Letting Schedule for August, 2011 (FY 2011)
Letting Schedule for August, 2011 (FY 2011) | ||||
Last Update: Tuesday, September 6, 2011 |
August, 2011 (FY 2011) | (see Links) |
SEP 2010 | OCT 2010 | NOV 2010 | DEC 2010 | JAN 2011 | FEB 2011 | MAR 2011 | APR 2011 | MAY 2011 | JUN 2011 | JUL 2011 | AUG 2011 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0913-20-078 | Austin/ Yoakum |
CR | Actual | $445,958 | 6 | REPLACE BRIDGE AND APPROACHES |
0913-20-080 | Austin/ Yoakum |
CR | Actual | $208,183 | 6 | REPLACE BRIDGE AND APPROACHES |
0291-06-043 | Bandera/ San Antonio |
SH 16 | Actual | $1,472,364 | 8 | WIDEN TO PROVIDE PASSING LANE |
0320-01-070 | Bell/ Waco |
SP 290 | Actual | $799,000 | 9 | LANDSCAPING OF CENTER MEDIANS |
0836-02-050 | Bell/ Waco |
SH 195 | Actual | $15,235,438 | 12 | CONSTRUCT OVERPASS AND RAMPS TO IMPROVE SAFETY AND COMPLETE |
0017-02-072 | Bexar/ San Antonio |
IH 35 | Actual | $444,441 | 8 | CONTINUOUS ILLUMINATION |
0072-08-120 | Bexar/ San Antonio |
IH 10 | Actual | $35,968,285 | 7 | EXPAND 6 TO 8 LANE EXPRESSWAY AND OPERATIONAL IMPROVEMENTS |
0072-08-122 | Bexar/ San Antonio |
LP 345 | Actual | $12,142,047 | ROW | GRADE SEPARATION @ MEDICAL & OPERATIONAL IMPVMNTS ON MEDICAL |
0073-08-167 | Bexar/ San Antonio |
IH 37 | Actual | $520,750 | 10 | LANDSCAPE DEVELOPMENT |
0915-12-489 | Bexar/ San Antonio |
VA | Actual | $5,400,000 | 7 | COSTS ASSOCIATED WITH BUS PURCHASES, ROW, CONSTRUCTION, |
0586-01-063 | Brazoria/ Houston |
SH 332 | Actual | $299,499 | 11 | REMOVE AND REPLACE EXISTING DRAINAGE STRUCTURE, RIPRAP, |
1003-01-089 | Brazoria/ Houston |
FM 523 | Actual | $1,083,224 | 8 | CENTERLINE RUMBLE STRIPS |
1414-03-034 | Brazoria/ Houston |
FM 1462 | Actual | $1,489,044 | 6 | REPLACE BRIDGE AND APPROACHES |
0506-01-091 | Brazos/ Bryan |
FM 60 | Actual | $3,692,020 | 11 | REHABILITATION OF EXISTING ROAD CONSISTING OF SIDEWALKS, |
2399-01-060 | Brazos/ Bryan |
FM 2818 | Actual | $14,139,149 | 8 | SAFETY IMPROVEMENT WORK CONSISTING OF GRADING, STRUCTURES, |
3138-01-023 | Brazos/ Bryan |
FM 2347 | Actual | $155,332 | 11 | SAFETY WORK CONSISTING OF IMPROVEMENTS TO TRAFFIC SIGNAL |
0818-01-015 | Brooks/ Pharr |
FM 755 | Actual | $2,138,271 | 1 | REHABILITATE ROADWAY |
1103-01-011 | Brooks/ Pharr |
FM 755 | Actual | $2,060,464 | 1 | REHABILITATE ROADWAY |
0914-24-011 | Burnet/ Austin |
CR | Actual | $336,916 | 6 | REPLACE BRIDGE AND APPROACHES |
2206-01-014 | Burnet/ Austin |
RM 2341 | Actual | $418,364 | 1 | IMPROVEMENTS TO EXISTING BOX CULVERT STRUCTURE |
0152-02-069 | Caldwell/ Austin |
US 183 | Actual | $3,044,359 | 1 | PAVEMENT REPAIR, MILL, SEAL, & OVERLAY |
0921-06-187 | Cameron/ Pharr |
CS | Actual | $5,399,888 | 3 | WIDEN TO 4 LANES |
0921-06-244 | Cameron/ Pharr |
VA | Actual | $2,314,017 | 10 | OLMITO SWITCHYARD IMPROVEMENTS CONSTRUCT A REPAIR - IN - PLACE |
3510-10-013 | Chambers/ Beaumont |
SH 99 | Actual | $123,634 | 11 | ADD RIGHT TURN LANE |
0047-05-050 | Collin/ Dallas |
SH 5 | Actual | $1,710,332 | 10 | ADD RIGHT TURN LNS AT INTERSECTION AND ADD RAISED MEDIAN AT |
0091-05-061 | Collin/ Dallas |
SH 289 | Actual | $3,685,505 | 1 | REPAIR PAVEMENT, RESURFACE HIGHWAY, PAVEMENT MARKINGS |
0918-24-097 | Collin/ Dallas |
VA | Actual | $1,042,073 | 9 | CONSTRUCT SIDEWALKS ALONG CITY STREETS IN CITY OF MELISSA |
0070-04-030 | Concho/ San Angelo |
US 87 | Actual | $1,338,359 | 6 | REPLACE BRIDGE AND APPROACHES |
0047-07-220 | Dallas/ Dallas |
US 75 | Actual | $408,549 | 10 | LANDSCAPE DEVELOPMENT |
0430-01-054 | Dallas/ Dallas |
SH 352 | Actual | $1,992,064 | 1 | FULL DEPTH CONCRETE PVMT REPAIR, UTBHMWC, PAVEMENT MARKINGS |
0581-01-128 | Dallas/ Dallas |
LP 12 | Actual | $1,434,000 | 1 | OVERLAY HIGHWAY - PLANING, ACP OVERLAY, FULL DEPTH CONCRETE |
0918-00-169 | Dallas/ Dallas |
VA | Actual | $266,462 | 1 | UPGRADE VIDEO DETECTION FOR HIGH SPEED APPROACHES |
2374-03-057 | Dallas/ Dallas |
IH 20 | Actual | $5,699,998 | 1 | WIDEN BRIDGE TO TWO LANES |
2374-07-060 | Dallas/ Dallas |
IH 635 | Actual | $808,360 | 1 | BRIDGE REPAIR FULL DEPTH CONCRETE REPAIR |
2374-07-065 | Dallas/ Dallas |
IH 635 | Actual | $518,674 | 1 | FULL DEPTH CONCRETE REPAIR, SUBGRADE WORK AND STRIPING |
0195-02-064 | Denton/ Dallas |
IH 35 | Actual | $76,044 | 11 | INSTALLATION OF AESTHETIC LIGHTING |
2353-02-015 | Denton/ Dallas |
FM 2450 | Actual | $2,060,845 | 1 | BASE REPAIR AND 2 INCH OVERLAY |
0913-17-034 | Dewitt/ Yoakum |
VA | Actual | $113,169 | 1 | LANDSCAPE DEVELOPMENT |
0924-06-366 | El Paso/ El Paso |
VA | Actual | $392,000 | 5 | VANPOOL PROGRAM FY 2011 |
0924-06-407 | El Paso/ El Paso |
VA | Actual | $181,139 | 11 | CONSTRUCTION / REHAB SIDEWALKS |
2121-02-143 | El Paso/ El Paso |
IH 10 | Actual | $178,760 | 11 | LANDSCAPE IMPROVEMENT TO INCLUDE VEGETATION, SOIL MIX, AND |
0267-03-026 | Fayette/ Yoakum |
FM 609 | Actual | $2,600,295 | 1 | ADD SHOULDERS |
0913-28-063 | Fayette/ Yoakum |
CR | Actual | $573,322 | 6 | REHABILITATE EXISTING TRUSS BRIDGE |
0908-23-024 | Fisher/ Abilene |
CR | Actual | $209,509 | 6 | REPLACE BRIDGE AND APPROACHES |
0908-23-025 | Fisher/ Abilene |
CR | Actual | $750,475 | 6 | REPLACE BRIDGE AND APPROACHES |
0908-23-026 | Fisher/ Abilene |
CR | Actual | $263,908 | 6 | REPLACE BRIDGE AND APPROACHES |
0908-23-028 | Fisher/ Abilene |
CR | Actual | $564,101 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-34-175 | Fort Bend/ Houston |
VA | Actual | $594,378 | 10 | LANDSCAPE |
3510-04-043 | Fort Bend/ Houston |
SH 99 | Actual | $10,440,499 | 10 | CONSTRUCT OVERPASS AND APPROACHES |
3510-04-046 | Fort Bend/ Houston |
SH 99 | Actual | $8,940,684 | 10 | CONSTRUCT OVERPASS AND APPROACHES (SEG D TOLL) |
0675-01-060 | Freestone/ Bryan |
IH 45 | Actual | $94,511 | 8 | SAFETY WORK CONSISTING OF INSTALLING TRAFFIC SIGNALS |
0367-02-078 | Galveston/ Houston |
SH 87 | Actual | $64,605 | 8 | CENTERLINE RUMBLE STRIPS |
0367-06-058 | Galveston/ Houston |
SH 87 | Actual | $323,341 | 5 | INSTALL ARTERIAL TRAFFIC MANAGEMENT SYSTEM |
0389-07-035 | Galveston/ Houston |
SH 146 | Actual | $154,994 | 8 | IMPROVE TRAFFIC SIGNAL |
0686-02-024 | Galveston/ Houston |
FM 1765 | Actual | $560,971 | 6 | REPLACE BRIDGE AND APPROACHES (NBI# 12085068602003) |
0912-73-113 | Galveston/ Houston |
CR | Actual | $377,938 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-73-176 | Galveston/ Houston |
PW | Actual | $330,787 | 10 | CONSTRUCT INTERIM ROAD, PARKING AND EQUESTRIAN PARKING |
0912-73-180 | Galveston/ Houston |
VA | Actual | $3,284,826 | 10 | ADA CURB RAMP PROGRAM FY 11 (VARIOUS LOCATIONS IN GALVESTON |
1607-01-049 | Galveston/ Houston |
FM 1764 | Actual | $1,219,291 | 1 | MILLING, 1" CAM, 1.5" TY - D OVERLAY & CURB REPAIR |
2523-01-023 | Galveston/ Houston |
FM 2004 | Actual | $1,626,528 | 1 | ACP OVERLAY |
3049-01-027 | Galveston/ Houston |
FM 646 | Actual | $9,777,012 | 1 | WIDEN FROM 2 LANES TO 4 LANES DIVIDED WITHOUT GRADE |
0169-10-021 | Gray/ Waco |
FM 282 | Actual | $5,104,273 | 8 | RR CROSSING SIGNAL UPGRADE |
0047-02-092 | Grayson/ Paris |
US 69 | Actual | $7,983,528 | 6 | REPLACE BRIDGE AND APPROACHES |
0047-03-074 | Grayson/ Paris |
US 75 | Actual | $1,103,251 | 10 | REVERSE EXISTING RAMP CONFIGURATION |
1763-03-029 | Gregg/ Tyler |
LP 281 | Actual | $13,235,357 | 11 | CONSTRUCT RAILROAD OVERPASS & APPROACHES AT UPRR |
1400-01-028 | Grimes/ Bryan |
FM 1774 | Actual | $198,974 | 1 | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, |
0025-10-087 | Guadalupe/ San Antonio |
FM 78 | Actual | $268,567 | 1 | UPGRADE EXISTING FLASHING BEACON TO A TRAFFIC SIGNAL |
0535-01-066 | Guadalupe/ San Antonio |
IH 10 | Actual | $2,148,543 | 1 | WIDEN BRIDGE TO ACCOMODATE EMERGENCY LANE |
0050-08-091 | Harris/ Houston |
US 290 | Actual | $446,814 | 8 | IMPROVE TRAFFIC SIGNAL |
0598-01-093 | Harris/ Houston |
SH 288 | Actual | $308,184 | 8 | IMPROVE TRAFFIC SIGNAL |
0912-00-399 | Harris/ Houston |
VA | Actual | $3,134,199 | 1 | ACCESS MANAGEMENT IMPROVEMENTS (PHASE II) |
0912-70-066 | Harris/ Houston |
CS | Actual | $1,034,550 | 10 | CONSTRUCT PUMP STATION |
0912-70-079 | Harris/ Houston |
VA | Actual | $1,191,335 | 10 | LANDSCAPE DEVELOPMENT |
0912-70-080 | Harris/ Houston |
VA | Actual | $1,437,955 | 10 | LANDSCAPE DEVELOPMENT |
0912-71-043 | Harris/ Houston |
CS | Actual | $2,374,620 | 5 | UPPER KIRBY TRAFFIC SIGNAL OPERATIONS IMPROVEMENT PROGRAM |
0912-71-503 | Harris/ Houston |
VA | Actual | $4,586,474 | 5 | BIKE TRAIL ON BUFFALO BAYOU PARALLEL TO MEMORIAL DR & ALLEN |
0912-71-803 | Harris/ Houston |
CS | Actual | $4,901,088 | 9 | WESTCHASE DISTRICT TRAIL NORTH - WESTCHASE MANAGEMENT DISTRICT |
0912-72-057 | Harris/ Houston |
CR | Actual | $681,208 | 6 | REPLACE BRIDGE (NBI# 12102AA0233001) |
0912-72-126 | Harris/ Houston |
CS | Actual | $1,167,230 | 6 | REPLACE BRIDGE (NBI# 12102B20595001) |
0976-01-035 | Harris/ Houston |
FM 865 | Actual | $9,266,318 | 1 | WIDEN FROM 2 TO 4 LANES WITH CURB AND GUTTER (PHASE 2 AFTER |
1258-04-059 | Harris/ Houston |
FM 1093 | Actual | $146,422 | 8 | IMPROVE TRAFFIC SIGNAL |
1685-05-101 | Harris/ Houston |
SH 6 | Actual | $256,046 | 8 | IMPROVE TRAFFIC SIGNAL |
2941-02-048 | Harris/ Houston |
FM 2920 | Actual | $401,310 | 5 | INSTALL VIVDS, PAN TILT CAMERAS AND DMS AT MAJOR |
3256-01-099 | Harris/ Houston |
BW 8 | Actual | $200,779 | 10 | LANDSCAPE DEVELOPMENT |
3256-02-086 | Harris/ Houston |
BW 8 | Actual | $380,586 | 8 | IMPROVE TRAFFIC SIGNAL |
3510-05-018 | Harris/ Houston |
SH 99 | Actual | $49,439,343 | 12 | CONSTRUCT 2 DIRECT CONNECTORS (SEGMENT E) (TOLL) |
0640-06-033 | Harrison/ Atlanta |
FM 449 | Actual | $2,744,220 | 11 | REPLACE BRIDGES AND APPROACHES |
0016-03-097 | Hays/ Austin |
IH 35 | Actual | $248,788 | 11 | LANDSCAPING AND IRRIGATION (ON FRONTAGE ROADS) |
0921-02-291 | Hidalgo/ Pharr |
CS | Actual | $703,332 | 8 | UPDGRADE RRX WARNING DEVICES |
0203-02-041 | Hunt/ Paris |
US 69 | Actual | $14,582,825 | 1 | CONSTRUCT SUPER 2 |
0901-22-077 | Hunt/ Paris |
CR | Actual | $794,570 | 6 | REPLACE BRIDGE AND APPROACHES |
0901-22-102 | Hunt/ Paris |
VA | Actual | $104,820 | 1 | LANDSCAPE AND SCENIC ENHANCEMENT |
1494-01-023 | Hunt/ Paris |
FM 1565 | Actual | $1,351,858 | 8 | WIDEN ROADWAY |
0904-07-011 | Hutchinson/ Amarillo |
CR | Actual | $3,192,062 | 6 | REPLACE BRIDGE & APPROACHES AT STRUCTURE # AA02 - 25 - 002 |
0902-40-024 | Jack/ Fort Worth |
CR | Actual | $931,549 | 6 | REPLACE BRIDGE AND APPROACHES |
0508-04-158 | Jefferson/ Beaumont |
SH 73 | Actual | $267,106 | 6 | RELACE EXISTING BOX CULVERT |
0508-05-029 | Jefferson/ Beaumont |
SH 82 | Actual | $4,626,389 | 6 | REHABILITATE EXISTING ROADWAY |
0786-01-077 | Jefferson/ Beaumont |
FM 364 | Actual | $257,941 | 1 | OVERLAY EXISTING ROADWAY |
0172-03-016 | Johnson/ Fort Worth |
BU 287P | Actual | $495,312 | 8 | INSTALL SIGNAL AND ADD LEFT TURN LANE |
0259-06-006 | Johnson/ Fort Worth |
US 67 | Actual | $378,723 | 8 | INSTALL TRAFFIC SIGNAL AND ADD LEFT TURN LANE |
0712-02-013 | Johnson/ Fort Worth |
FM 916 | Actual | $1,800,641 | 11 | REPLACE BRIDGE AND APPROACHES |
0901-29-015 | Lamar/ Paris |
CR | Actual | $1,216,179 | 6 | REPLACE BRIDG & APPROACHES |
0170-02-017 | Lipscomb/ Amarillo |
US 60 | Actual | $3,121,534 | 1 | OVERLAY |
1550-01-012 | Live Oak/ Corpus Christi |
FM 534 | Actual | $3,574,051 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0914-25-003 | Llano/ Austin |
PW | Actual | $52,168 | 10 | INSTALL HIGHWAY SIGNAGE AND HIGHWAY ADVISORY RADIO |
0062-06-051 | Marion/ Atlanta |
US 59 | Actual | $1,915,676 | 8 | IMPROVE TRAFFIC SIGNAL & ADVANCE WARNING |
0138-12-022 | Marion/ Atlanta |
FM 2208 | Actual | $1,915,771 | 8 | SAFETY TREAT FIXED OBJECTS |
0913-21-043 | Matagorda/ Yoakum |
CS | Actual | $203,067 | 8 | CONSTRUCT PEDESTRIAN BRIDGE |
0913-21-044 | Matagorda/ Yoakum |
CS | Actual | $363,182 | 8 | SAFE ROUTES TO SCHOOL |
0276-02-027 | Maverick/ Laredo |
US 57 | Actual | $1,821,126 | 1 | HMA LEVEL - UP & PAV MARKINGS |
0014-09-098 | McLennan/ Yoakum |
BU 77-L | Actual | $11,856,560 | 8 | INSTALL RAILROAD SIGNAL |
0210-03-021 | Milam/ Bryan |
FM 1712 | Actual | $2,387,641 | 8 | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, |
0908-21-018 | Mitchell/ Abilene |
CR | Actual | $214,649 | 6 | REPLACE BRIDGE AND APPROACHES |
0044-04-044 | Montague/ Wichita Falls |
US 82 | Actual | $6,249,421 | 6 | REPLACE EXISTING RAILROAD UNDERPASS AND EMBANKMENT |
0675-08-071 | Montgomery/ Houston |
IH 45 | Actual | $1,095,537 | 5 | INSTALL COMPUTERIZED TRANSPORTATION MANAGEMENT SYSTEM |
0912-37-190 | Montgomery/ Houston |
CS | Actual | $2,300,989 | 5 | CONSTRUCT INTERMODAL TERMINAL |
1400-04-035 | Montgomery/ Houston |
FM 1774 | Actual | $11,301,777 | 11 | RECONSTRUCT ROADWAY |
0908-20-021 | Nolan/ Abilene |
CR | Actual | $240,230 | 6 | REPLACE BRIDGE AND APPROACHES |
0908-20-022 | Nolan/ Abilene |
CR | Actual | $391,137 | 6 | REPLACE BRIDGE AND APPROACHES |
0326-05-002 | Nueces/ Corpus Christi |
BS 286A | Actual | $5,480,201 | 1 | REHABILITATE ROADWAY AND WIDEN |
0617-01-173 | Nueces/ Corpus Christi |
SH 358 | Actual | $176,120 | 11 | LANDSCAPE |
0617-01-181 | Nueces/ Corpus Christi |
SH 358 | Actual | $385,794 | 11 | LANDSCAPE |
1069-01-031 | Nueces/ Corpus Christi |
SH 357 | Actual | $152,606 | 8 | INSTALL TRAFFIC SIGNAL |
1557-01-039 | Nueces/ Corpus Christi |
FM 43 | Actual | $126,677 | 8 | INSTALL TRAFFIC SIGNAL |
1558-02-025 | Nueces/ Corpus Christi |
FM 70 | Actual | $806,742 | 1 | BRIDGE REPLACEMENT |
2263-02-087 | Nueces/ Corpus Christi |
SH 361 | Actual | $3,572,850 | 10 | REPLACE CREOSOTE SYSTEM, FENDER & DOLPHINS AT FERRY LANDINGS |
0920-30-073 | Orange/ Beaumont |
CS | Actual | $1,406,664 | 8 | RAILROAD SIGNAL UPGRADE |
0902-39-026 | Palo Pinto/ Fort Worth |
CR | Actual | $276,960 | 6 | REPLACE BRIDGE AND APPROACHES |
1222-01-014 | Panola/ Atlanta |
FM 10 | Actual | $2,848,993 | 6 | REPLACE 3 BRIDGES & APPROACHES ON 2 - LANE RURAL HIGHWAY |
1601-01-018 | Parker/ Fort Worth |
FM 730 | Actual | $2,502,494 | 1 | REPLACE BRIDGE |
0067-01-077 | Randall/ Amarillo |
US 87 | Actual | $956,530 | 1 | LANDSCAPE ENHANCEMENT |
2400-01-011 | Robertson/ Bryan |
FM 979 | Actual | $50,639 | 10 | MISCELLANEOUS WORK CONSISTING OF THE INSTALLATION OF AN |
1017-01-014 | Rockwall/ Dallas |
FM 552 | Actual | $3,714,077 | 8 | RECONSTRUCT AND PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0087-06-028 | San Patricio/ Corpus Christi |
BS 359B | Actual | $144,867 | 10 | UPGRADE EXISTING SIDEWALK TO ADA STANDARDS |
0180-06-090 | San Patricio/ Corpus Christi |
BS 35-L | Actual | $239,707 | 8 | INSTALL SIDEWALK |
0039-01-075 | Starr/ Pharr |
US 83 | Actual | $1,350,622 | 1 | DRAINAGE IMPROVEMENTS AT 6TH STREET (ROMA) , LOS VILLAREALES, |
0908-25-011 | Stonewall/ Abilene |
CR | Actual | $314,826 | 6 | REPLACE BRIDGE AND APPROACHES |
0080-07-089 | Tarrant/ Fort Worth |
US 377 | Actual | $644,261 | 10 | LANDSCAPE DEVELOPMENT, TREE AND SHRUB PLANTING & IRRIGATION |
0094-01-030 | Tarrant/ Fort Worth |
SH 183 | Actual | $10,591,981 | 6 | REPLACE BRIDGE AND APPROACHES |
0363-01-136 | Tarrant/ Fort Worth |
SH 26 | Actual | $11,469,298 | 7 | WIDEN FROM 4 LANES TO 6 LANES INCLUDING C & G, STORM SEWER, |
0902-48-381 | Tarrant/ Fort Worth |
CR | Actual | $1,896,430 | 6 | REPLACE BRIDGE |
0902-48-787 | Tarrant/ Fort Worth |
VA | Actual | $464,001 | 7 | INSTALL WARNING DEVICES AND HIGH INTENSITY LED AT BOWEN RD; |
0902-48-798 | Tarrant/ Fort Worth |
CS | Actual | $50,000 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING; PRELIMINARY |
0902-48-800 | Tarrant/ Fort Worth |
VA | Actual | $1,000,000 | 7 | VANPOOL PROGRAM FY11; OPER VANPOOL SUBSIDY INITIATIVE FOR |
0902-48-801 | Tarrant/ Fort Worth |
CS | Actual | $277,375 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-805 | Tarrant/ Fort Worth |
CS | Actual | $50,000 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-806 | Tarrant/ Fort Worth |
CS | Actual | $32,500 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-807 | Tarrant/ Fort Worth |
CS | Actual | $50,000 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING; PRELIMINARY |
0902-48-808 | Tarrant/ Fort Worth |
CS | Actual | $112,225 | 7 | UPGRADE TO QUAD GATES, RESURFACE CROSSING |
0902-48-809 | Tarrant/ Fort Worth |
CS | Actual | $93,600 | 7 | UPGRADE TO QUAD GATE AND RESURFACE CROSSING |
0902-48-810 | Tarrant/ Fort Worth |
CS | Actual | $232,000 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-811 | Tarrant/ Fort Worth |
CS | Actual | $349,513 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-812 | Tarrant/ Fort Worth |
CS | Actual | $338,233 | 7 | UPGRADE TO QUAD GATES AND RESURFACE CROSSING |
0902-48-813 | Tarrant/ Fort Worth |
CS | Actual | $292,000 | 7 | UPGRADE TO QUAD GATES |
0902-48-814 | Tarrant/ Fort Worth |
VA | Actual | $400,000 | 5 | CONSTRUCT ADDITIONAL 80 SPACES; PARK AND RIDE / RAIL STATION |
0902-48-815 | Tarrant/ Fort Worth |
VA | Actual | $2,258,000 | 5 | CONSTRUCT SOUTH TO WEST Y RAIL CONNECTION AT UPRR GRADE |
0902-48-816 | Tarrant/ Fort Worth |
VA | Actual | $547,063 | 5 | PE FOR CONSTRUCTION OF STRUCTURES, TRACK AND SIGNAL |
0902-48-819 | Tarrant/ Fort Worth |
VA | Actual | $8,700,063 | 5 | CONSTRUCT STRUCTURES, TRACK AND SIGNALS FOR NEW BRIDGE OVER |
1978-01-054 | Tarrant/ Fort Worth |
FM 1938 | Actual | $180,708 | 10 | LANDSCAPING |
2855-01-016 | Tarrant/ Fort Worth |
RM 2871 | Actual | $1,796,479 | 1 | REHABILITATE AND WIDEN BRIDGE AND APPROACHES |
0125-03-042 | Throckmorton/ Wichita Falls |
US 183 | Actual | $271,132 | 11 | LANDSCAPE |
0919-30-033 | Titus/ Atlanta |
CS | Actual | $247,442 | 6 | REPLACE BRIDGE AND APPROACHES_ON E. FOURTEENTH ST. AT HAYES |
0264-07-031 | Tom Green/ San Angelo |
SL 306 | Actual | $5,987,628 | 11 | CONSTRUCT INTERCHANGE |
0907-00-158 | Tom Green/ San Angelo |
VA | Actual | $609,566 | 10 | CONSTRUCT CURB RAMPS |
0907-00-159 | Tom Green/ San Angelo |
VA | Actual | $806,768 | 10 | CONSTRUCT CURB RAMPS |
7107-09-003 | Tom Green/ San Angelo |
RL SO | Actual | $3,311,668 | 10 | REHAB RAILROAD BRIDGES, ROAD CROSSINGS, SWITCHES, AND RAIL |
0113-08-070 | Travis/ Austin |
US 290 | Actual | $1,063,830 | 1 | INSTALL CENTER TURN LANE AND PAVED SHOULDERS |
0113-13-144 | Travis/ Austin |
US 290 | Actual | $1,192,682 | 1 | REHABILITATE ROADWAY |
0113-13-149 | Travis/ Austin |
SH 71 | Actual | $34,982,607 | ROW | CONST UNDERPASS, FRT RDS & MAIN LANES |
0113-13-152 | Travis/ Austin |
LP 360 | Actual | $1,640,003 | 1 | MILL, SEAL & THIN OVERLAY |
0914-00-297 | Travis/ Austin |
VA | Actual | $387,814 | 1 | SIGNS, STRUCT & LANE CONTROL SIGNAL |
0914-00-329 | Travis/ Austin |
VA | Actual | $20,000 | 7 | MODEL IMPROVEMENTS II |
0914-00-330 | Travis/ Austin |
VA | Actual | $300,000 | 7 | AIR QUALITY PROG CONGST MANGMT PROG |
0914-00-331 | Travis/ Austin |
VA | Actual | $600,000 | 7 | IMPRVMTS TO CAMPO TRVL DEMAND MODEL |
0914-04-187 | Travis/ Austin |
CS | Actual | $1,277,049 | ROW | REPLACE BRIDGE AND APPROACHES |
0914-04-268 | Travis/ Austin |
VA | Actual | $1,195,085 | 10 | CONSTRUCT CURB RAMPS___ (ON - SYSTEM) |
1377-01-019 | Travis/ Austin |
FM 1327 | Actual | $181,177 | 8 | RESURFACE, RESTORE SKID VALUE (SKIDABRADER) |
2102-01-062 | Travis/ Austin |
RM 2244 | Actual | $1,471,599 | ROW | CONST 4 LN URBAN RDWY W / CONT LTL |
3136-01-169 | Travis/ Austin |
LP 1 | Actual | $246,629 | 11 | LANDSCAPING AND IRRIGATION (ALONG FRONTAGE ROADS) |
0946-03-022 | Upshur/ Atlanta |
FM 593 | Actual | $1,107,363 | 8 | SAFETY TREAT FIXED OBJECTS |
1706-01-022 | Walker/ Bryan |
FM 1791 | Actual | $1,421,557 | 1 | REPLACEMENT OF EXISTING BRIDGE FACILITY CONSISTING OF |
2673-02-010 | Washington/ Bryan |
FM 2679 | Actual | $1,578,701 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
0922-33-092 | Webb/ Laredo |
CR | Actual | $296,293 | 6 | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
0903-03-099 | Wichita/ Wichita Falls |
CS | Actual | $1,910,891 | 9 | HIKE AND BIKE TRAIL (SECTIONS 3, 4, 5 AND 8) |
0015-08-133 | Williamson/ Austin |
IH 35 | Actual | $113,599 | 1 | INTERSECTION IMPROVEMENTS |
0683-06-029 | Williamson/ Austin |
SH 45 | Actual | $92,268 | 7 | COMBINE LTL & U - TURN LANES TO SHARED |
0914-05-160 | Williamson/ Austin |
VA | Actual | $306,045 | 8 | SIDEWALKS & CROSSWALKS |
1378-02-037 | Williamson/ Austin |
RM 1431 | Actual | $357,256 | 11 | LANDSCAPING, IRRIGATION & PAVERS |
0352-01-055 | Wise/ Fort Worth |
SH 114 | Actual | $2,884,900 | 8 | CONSTRUCT GRADE SEPARATION |
1606-02-013 | Wise/ Fort Worth |
FM 2123 | Actual | $1,968,338 | 6 | REPL BRIDGES |
|
|