFFIC SIGNAL SYSTEM AT |
0912-73-131 | Galveston/ Houston |
VA | Actual | $442,389 | 1 | COUNTYWIDE FULL DEPTH CONCRETE REPAIR |
1607-01-029 | Galveston/ Houston |
FM 1764 | Actual | $10,442,568 | 5 | CONSTRUCT GRADE SEPARATION |
0025-05-019 | Gonzales/ Yoakum |
US 90A | Actual | $5,485,639 | 1 | SEAL COAT |
0045-03-044 | Grayson/ Paris |
SH 56 | Actual | $6,508,997 | 1 | SEAL COAT |
0045-18-029 | Grayson/ Paris |
US 82 | Actual | $1,996,659 | 1 | INSTALL MEDIAN BARRIER |
0393-01-089 | Gregg/ Tyler |
SH 149 | Actual | $239,593 | 8 | CONSTRUCT LEFT TURN LANE |
2642-01-041 | Gregg/ Tyler |
LP 281 | Actual | $19,937,618 | 10 | RECONSTRUCT AS 6 - LN URBAN HIGHWAY WITH RAISED MEDIAN |
0050-09-059 | Harris/ Houston |
US 290 | Actual | $2,526,732 | 1 | TSM IMPROVEMENTS AT VARIOUS LOCATIONS ADD U - TNS & AUX LNS, |
0912-00-329 | Harris/ Houston |
VA | Actual | $3,500,000 | 1 | ITS - MAINTENANCE (NON - LETTING) |
0912-00-398 | Harris/ Houston |
VA | Actual | $2,500,000 | 1 | IH 69 / HOUSTON TMA FREIGHT ANALYSIS |
3256-03-090 | Harris/ Houston |
BW 8 | Actual | $64,000,000 | 10 | CONSTRUCT 6 MAIN LANES (SECTION 5) TOLL_ (HCTRA LETTING) |
1776-02-014 | Hays/ Austin |
FM 2001 | Actual | $492,050 | 10 | WIDEN EXISTING ROADWAY |
0030-06-053 | Hemphill/ Amarillo |
US 83 | Actual | $7,856,825 | 1 | SEAL COAT |
0889-01-019 | Henderson/ Tyler |
FM 317 | Actual | $1,787,480 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0255-06-056 | Hidalgo/ Pharr |
US 281 | Actual | $82,332 | 8 | INSTALL MEDIAN BARRIER |
0921-02-139 | Hidalgo/ Pharr |
CS | Actual | $5,428,218 | 7 | RECONSTRUCTION AND WIDENING OF MILE 2 NORTH ROAD |
3126-04-004 | Hockley/ Lubbock |
FM 1585 | Actual | $687,169 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0005-06-112 | Howard/ Abilene |
IH 20 | Actual | $1,227,575 | 11 | INSTALL MEDIAN BARRIER |
0203-01-051 | Hunt/ Paris |
US 69 | Actual | $1,386,787 | 1 | INSTALL CENTER TURN LANE |
0739-02-146 | Jefferson/ Beaumont |
IH 10 | Actual | $1,933,971 | 8 | INSTALL CABLE BARRIER SYSTEM |
0920-38-168 | Jefferson/ Beaumont |
VA | Actual | $10,479,996 | 5 | CONSTRUCTION OF RAIL INTERCHANGE FACILITIES AT THE PORT |
0086-11-042 | Jim Wells/ Corpus Christi |
SH 44 | Actual | $258,765 | 8 | INSTALL TRAFFIC SIGNALS |
0014-04-075 | Johnson/ Fort Worth |
IH 35W | Actual | $557,982 | 8 | INSTALLATION OF WIRE ROPE MEDIAN BARRIER |
0259-04-037 | Johnson/ Fort Worth |
US 67 | Actual | $591,602 | 8 | ADD LEFT TURN LANE AT CR 1226 |
2464-01-013 | Johnson/ Fort Worth |
FM 2415 | Actual | $1,249,457 | 1 | RECONSTRUCT ROADWAY |
3372-01-013 | Johnson/ Fort Worth |
FM 3391 | Actual | $572,762 | 8 | INSTALLATION OF TWO WAY LEFT TURN LANE |
0017-17-006 | La Salle/ Laredo |
BI 35-C | Actual | $573,297 | 1 | FOR THE CONSTRUCTION OF MICROSEAL TYPE OF WORK |
1073-02-023 | Lee/ Austin |
FM 696 | Actual | $2,075,715 | 6 | REPLACE BRIDGE AND APPROACHES |
0074-01-046 | Live Oak/ Corpus Christi |
IH 37 | Actual | $576,871 | 8 | INSTALL MEDIAN BARRIER |
0024-05-092 | Medina/ San Antonio |
US 90 | Actual | $872,485 | 8 | INSTALL CABLE MEDIAN BARRIER |
0887-01-032 | Midland/ Odessa |
FM 307 | Actual | $5,697,710 | 3 | ROADWAY REHABILITATION |
0110-02-021 | Montgomery/ Houston |
SH 75 | Actual | $529,308 | 8 | INSTALL LEFT TURN LANE |
0162-04-051 | Navarro/ Dallas |
SH 31 | Actual | $856,467 | 6 | REPLACE BRIDGE |
0918-18-111 | Navarro/ Dallas |
CS | Actual | $241,096 | 8 | CONSTRUCT SIDEWALKS, CROSSWALKS, SCHOOL ZONE SIGNS WITH |
0102-01-102 | Nueces/ Corpus Christi |
SH 44 | Actual | $646,243 | 8 | INSTALL MEDIAN BARRIER |
2667-01-012 | Polk/ Lufkin |
FM 2665 | Actual | $2,661,163 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0904-02-030 | Potter/ Amarillo |
VA | Actual | $709,461 | 11 | NEW FOUR LANE ARTERIAL |
0901-27-032 | Red River/ Paris |
CR | Actual | $823,911 | 6 | REPLACE BRIDGE AND APPROACHES |
2594-02-011 | San Jacinto/ Lufkin |
FM 3081 | Actual | $1,120,845 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0101-04-107 | San Patricio/ Corpus Christi |
US 181 | Actual | $833,044 | 8 | INSTALL MEDIAN BARRIER |
0014-15-032 | Tarrant/ Fort Worth |
US 81 | Actual | $1,637,542 | 7 | RELOCATE NB EXIT RAMP TO AVONDALE HASLET ROAD AND |
0902-48-338 | Tarrant/ Fort Worth |
CS | Actual | $527,500 | 9 | TRANSPORTATION ENHANCEMENT |
0908-33-074 | Taylor/ Abilene |
CR | Actual | $417,249 | 6 | REPLACE BRIDGE & APPROACHES |
0077-09-005 | Tom Green/ San Angelo |
BU 67H | Actual | $2,367,545 | 1 | ASPHALT CONCRETE PAVEMENT OVERLAY |
0914-04-191 | Travis/ Austin |
VA | Actual | $3,044,285 | 9 | CONSTRUCT TRAIL |
0914-04-200 | Travis/ Austin |
VA | Actual | $350,652 | 7 | CONSTRUCT TRAIL SYSTEM |
0018-06-159 | Webb/ Laredo |
IH 35 | Actual | $729,061 | 11 | UPGRADE APPROACH RAIL AND BRIDGE RAIL |
0922-00-043 | Webb/ Laredo |
VA | Actual | $824,910 | 10 | ADA RAMP IMPROVEMENT DISTRICTWIDE |
0922-33-114 | Webb/ Laredo |
VA | Actual | $4,620,000 | 10 | CONSTRUCT 7 FEDERAL INSPECTION BOOTHS |
0151-04-063 | Williamson/ Austin |
US 183 | Actual | $14,677,727 | 6 | CONSTRUCT 4 LN DIVIDED RDWY |
0914-05-162 | Williamson/ Austin |
VA | Actual | $5,000,000 | 7 | DEVELOP AUSTIN - SAN ANTONIO PASSENGER RAIL |
0914-05-163 | Williamson/ Austin |
VA | Actual | $5,000,000 | 7 | DEVELOP AUSTIN - SAN ANTONIO PASSENGER RAIL |
3099-03-014 | Zapata/ Pharr |
FM 3169 | Actual | $257,619 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0037-03-071 | Zavala/ Laredo |
US 83 | Actual | $2,400,948 | 1 | FOR THE CONSTRUCTION OF SEALCOAT TYPE WORK |
|
|