Detail Letting Schedule for Stephens County (FY 2018)
| Stephens County (FY 2018) |
CCSJ: 0257-01-047 |
|||
| District: | BROWNWOOD | Let Date: | Nov 2017 |
| Highway: | US 183 | Let Status: | Actual |
| Project ID: | STP 2018(244) | CSJ: | 0257-01-047 |
| Description: | DRAIANGE IMPROVEMENTS | Handling Code: | |
| Limits From: | .5 MI N OF FM 2231 | Fund Cat: | 11 |
| Limits To: | FM 2231 | ESTIMATE: | $307,470 |
| Length: | 0.5 | Actual | $223,074 |
| Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0257-01-047 | ||
|---|---|---|---|
| Length: | 0.5 | ||
| Estimate: | $307,470 | ||
| Actual: | $223,074 | ||
CCSJ: 0923-22-021 |
|||
| District: | BROWNWOOD | Let Date: | Oct 2017 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2018(217) | CSJ: | 0923-22-021 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
| Limits From: | ON CR 157 AT W FORK GONZALES CREEK | Fund Cat: | 6 |
| Limits To: | . | ESTIMATE: | $360,230 |
| Length: | 0.1 | Actual | $284,044 |
| District: | BROWNWOOD | Let Date: | Oct 2017 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2017(999) | CSJ: | 0923-22-022 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
| Limits From: | ON CR 154 AT W FORK GONZALES CREEK | Fund Cat: | 6 |
| Limits To: | . | ESTIMATE: | $459,692 |
| Length: | 0.1 | Actual | $392,223 |
| Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0923-22-021 | ||
| Length: | 0.2 | ||
| Estimate: | $819,922 | ||
| Actual: | $676,267 | ||
| Handling Code | Definition |
|---|---|
| XX | Project not processed through statewide letting |
| TR | Transfer of funds |
| LC | Project let through local entity |
| LC | Project not charged against district apportionment |
| Let Status | Definition |
|---|---|
| Tentative | Estimated letting date for this project |
| Approved | Project has administrative approval to be let |
| Actual | Project was let to contract |