Detail Letting Schedule for Refugio County (FY 2018)
| Refugio County (FY 2018) |
CCSJ: 0180-02-043 |
|||
| District: | CORPUS CHRISTI | Let Date: | Aug 2018 |
| Highway: | SH 35 | Let Status: | Actual |
| Project ID: | ER 2018(918) | CSJ: | 0180-02-043 |
| Description: | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMANGED BY HIGH WIND | Handling Code: | XX |
| Limits From: | ON SH35 270 FT S SH239 INTERSECTION | Fund Cat: | 10 |
| Limits To: | WITH SH 35 | ESTIMATE: | $7,039 |
| Length: | 0.1 | Actual | $7,039 |
| Back... | Totals for 0180-02-043 | ||
|---|---|---|---|
| Length: | 0.1 | ||
| Estimate: | $7,039 | ||
| Actual: | $7,039 | ||
CCSJ: 0371-03-122 |
|||
| District: | CORPUS CHRISTI | Let Date: | Aug 2018 |
| Highway: | US 77 | Let Status: | Actual |
| Project ID: | ER 2018(916) | CSJ: | 0371-03-122 |
| Description: | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | Handling Code: | XX |
| Limits From: | 545 FT N OF US 183 | Fund Cat: | 10 |
| Limits To: | 311 FT S OF DEL MAR ST. | ESTIMATE: | $21,812 |
| Length: | 0.1 | Actual | $21,812 |
| Back... | Totals for 0371-03-122 | ||
| Length: | 0.1 | ||
| Estimate: | $21,812 | ||
| Actual: | $21,812 | ||
CCSJ: 1423-01-034 |
|||
| District: | CORPUS CHRISTI | Let Date: | Jun 2018 |
| Highway: | FM 1360 | Let Status: | Actual |
| Project ID: | STP 2018(978)HES | CSJ: | 1423-01-034 |
| Description: | SAFETY TRT FIXED OBJ, WIDEN LANES, WIDEN PAVED SHOULDERS | Handling Code: | |
| Limits From: | BOENIG RD. | Fund Cat: | 1 |
| Limits To: | FM 629 | ESTIMATE: | $1,306,334 |
| Length: | 3.1 | Actual | $1,520,496 |
| Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 1423-01-034 | ||
| Length: | 3.1 | ||
| Estimate: | $1,306,334 | ||
| Actual: | $1,520,496 | ||
| Handling Code | Definition |
|---|---|
| XX | Project not processed through statewide letting |
| TR | Transfer of funds |
| LC | Project let through local entity |
| LC | Project not charged against district apportionment |
| Let Status | Definition |
|---|---|
| Tentative | Estimated letting date for this project |
| Approved | Project has administrative approval to be let |
| Actual | Project was let to contract |