Detail Letting Schedule for Cameron County (FY 2011)
Detail Letting Schedule for Cameron County (FY 2011) | ||||
Last Update: Tuesday, September 6, 2011 |
Cameron County (FY 2011) |
CCSJ: 0039-12-052 | |||
District: | Pharr | Let Date: | JUL 2011 |
Highway: | SH 4 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 0039-10-074 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: |
|
Limits From: | @ SH 48 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $148,355 |
Length: | 0.1 Miles | Actual: | $182,619 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | BU 77-X | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 0039-12-052 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ LOVETT RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $73,665 |
Length: | 0.1 Miles | Actual: | $79,838 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 0255-09-093 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ LAS MILPAS RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $85,553 |
Length: | 0.1 Miles | Actual: | $86,214 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | FM 681 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 0669-01-055 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ LOS EBANOS RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $96,221 |
Length: | 0.1 Miles | Actual: | $105,236 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | FM 1423 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 1427-01-025 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ ALBERTA RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $91,938 |
Length: | 0.1 Miles | Actual: | $102,436 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | FM 1423 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 1427-01-026 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ NOLANA/EARLING RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $88,880 |
Length: | 0.1 Miles | Actual: | $100,124 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | FM 907 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 1586-01-065 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ ELDORA RD | Fund Cat: | 8 |
Limits To: | . | Estimate: | $71,534 |
Length: | 0.1 Miles | Actual: | $78,016 |
District: | Pharr | Let Date: | JUL 2011 |
Highway: | FM 1925 | Let Status: | Actual |
Project ID: | STP 1102(172)HES | CSJ: | 1803-01-087 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | @ FM 2993 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $112,421 |
Length: | 0.1 Miles | Actual: | $118,106 |
Bid Tabulations Back... |
Totals for 0039-12-052 | ||
---|---|---|---|
Length: | 0.8 Miles | ||
Estimate: | $768,567 | ||
Actual: | $852,589 | ||
CCSJ: 0220-04-042 | |||
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0220-03-025 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 509 | Fund Cat: | 1 |
Limits To: | .494 MI WEST OF FM 732 | Estimate: | $170,707 |
Length: | 4.5 Miles | Actual: | $159,075 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0220-03-026 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | HID/CAM COUNTY LINE E | Fund Cat: | 1 |
Limits To: | FM 509 | Estimate: | $293,506 |
Length: | 7.9 Miles | Actual: | $274,978 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0220-04-038 |
Description: | FY 2010 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 1732 | Fund Cat: | 1 |
Limits To: | .494 MI WEST OF FM 732 | Estimate: | $174,716 |
Length: | 4.6 Miles | Actual: | $162,752 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0220-04-042 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 1732 | Fund Cat: | 1 |
Limits To: | FM 3248 | Estimate: | $438,712 |
Length: | 7.0 Miles | Actual: | $366,966 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 77 | Let Status: | Actual |
Project ID: | NH 2011(479) | CSJ: | 0327-02-049 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | KLEBERG/KEN CL | Fund Cat: | 1 |
Limits To: | SOUTH 11.7 MI | Estimate: | $800,304 |
Length: | 11.7 Miles | Actual: | $743,089 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | US 77 | Let Status: | Actual |
Project ID: | NH 2011(479) | CSJ: | 0327-05-039 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | 34 MI S OF KLEBERG/KENEDY CL | Fund Cat: | 1 |
Limits To: | 4.5 MI N OF KENEDY/WILLACY CL | Estimate: | $289,209 |
Length: | 8.4 Miles | Actual: | $268,121 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | BU 77-W | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0327-06-025 |
Description: | FY 2011 SEAL COAT PROGRAM | Handling Code: |
|
Limits From: | SH 186 | Fund Cat: | 1 |
Limits To: | US 77 NORTH | Estimate: | $105,361 |
Length: | 3.2 Miles | Actual: | $99,913 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 107 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0342-03-033 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 506 (NORTH) | Fund Cat: | 1 |
Limits To: | FM 506 (SOUTH) | Estimate: | $33,068 |
Length: | 0.6 Miles | Actual: | $30,661 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 107 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0342-03-034 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 506 | Fund Cat: | 1 |
Limits To: | FM 800 | Estimate: | $104,624 |
Length: | 2.4 Miles | Actual: | $96,757 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 107 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0342-04-029 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | BUS 77 | Estimate: | $17,814 |
Length: | 0.4 Miles | Actual: | $16,584 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 186 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0433-02-050 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | .553 EAST OF FM 493 | Fund Cat: | 1 |
Limits To: | FM 1834 | Estimate: | $450,615 |
Length: | 11.4 Miles | Actual: | $421,705 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 186 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0433-04-026 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | 0.277 MI EAST OF FM 2099 | Estimate: | $143,733 |
Length: | 4.0 Miles | Actual: | $134,662 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 186 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0433-04-027 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | 0.277 MI E OF FM 2099 | Fund Cat: | 1 |
Limits To: | 880 FT W OF FM 2209 | Estimate: | $137,527 |
Length: | 3.9 Miles | Actual: | $128,596 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | SH 186 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0433-04-028 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | 880 FT. WEST OF FM 2209 | Fund Cat: | 1 |
Limits To: | 293 FT EAST OF FM 2209 | Estimate: | $8,589 |
Length: | 0.2 Miles | Actual: | $7,871 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 2925 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0630-03-020 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 1847 WEST AND SOUTH | Fund Cat: | 1 |
Limits To: | FM 106 | Estimate: | $300,825 |
Length: | 11.7 Miles | Actual: | $281,302 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 490 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 0860-02-011 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | HIDALGO/WILLACY CL | Fund Cat: | 1 |
Limits To: | FM 88 | Estimate: | $60,052 |
Length: | 3.0 Miles | Actual: | $56,090 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 510 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 1057-03-034 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 3462 | Fund Cat: | 1 |
Limits To: | 2 MI EAST | Estimate: | $52,104 |
Length: | 2.0 Miles | Actual: | $48,811 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 800 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 1136-01-016 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 2994 | Fund Cat: | 1 |
Limits To: | US 83 | Estimate: | $72,578 |
Length: | 2.0 Miles | Actual: | $68,084 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 800 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 1136-02-044 |
Description: | FY 2011 SEALCOAT PROGRAM | Handling Code: |
|
Limits From: | FM 1479 | Fund Cat: | 1 |
Limits To: | FM 2520 | Estimate: | $141,948 |
Length: | 4.5 Miles | Actual: | $134,093 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 490 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 1430-01-021 |
Description: | FY 2011 SEAL COAT PROGRAM | Handling Code: |
|
Limits From: | FM 1425 | Fund Cat: | 1 |
Limits To: | FM 1834 | Estimate: | $76,419 |
Length: | 3.0 Miles | Actual: | $71,770 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | FM 1847 | Let Status: | Actual |
Project ID: | STP 2011(480) | CSJ: | 1801-01-046 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | HENDERSON RD | Fund Cat: | 1 |
Limits To: | FM 510 | Estimate: | $120,689 |
Length: | 2.9 Miles | Actual: | $114,157 |
Back... |
Totals for 0220-04-042 | ||
Length: | 99.3 Miles | ||
Estimate: | $3,993,100 | ||
Actual: | $3,686,037 | ||
CCSJ: 0921-06-073 | |||
District: | Pharr | Let Date: | OCT 2010 |
Highway: | CS | Let Status: | Actual |
Project ID: | HP 1108(1)ES | CSJ: | 0921-06-073 |
Description: | CONSTRUCT NEW RR | Handling Code: |
LC |
Limits From: | 0.03 MI N OF US 281 | Fund Cat: | 10 |
Limits To: | US 77/83 | Estimate: | $19,100,000 |
Length: | 6.0 Miles | Actual: | $19,529,283 |
District: | Pharr | Let Date: | OCT 2010 |
Highway: | CS | Let Status: | Actual |
Project ID: | DMO 2010(721) | CSJ: | 0921-06-233 |
Description: | CONSTRUCT NEW RAIL INT'L BR OVER RIO GRANDE & ACCESS RD | Handling Code: |
LC |
Limits From: | RIO GRANDE RIVER | Fund Cat: | 10 |
Limits To: | 0.03 MI N OF US 281 | Estimate: | $8,900,000 |
Length: | 0.2 Miles | Actual: | $5,140,800 |
Back... |
Totals for 0921-06-073 | ||
Length: | 6.2 Miles | ||
Estimate: | $28,000,000 | ||
Actual: | $24,670,083 | ||
CCSJ: 0921-06-187 | |||
District: | Pharr | Let Date: | AUG 2011 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2005(292) | CSJ: | 0921-06-187 |
Description: | WIDEN TO 4 LANES | Handling Code: |
|
Limits From: | ON PRIMERA RD, FROM STUART PLACE RD | Fund Cat: | 3 |
Limits To: | US 77 | Estimate: | $5,105,480 |
Length: | 2.3 Miles | Actual: | $5,399,888 |
Award Status Bid Tabulations Back... |
Totals for 0921-06-187 | ||
Length: | 2.3 Miles | ||
Estimate: | $5,105,480 | ||
Actual: | $5,399,888 | ||
CCSJ: 0921-06-218 | |||
District: | Pharr | Let Date: | JAN 2011 |
Highway: | CS | Let Status: | Actual |
Project ID: | CBI 2010(579) | CSJ: | 0921-06-218 |
Description: | CONSTRUCT 4 - LANE TWIN BRIDGE AND RECONSTRUCT APPROACHES | Handling Code: |
LC |
Limits From: | @ LOS TOMATES INT'L BRIDGE | Fund Cat: | 10 |
Limits To: | . | Estimate: | $6,247,740 |
Length: | 0.6 Miles | Actual: | $5,848,787 |
Back... |
Totals for 0921-06-218 | ||
Length: | 0.6 Miles | ||
Estimate: | $6,247,740 | ||
Actual: | $5,848,787 | ||
CCSJ: 0921-06-228 | |||
District: | Pharr | Let Date: | OCT 2010 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2011(629)ES | CSJ: | 0921-06-228 |
Description: | ADA IMPROVEMENTS PRG | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS IN CAMERON CTY | Fund Cat: | 10 |
Limits To: | . | Estimate: | $179,916 |
Length: | 0.0 Miles | Actual: | $147,964 |
Back... |
Totals for 0921-06-228 | ||
Length: | 0.0 Miles | ||
Estimate: | $179,916 | ||
Actual: | $147,964 | ||
CCSJ: 0921-06-244 | |||
District: | Pharr | Let Date: | AUG 2011 |
Highway: | VA | Let Status: | Actual |
Project ID: | HP 2011(865) | CSJ: | 0921-06-244 |
Description: | OLMITO SWITCHYARD IMPROVEMENTS CONSTRUCT A REPAIR - IN - PLACE | Handling Code: |
LC |
Limits From: | OLMITO SWITCHYARD | Fund Cat: | 10 |
Limits To: | . | Estimate: | $3,100,000 |
Length: | 0.1 Miles | Actual: | $2,314,017 |
Back... |
Totals for 0921-06-244 | ||
Length: | 0.1 Miles | ||
Estimate: | $3,100,000 | ||
Actual: | $2,314,017 | ||
CCSJ: 1136-02-046 | |||
District: | Pharr | Let Date: | SEP 2010 |
Highway: | FM 800 | Let Status: | Actual |
Project ID: | C 1136-2-25 | CSJ: | 1136-02-025 |
Description: | RECONTRUCT ROADWAY AND ADD SHOULDERS | Handling Code: |
|
Limits From: | 0.1 MI S OF TRIMPE LANE | Fund Cat: | 1 |
Limits To: | FM 3067 | Estimate: | $5,000,868 |
Length: | 1.8 Miles | Actual: | $4,749,611 |
District: | Pharr | Let Date: | SEP 2010 |
Highway: | FM 800 | Let Status: | Actual |
Project ID: | STP 2011(419) | CSJ: | 1136-02-046 |
Description: | DRAINAGE PROJECT | Handling Code: |
|
Limits From: | 0.54 MI SOUTH OF BUS 83 | Fund Cat: | 1 |
Limits To: | TRIMPE LANE | Estimate: | $570,965 |
Length: | 1.3 Miles | Actual: | $513,712 |
Back... |
Totals for 1136-02-046 | ||
Length: | 3.1 Miles | ||
Estimate: | $5,571,833 | ||
Actual: | $5,263,323 | ||
CCSJ: 1138-01-035 | |||
District: | Pharr | Let Date: | APR 2011 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | STP 2011(941)HES | CSJ: | 0039-01-081 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 1430 (EAST LEG) | Fund Cat: | 8 |
Limits To: | FM 2360 | Estimate: | $301,745 |
Length: | 3.6 Miles | Actual: | $232,443 |
District: | Pharr | Let Date: | APR 2011 |
Highway: | FM 510 | Let Status: | Actual |
Project ID: | STP 2011(941)HES | CSJ: | 1057-03-037 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 3462 | Fund Cat: | 8 |
Limits To: | FM 803 | Estimate: | $236,174 |
Length: | 4.7 Miles | Actual: | $185,123 |
District: | Pharr | Let Date: | APR 2011 |
Highway: | FM 755 | Let Status: | Actual |
Project ID: | STP 2011(941)HES | CSJ: | 1103-04-035 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | .25 MI N OF LUIS MARTINEZ LANE | Fund Cat: | 8 |
Limits To: | EISENHOWER ST (0.8 MI N OF US 83) | Estimate: | $246,883 |
Length: | 5.0 Miles | Actual: | $186,321 |
District: | Pharr | Let Date: | APR 2011 |
Highway: | FM 803 | Let Status: | Actual |
Project ID: | STP 2011(941)HES | CSJ: | 1138-01-035 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 2893 | Fund Cat: | 8 |
Limits To: | SH 100 | Estimate: | $163,344 |
Length: | 2.6 Miles | Actual: | $181,041 |
District: | Pharr | Let Date: | APR 2011 |
Highway: | FM 1423 | Let Status: | Actual |
Project ID: | STP 2011(941)HES | CSJ: | 1427-01-027 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | SH 107 | Fund Cat: | 8 |
Limits To: | 0.12 MI S OF SH 495 | Estimate: | $409,639 |
Length: | 7.0 Miles | Actual: | $312,305 |
Back... |
Totals for 1138-01-035 | ||
Length: | 22.9 Miles | ||
Estimate: | $1,357,785 | ||
Actual: | $1,097,233 | ||
CCSJ: 1806-01-010 | |||
District: | Pharr | Let Date: | JAN 2011 |
Highway: | FM 313 | Let Status: | Actual |
Project ID: | STP 2011(654) | CSJ: | 1806-01-010 |
Description: | REHABLITATE OUTSIDE LANES & OVERLAY | Handling Code: |
|
Limits From: | SH 4 | Fund Cat: | 1 |
Limits To: | SH 48 | Estimate: | $825,308 |
Length: | 1.7 Miles | Actual: | $1,040,811 |
Back... |
Totals for 1806-01-010 | ||
Length: | 1.7 Miles | ||
Estimate: | $825,308 | ||
Actual: | $1,040,811 |
|
|