Detail Letting Schedule for Fort Bend County (FY 2017)
| Fort Bend County (FY 2017) |
CCSJ: 0027-06-046 |
|||
| District: | HOUSTON | Let Date: | Jun 2017 |
| Highway: | US 90A | Let Status: | Actual |
| Project ID: | NH 2017(965) | CSJ: | 0027-06-046 |
| Description: | REPLACE RAILROAD UNDERPASS | Handling Code: | |
| Limits From: | AT UP RR IN ROSENBERG | Fund Cat: | 2M |
| Limits To: | . | ESTIMATE: | $13,340,497 |
| Length: | 1.1 | Actual | $12,892,702 |
| District: | HOUSTON | Let Date: | Jun 2017 |
| Highway: | SS 529 | Let Status: | Actual |
| Project ID: | NH 2017(965) | CSJ: | 0089-09-080 |
| Description: | REALIGN ROADWAY | Handling Code: | |
| Limits From: | FM 1640 | Fund Cat: | 2M |
| Limits To: | US 90A | ESTIMATE: | $2,417,995 |
| Length: | 0.6 | Actual | $2,900,425 |
| District: | HOUSTON | Let Date: | Jun 2017 |
| Highway: | SH 36 | Let Status: | Actual |
| Project ID: | STP 2017(966) | CSJ: | 0187-05-045 |
| Description: | REPLACE RAILROAD UNDERPASS | Handling Code: | |
| Limits From: | AT UP RR IN ROSENBERG | Fund Cat: | 2M |
| Limits To: | . | ESTIMATE: | $8,878,837 |
| Length: | 0.6 | Actual | $9,034,758 |
| Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0027-06-046 | ||
|---|---|---|---|
| Length: | 2.3 | ||
| Estimate: | $24,637,330 | ||
| Actual: | $24,827,885 | ||
CCSJ: 0027-06-057 |
|||
| District: | HOUSTON | Let Date: | Sep 2016 |
| Highway: | US 90A | Let Status: | Actual |
| Project ID: | STP 2017(044) | CSJ: | 0027-06-057 |
| Description: | BASE REPAIR AND 1.5" ACP OVERLAY | Handling Code: | |
| Limits From: | 0.267 MILE EAST OF SPUR 10 | Fund Cat: | 1 |
| Limits To: | 0.147 MILE WEST OF SPUR 529 | ESTIMATE: | $974,274 |
| Length: | 3.9 | Actual | $741,888 |
| Back... | Totals for 0027-06-057 | ||
| Length: | 3.9 | ||
| Estimate: | $974,274 | ||
| Actual: | $741,888 | ||
CCSJ: 0027-07-032 |
|||
| District: | HOUSTON | Let Date: | Jan 2017 |
| Highway: | US 90A | Let Status: | Actual |
| Project ID: | C 27-7-32 | CSJ: | 0027-07-032 |
| Description: | REPLACE RAILROAD UNDERPASS | Handling Code: | |
| Limits From: | 0.21 MILES WEST OF LANE DRIVE | Fund Cat: | 3 |
| Limits To: | FM 3155 | ESTIMATE: | $20,263,944 |
| Length: | 0.6 | Actual | $18,405,189 |
| Bid Tabulations Back... | Totals for 0027-07-032 | ||
| Length: | 0.6 | ||
| Estimate: | $20,263,944 | ||
| Actual: | $18,405,189 | ||
CCSJ: 0027-08-179 |
|||
| District: | HOUSTON | Let Date: | Apr 2017 |
| Highway: | US 90A | Let Status: | Actual |
| Project ID: | ER 1702(162) | CSJ: | 0027-08-179 |
| Description: | REPLACEMENT OF TRAFFIC SIGNAL CABINET | Handling Code: | XX |
| Limits From: | AT HARLEM RD | Fund Cat: | 10 |
| Limits To: | . | ESTIMATE: | $12,306 |
| Length: | 0.1 | Actual | $12,306 |
| Back... | Totals for 0027-08-179 | ||
| Length: | 0.1 | ||
| Estimate: | $12,306 | ||
| Actual: | $12,306 | ||
CCSJ: 0027-12-153 |
|||
| District: | HOUSTON | Let Date: | Apr 2017 |
| Highway: | IH 69 | Let Status: | Actual |
| Project ID: | ER 1702(163) | CSJ: | 0027-12-153 |
| Description: | CONSTRUCTION OF MISCELLANEOUS WORK CONSISTING OF EMBANKMENT | Handling Code: | XX |
| Limits From: | AT BRAZOS RIVER | Fund Cat: | 10 |
| Limits To: | . | ESTIMATE: | $1,562,568 |
| Length: | 0.2 | Actual | $1,562,568 |
| Back... | Totals for 0027-12-153 | ||
| Length: | 0.2 | ||
| Estimate: | $1,562,568 | ||
| Actual: | $1,562,568 | ||
CCSJ: 0271-05-042 |
|||
| District: | HOUSTON | Let Date: | Dec 2016 |
| Highway: | IH 10 | Let Status: | Actual |
| Project ID: | CC 271-5-42 | CSJ: | 0271-05-042 |
| Description: | ENTRANCE AND EXIT RAMPS RELOCATION, EXTEND FRONTAGE ROAD AND | Handling Code: | |
| Limits From: | CANE ISLAND PARKWAY | Fund Cat: | 3 |
| Limits To: | FM 1463 | ESTIMATE: | $2,453,647 |
| Length: | 0.9 | Actual | $2,297,995 |
| Back... | Totals for 0271-05-042 | ||
| Length: | 0.9 | ||
| Estimate: | $2,453,647 | ||
| Actual: | $2,297,995 | ||
CCSJ: 0271-05-043 |
|||
| District: | HOUSTON | Let Date: | Jan 2017 |
| Highway: | IH 10 | Let Status: | Actual |
| Project ID: | NH 2017(487) | CSJ: | 0271-05-043 |
| Description: | CONSTRUCT INTERSECTION IMPROVEMENTS | Handling Code: | |
| Limits From: | AT FM 1463 | Fund Cat: | 11 |
| Limits To: | . | ESTIMATE: | $936,142 |
| Length: | 0.1 | Actual | $1,107,206 |
| Bid Tabulations Back... | Totals for 0271-05-043 | ||
| Length: | 0.1 | ||
| Estimate: | $936,142 | ||
| Actual: | $1,107,206 | ||
CCSJ: 0527-06-019 |
|||
| District: | HOUSTON | Let Date: | Sep 2016 |
| Highway: | FM 360 | Let Status: | Actual |
| Project ID: | STP 2017(113) | CSJ: | 0527-06-019 |
| Description: | BASE REPAIR, MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: | |
| Limits From: | SH 36 | Fund Cat: | 1 |
| Limits To: | US 59 | ESTIMATE: | $392,258 |
| Length: | 1.9 | Actual | $320,888 |
| District: | HOUSTON | Let Date: | Sep 2016 |
| Highway: | SS 529 | Let Status: | Actual |
| Project ID: | STP 2017(113) | CSJ: | 0089-09-084 |
| Description: | BASE REPAIR, MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: | |
| Limits From: | US 59 | Fund Cat: | 1 |
| Limits To: | US 90A | ESTIMATE: | $940,611 |
| Length: | 2.8 | Actual | $764,322 |
| District: | HOUSTON | Let Date: | Sep 2016 |
| Highway: | FM 442 | Let Status: | Actual |
| Project ID: | STP 2017(113) | CSJ: | 0838-02-020 |
| Description: | BASE REPAIR, MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: | |
| Limits From: | WHARTON C/L | Fund Cat: | 1 |
| Limits To: | SH 36 | ESTIMATE: | $527,068 |
| Length: | 6.6 | Actual | $397,693 |
| Back... | Totals for 0527-06-019 | ||
| Length: | 11.3 | ||
| Estimate: | $1,859,938 | ||
| Actual: | $1,482,902 | ||
CCSJ: 0543-03-072 |
|||
| District: | HOUSTON | Let Date: | Mar 2017 |
| Highway: | FM 762 | Let Status: | Actual |
| Project ID: | STP 2017(822) | CSJ: | 0543-03-072 |
| Description: | BASE REPAIR AND 1.5" ACP OVERLAY | Handling Code: | |
| Limits From: | 1.524 MI. SOUTH OF BRIDLEWOOD DRIVE | Fund Cat: | 1 |
| Limits To: | FM 1462 | ESTIMATE: | $2,513,313 |
| Length: | 13.9 | Actual | $1,849,420 |
| Proposal Request List Showing Order Bid Tabulations Addenda Bid List Award Status Back... | Totals for 0543-03-072 | ||
| Length: | 13.9 | ||
| Estimate: | $2,513,313 | ||
| Actual: | $1,849,420 | ||
CCSJ: 0912-34-143 |
|||
| District: | HOUSTON | Let Date: | Feb 2017 |
| Highway: | CS | Let Status: | Actual |
| Project ID: | C 912-34-143 | CSJ: | 0912-34-143 |
| Description: | CONSTRUCT 4 LANES CONCRETE DIVIDED, STORM SEWERS, ESPLANADE, | Handling Code: | |
| Limits From: | ON TRAMMEL FRESNO RD,FROM VICKSBURG | Fund Cat: | 3 |
| Limits To: | FT BEND PKWY | ESTIMATE: | $5,192,123 |
| Length: | 0.6 | Actual | $3,825,527 |
| Award Status Bid Tabulations Bid List Back... | Totals for 0912-34-143 | ||
| Length: | 0.6 | ||
| Estimate: | $5,192,123 | ||
| Actual: | $3,825,527 | ||
CCSJ: 1965-01-006 |
|||
| District: | HOUSTON | Let Date: | Feb 2017 |
| Highway: | FM 1994 | Let Status: | Actual |
| Project ID: | STP 2017(640) | CSJ: | 1965-01-006 |
| Description: | BASE REPAIR AND 1.5" ACP OVERLAY | Handling Code: | |
| Limits From: | SH 36 | Fund Cat: | 1 |
| Limits To: | FM 361 | ESTIMATE: | $988,773 |
| Length: | 3.9 | Actual | $850,261 |
| District: | HOUSTON | Let Date: | Feb 2017 |
| Highway: | FM 1994 | Let Status: | Actual |
| Project ID: | STP 2017(640) | CSJ: | 1965-02-009 |
| Description: | BASE REPAIR AND 1.5" ACP OVERLAY | Handling Code: | |
| Limits From: | FM 361 | Fund Cat: | 1 |
| Limits To: | FM 762 | ESTIMATE: | $1,145,161 |
| Length: | 3.7 | Actual | $924,300 |
| Award Status Bid Tabulations Bid List Back... | Totals for 1965-01-006 | ||
| Length: | 7.6 | ||
| Estimate: | $2,133,934 | ||
| Actual: | $1,774,561 | ||
CCSJ: 2940-02-010 |
|||
| District: | HOUSTON | Let Date: | Apr 2017 |
| Highway: | FM 2919 | Let Status: | Actual |
| Project ID: | ER 1702(165) | CSJ: | 2940-02-010 |
| Description: | REMOVAL AND DISPOSAL OF ALL DAMAGED ASPHALT AND DEBRIS. | Handling Code: | XX |
| Limits From: | AT SAN BERNARD RIVER | Fund Cat: | 10 |
| Limits To: | . | ESTIMATE: | $5,689 |
| Length: | 0.1 | Actual | $5,689 |
| Back... | Totals for 2940-02-010 | ||
| Length: | 0.1 | ||
| Estimate: | $5,689 | ||
| Actual: | $5,689 | ||
CCSJ: 3422-01-011 |
|||
| District: | HOUSTON | Let Date: | Apr 2017 |
| Highway: | PR 72 | Let Status: | Actual |
| Project ID: | C 3422-1-11 | CSJ: | 3422-01-011 |
| Description: | 1.5 INCH PLANING, 1.5 INCH ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: | |
| Limits From: | IN BRAZOS BEND STATE PARK | Fund Cat: | 10 |
| Limits To: | . | ESTIMATE: | $583,592 |
| Length: | 1.9 | Actual | $563,996 |
| Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 3422-01-011 | ||
| Length: | 1.9 | ||
| Estimate: | $583,592 | ||
| Actual: | $563,996 | ||
CCSJ: 3510-04-053 |
|||
| District: | HOUSTON | Let Date: | Nov 2016 |
| Highway: | SH 99 | Let Status: | Actual |
| Project ID: | NH 2017(247) | CSJ: | 3510-04-053 |
| Description: | ADD U-TURN AND LEFT TURN LANES AND REBUILD TRAFFIC SIGNALS | Handling Code: | |
| Limits From: | AT HARLEM ROAD | Fund Cat: | 3 |
| Limits To: | SH 99 AT HARLEM ROAD, NB & SB | ESTIMATE: | $2,129,089 |
| Length: | 0.6 | Actual | $2,240,983 |
| Back... | Totals for 3510-04-053 | ||
| Length: | 0.6 | ||
| Estimate: | $2,129,089 | ||
| Actual: | $2,240,983 | ||
| Handling Code | Definition |
|---|---|
| XX | Project not processed through statewide letting |
| TR | Transfer of funds |
| LC | Project let through local entity |
| LC | Project not charged against district apportionment |
| Let Status | Definition |
|---|---|
| Tentative | Estimated letting date for this project |
| Approved | Project has administrative approval to be let |
| Actual | Project was let to contract |