Detail Letting Schedule for Brazoria County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Brazoria County (FY 2021) |
CCSJ: 0111-04-035 |
|||
District: | HOUSTON | Let Date: | Apr 2020 |
Highway: | FM 521 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0111-04-035 |
Description: | PAVEMENT REPAIR, SEAL COAT AND 1.5 IN PFC OVERLAY | Handling Code: | |
Limits From: | BS 288B | Fund Cat: | 1 |
Limits To: | FM 1462 | ESTIMATE: | $1,842,000 |
Length: | 4.7 | Actual | $0 |
Proposal Request Back... | Totals for 0111-04-035 | ||
---|---|---|---|
Length: | 4.7 | ||
Estimate: | $1,842,000 | ||
Actual: | |||
CCSJ: 0111-08-100 |
|||
District: | HOUSTON | Let Date: | Dec 2019 |
Highway: | SH 36 | Let Status: | Tentative |
Project ID: | NH 1802(306) | CSJ: | 0111-08-100 |
Description: | WIDEN TO 4-LANE DIVIDED | Handling Code: | |
Limits From: | 0.5 MI S OF THE BRAZOS RIVER | Fund Cat: | 2M |
Limits To: | FM 1495 (SEG. 15 | ESTIMATE: | $8,500,000 |
Length: | 1.2 | Actual | $0 |
Back... | Totals for 0111-08-100 | ||
Length: | 1.2 | ||
Estimate: | $8,500,000 | ||
Actual: | |||
CCSJ: 0111-09-042 |
|||
District: | HOUSTON | Let Date: | Jul 2020 |
Highway: | BS 288B | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0111-09-042 |
Description: | WIDEN TO ADD 8 FT SHOULDERS, PAVEMENT REPAIR, OCST, 1.5 IN | Handling Code: | |
Limits From: | FM 523 | Fund Cat: | 1 |
Limits To: | FM 521 | ESTIMATE: | $5,445,000 |
Length: | 5.9 | Actual | $0 |
Back... | Totals for 0111-09-042 | ||
Length: | 5.9 | ||
Estimate: | $5,445,000 | ||
Actual: | |||
CCSJ: 0178-03-156 |
|||
District: | HOUSTON | Let Date: | Aug 2020 |
Highway: | SH 35 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0178-03-156 |
Description: | WIDEN SHOULDERS, 1.5 IN LEVEL UP, 1.5 IN ACP OVERLAY, | Handling Code: | |
Limits From: | FM 2403 | Fund Cat: | 1 |
Limits To: | FM 523 | ESTIMATE: | $6,695,000 |
Length: | 15.4 | Actual | $0 |
Back... | Totals for 0178-03-156 | ||
Length: | 15.4 | ||
Estimate: | $6,695,000 | ||
Actual: | |||
CCSJ: 0188-06-054 |
|||
District: | HOUSTON | Let Date: | Feb 2020 |
Highway: | SH 36 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0188-06-054 |
Description: | INSTALL LED FLASHING CHEVRONS (CURVE) | Handling Code: | |
Limits From: | 0.89 MI N OF CR 217 | Fund Cat: | 8 |
Limits To: | 0.61 MI S OF CR 217 | ESTIMATE: | $150,800 |
Length: | 1.5 | Actual | $0 |
Back... | Totals for 0188-06-054 | ||
Length: | 1.5 | ||
Estimate: | $150,800 | ||
Actual: | |||
CCSJ: 0192-02-054 |
|||
District: | HOUSTON | Let Date: | Mar 2020 |
Highway: | SH 6 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0192-02-054 |
Description: | IMPROVE TRAFFIC SIGNALS, INSTALL ADVANCED WARNING SIGNALS | Handling Code: | |
Limits From: | AT CR 146 (SCHROEDER LN) | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $322,114 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0192-02-054 | ||
Length: | 0.2 | ||
Estimate: | $322,114 | ||
Actual: | |||
CCSJ: 0192-02-055 |
|||
District: | HOUSTON | Let Date: | Mar 2020 |
Highway: | SH 6 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0192-02-055 |
Description: | IMPROVE TRAFFIC SIGNALS, INSTALL ADVANCED WARNING SIGNALS | Handling Code: | |
Limits From: | AT PEARLAND SITES RD/CR 99 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $322,114 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0192-02-055 | ||
Length: | 0.2 | ||
Estimate: | $322,114 | ||
Actual: | |||
CCSJ: 0192-02-056 |
|||
District: | HOUSTON | Let Date: | Dec 2019 |
Highway: | SH 6 | Let Status: | Tentative |
Project ID: | BR ( ) | CSJ: | 0192-02-056 |
Description: | REPLACE BEARING PADS (NBI# 12020019202029) | Handling Code: | |
Limits From: | AT MUSTANG BAYOU | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $115,555 |
Length: | 0.0 | Actual | $0 |
District: | HOUSTON | Let Date: | Dec 2019 |
Highway: | FM 2004 | Let Status: | Tentative |
Project ID: | BR ( ) | CSJ: | 2523-02-072 |
Description: | REPLACE BEARING PADS (NBI# 12020252302017) | Handling Code: | |
Limits From: | AT BRAZOS RIVER | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $103,140 |
Length: | 0.3 | Actual | $0 |
District: | HOUSTON | Let Date: | Dec 2019 |
Highway: | FM 2917 | Let Status: | Tentative |
Project ID: | BR ( ) | CSJ: | 2938-02-024 |
Description: | REPLACE BEARING PADS (NBI# 12020293802006) | Handling Code: | |
Limits From: | AT NEW BAYOU | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $103,140 |
Length: | 0.0 | Actual | $0 |
Award Status Back... | Totals for 0192-02-056 | ||
Length: | 0.3 | ||
Estimate: | $321,835 | ||
Actual: | |||
CCSJ: 0598-02-118 |
|||
District: | HOUSTON | Let Date: | Mar 2020 |
Highway: | SH 288 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0598-02-118 |
Description: | MILL, SEAL COAT AND 1.5 IN PFC OVERLAY | Handling Code: | |
Limits From: | HAYES CREEK | Fund Cat: | 1 |
Limits To: | FM 1462 | ESTIMATE: | $1,903,000 |
Length: | 2.8 | Actual | $0 |
District: | HOUSTON | Let Date: | Mar 2020 |
Highway: | SH 288 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0598-03-060 |
Description: | MILL, SEAL COAT AND 1.5 IN PFC OVERLAY | Handling Code: | |
Limits From: | FM 1462 | Fund Cat: | 1 |
Limits To: | BS 288B | ESTIMATE: | $3,805,000 |
Length: | 6.6 | Actual | $0 |
List Showing Order Back... | Totals for 0598-02-118 | ||
Length: | 9.4 | ||
Estimate: | $5,708,000 | ||
Actual: | |||
CCSJ: 0912-31-293 |
|||
District: | HOUSTON | Let Date: | May 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ( )MM | CSJ: | 0912-31-293 |
Description: | WIDEN TO 4 LANES | Handling Code: | LC |
Limits From: | SMITH RANCH RD; HUGHES RANCH RD | Fund Cat: | 3 |
Limits To: | N OF BROADWAY (FM 518) | ESTIMATE: | $4,948,242 |
Length: | 0.7 | Actual | $0 |
Back... | Totals for 0912-31-293 | ||
Length: | 0.7 | ||
Estimate: | $4,948,242 | ||
Actual: | |||
CCSJ: 0912-31-310 |
|||
District: | HOUSTON | Let Date: | Feb 2020 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0912-31-310 |
Description: | CONSTRUCT BRAZORIA COUNTY BICYCLE LOOP BY WIDENING SHOULDERS | Handling Code: | |
Limits From: | VARIOUS-FM ROADS 1462,2403,2917, | Fund Cat: | 11 |
Limits To: | 762,521,2004,523,528 AND SH 332 | ESTIMATE: | $4,033,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-31-310 | ||
Length: | 0 | ||
Estimate: | $4,033,000 | ||
Actual: | |||
CCSJ: 0912-31-319 |
|||
District: | HOUSTON | Let Date: | May 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ( )MM | CSJ: | 0912-31-319 |
Description: | WIDEN TO 4-LANE BLVD SECTION | Handling Code: | |
Limits From: | MYKAWA ROAD, HARRIS COUNTY LINE | Fund Cat: | 3 |
Limits To: | FM 518 | ESTIMATE: | $37,231,000 |
Length: | 2.3 | Actual | $0 |
District: | HOUSTON | Let Date: | May 2020 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ( )MM | CSJ: | 0912-72-564 |
Description: | WIDEN TO 4-LANE BLVD SECTION | Handling Code: | |
Limits From: | MYKAWA ROAD, BELTWAY 8 | Fund Cat: | 3 |
Limits To: | BRAZORIA COUNTY LINE | ESTIMATE: | $2,802,000 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0912-31-319 | ||
Length: | 2.5 | ||
Estimate: | $40,033,000 | ||
Actual: | |||
CCSJ: 1003-01-095 |
|||
District: | HOUSTON | Let Date: | Feb 2020 |
Highway: | FM 523 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1003-01-095 |
Description: | INSTALL INTERSECTION FLASHING BEACON, INSTALL ADVANCED | Handling Code: | |
Limits From: | AT SH 288 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $67,704 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 1003-01-095 | ||
Length: | 0.2 | ||
Estimate: | $67,704 | ||
Actual: | |||
CCSJ: 1003-01-096 |
|||
District: | HOUSTON | Let Date: | Feb 2020 |
Highway: | FM 523 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1003-01-096 |
Description: | INSTALL LED FLASHING CHEVRONS (CURVE) | Handling Code: | |
Limits From: | 0.477 MI SOUTH OF CR 595 | Fund Cat: | 8 |
Limits To: | 0.977 MI SOUTH OF CR 595 | ESTIMATE: | $150,800 |
Length: | 0.5 | Actual | $0 |
Back... | Totals for 1003-01-096 | ||
Length: | 0.5 | ||
Estimate: | $150,800 | ||
Actual: | |||
CCSJ: 1004-01-060 |
|||
District: | HOUSTON | Let Date: | Apr 2020 |
Highway: | FM 521 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1004-01-060 |
Description: | PAVEMENT REPAIR, SEAL COAT AND 1.5 IN ACP OVERLAY | Handling Code: | |
Limits From: | SAN BERNARD RIVER | Fund Cat: | 1 |
Limits To: | SH 36 | ESTIMATE: | $953,000 |
Length: | 2.5 | Actual | $0 |
Back... | Totals for 1004-01-060 | ||
Length: | 2.5 | ||
Estimate: | $953,000 | ||
Actual: | |||
CCSJ: 1004-01-061 |
|||
District: | HOUSTON | Let Date: | Jun 2020 |
Highway: | FM 521 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1004-01-061 |
Description: | MILLED EDGELINE RUMBLE STRIPS AND MILLED CENTERLINE RUMBLE | Handling Code: | |
Limits From: | FM 524 | Fund Cat: | 8 |
Limits To: | 0.445 MILES SOUTH OF SH 36 | ESTIMATE: | $76,336 |
Length: | 5.6 | Actual | $0 |
District: | HOUSTON | Let Date: | Jun 2020 |
Highway: | FM 521 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0847-02-016 |
Description: | MILLED EDGELINE RUMBLE STRIPS AND MILLED CENTERLINE RUMBLE | Handling Code: | |
Limits From: | MATAGORDA COUNTY LINE | Fund Cat: | 8 |
Limits To: | FM 524 | ESTIMATE: | $50,891 |
Length: | 3.8 | Actual | $0 |
Back... | Totals for 1004-01-061 | ||
Length: | 9.4 | ||
Estimate: | $127,227 | ||
Actual: | |||
CCSJ: 1004-02-017 |
|||
District: | HOUSTON | Let Date: | Apr 2020 |
Highway: | FM 524 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1004-02-017 |
Description: | PAVEMENT REPAIR, SEAL COAT AND 1.5 IN ACP OVERLAY | Handling Code: | |
Limits From: | FM 1301 | Fund Cat: | 1 |
Limits To: | SH 35 | ESTIMATE: | $1,774,000 |
Length: | 7.7 | Actual | $0 |
Back... | Totals for 1004-02-017 | ||
Length: | 7.7 | ||
Estimate: | $1,774,000 | ||
Actual: | |||
CCSJ: 1412-02-019 |
|||
District: | HOUSTON | Let Date: | Feb 2020 |
Highway: | FM 1301 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 1412-02-019 |
Description: | INSTALL LED FLASHING CHEVRONS (CURVE) | Handling Code: | |
Limits From: | 0.1 MI WEST OF DONELY ROAD | Fund Cat: | 8 |
Limits To: | 0.1 MI EAST OF DONELY ROAD | ESTIMATE: | $150,800 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 1412-02-019 | ||
Length: | 0.2 | ||
Estimate: | $150,800 | ||
Actual: | |||
CCSJ: 2523-02-068 |
|||
District: | HOUSTON | Let Date: | May 2020 |
Highway: | FM 2004 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 2523-02-068 |
Description: | ADD SHOULDERS, WIDEN BRIDGES, REPLACE BRIDGE AT CHOCOLATE | Handling Code: | |
Limits From: | FM 523 | Fund Cat: | 1 |
Limits To: | GALVESTON COUNTY LINE | ESTIMATE: | $32,000,000 |
Length: | 20.6 | Actual | $0 |
Bid Tabulations Back... | Totals for 2523-02-068 | ||
Length: | 20.6 | ||
Estimate: | $32,000,000 | ||
Actual: | |||
CCSJ: 2524-02-022 |
|||
District: | HOUSTON | Let Date: | Sep 2019 |
Highway: | FM 2611 | Let Status: | Tentative |
Project ID: | BR 2018(103) | CSJ: | 2524-02-022 |
Description: | REPLACE BRIDGE AND APPROACHES (NBI# 12020252402001) | Handling Code: | |
Limits From: | AT SAN BERNARD RIVER | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $9,621,216 |
Length: | 0.8 | Actual | $0 |
Bid Tabulations Back... | Totals for 2524-02-022 | ||
Length: | 0.8 | ||
Estimate: | $9,621,216 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |