CCSJ: 0369-01-036 | |||
| District: | San Antonio | Let Date: | OCT 2011 |
| Highway: | SH 127 | Let Status: | Actual |
| Project ID: | STP 2012(077) | CSJ: | 0369-01-036 |
| Description: | REHAB AND WIDEN NARROW ROADWAY TO ADD SHOULDERS & PAV MRK & | Handling Code: |
|
| Limits From: | 0.3 MI NW OF FM 2690 | Fund Cat: | 1 |
| Limits To: | US 83 | Estimate: | $2,828,586 |
| Length: | 4.8 Miles | Actual: | $2,575,821 |
|
Back... |
Totals for 0369-01-036 | ||
|---|---|---|---|
| Length: | 4.8 Miles | ||
| Estimate: | $2,828,586 | ||
| Actual: | $2,575,821 | ||
CCSJ: 0595-01-008 | |||
| District: | San Antonio | Let Date: | AUG 2012 |
| Highway: | FM 1796 | Let Status: | Actual |
| Project ID: | STP 2013(034) | CSJ: | 0595-01-008 |
| Description: | REHAB AND WIDEN NARROW ROADWAY | Handling Code: |
|
| Limits From: | MEDINA COUNTY LINE | Fund Cat: | 1 |
| Limits To: | FM 187 | Estimate: | $2,228,384 |
| Length: | 3.8 Miles | Actual: | $1,993,667 |
|
Award Status Bid Tabulations Back... |
Totals for 0595-01-008 | ||
| Length: | 3.8 Miles | ||
| Estimate: | $2,228,384 | ||
| Actual: | $1,993,667 | ||
CCSJ: 1168-02-015 | |||
| District: | San Antonio | Let Date: | AUG 2012 |
| Highway: | FM 1049 | Let Status: | Actual |
| Project ID: | STP 2013(036) | CSJ: | 1168-02-015 |
| Description: | REHAB AND WIDEN NARROW ROADWAY TO ADD SHOULDERS | Handling Code: |
|
| Limits From: | SH 127 | Fund Cat: | 1 |
| Limits To: | 4.6 MI SOUTH OF SH 127 | Estimate: | $2,592,694 |
| Length: | 4.6 Miles | Actual: | $2,094,081 |
|
Award Status Bid Tabulations Back... |
Totals for 1168-02-015 | ||
| Length: | 4.6 Miles | ||
| Estimate: | $2,592,694 | ||
| Actual: | $2,094,081 | ||
CCSJ: 1169-01-023 | |||
| District: | San Antonio | Let Date: | OCT 2011 |
| Highway: | RM 187 | Let Status: | Actual |
| Project ID: | STP 2007(845) | CSJ: | 0678-01-027 |
| Description: | MILL, OVERLAY & PAVEMENT MARKINGS | Handling Code: |
|
| Limits From: | RM 1050 | Fund Cat: | 1 |
| Limits To: | BANDERA COUNTY LINE | Estimate: | $599,335 |
| Length: | 1.2 Miles | Actual: | $626,486 |
| District: | San Antonio | Let Date: | OCT 2011 |
| Highway: | RM 1050 | Let Status: | Actual |
| Project ID: | STP 2007(845) | CSJ: | 1169-01-023 |
| Description: | WIDEN NARROW ROADWAY AND ADD SHOULDERS | Handling Code: |
|
| Limits From: | RM 187 | Fund Cat: | 1 |
| Limits To: | US 83 | Estimate: | $7,689,032 |
| Length: | 14.7 Miles | Actual: | $7,832,674 |
|
Back... |
Totals for 1169-01-023 | ||
| Length: | 15.9 Miles | ||
| Estimate: | $8,288,367 | ||
| Actual: | $8,459,160 | ||
CCSJ: 1590-01-021 | |||
| District: | San Antonio | Let Date: | AUG 2012 |
| Highway: | FM 481 | Let Status: | Actual |
| Project ID: | BR 2012(755) | CSJ: | 1590-01-021 |
| Description: | REPLACE BRIDGE | Handling Code: |
|
| Limits From: | AT NUECES RIVER | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $2,432,609 |
| Length: | 0.3 Miles | Actual: | $2,663,513 |
|
Award Status Bid Tabulations Back... |
Totals for 1590-01-021 | ||
| Length: | 0.3 Miles | ||
| Estimate: | $2,432,609 | ||
| Actual: | $2,663,513 | ||
|
| |