The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Colorado County (FY 2022)

CCSJ: 0026-06-035

District:YOAKUMLet Date:Nov 2021
Highway:US 90Let Status:Actual
Project ID:F 2022(093)CSJ:0026-06-035
Description:SEAL COATHandling
Code:
 
Limits From:FM 806Fund Cat:1
Limits To:0.056 MI W OF FRONT ST.ESTIMATE:$1,650,494
Length:1.4Actual$1,643,923
 
District:YOAKUMLet Date:Nov 2021
Highway:US 90Let Status:Actual
Project ID:F 2022(093)CSJ:0027-01-047
Description:SEAL COATHandling
Code:
 
Limits From:0.056 MI W OF FRONT STFund Cat:1
Limits To:FRONT STESTIMATE:$2,918
Length:0.1Actual$3,051
 
District:YOAKUMLet Date:Nov 2021
Highway:US 59Let Status:Actual
Project ID:F 2022(094)CSJ:0088-05-106
Description:SEAL COATHandling
Code:
 
Limits From:SS 91Fund Cat:1
Limits To:BU 59TESTIMATE:$137,585
Length:1.9Actual$139,803
 
District:YOAKUMLet Date:Nov 2021
Highway:US 59Let Status:Actual
Project ID:F 2022(094)CSJ:0089-03-094
Description:SEAL COATHandling
Code:
 
Limits From:550' W OF PUMPHREY ST.Fund Cat:1
Limits To:350' E OF CR 116ESTIMATE:$61,816
Length:0.9Actual$63,017
 
District:YOAKUMLet Date:Nov 2021
Highway:US 59Let Status:Actual
Project ID:F 2022(094)CSJ:0089-03-095
Description:SEAL COATHandling
Code:
 
Limits From:US 59 INTERCHANGEFund Cat:1
Limits To:LAVACA RIVERESTIMATE:$35,491
Length:0.9Actual$36,259
 
District:YOAKUMLet Date:Nov 2021
Highway:US 59Let Status:Actual
Project ID:F 2022(094)CSJ:0089-04-080
Description:SEAL COATHandling
Code:
 
Limits From:1000' W OF CR 407Fund Cat:1
Limits To:1150' E OF SH 111ESTIMATE:$89,371
Length:1.2Actual$91,009
 
District:YOAKUMLet Date:Nov 2021
Highway:US 59Let Status:Actual
Project ID:F 2022(094)CSJ:0089-04-081
Description:SEAL COATHandling
Code:
 
Limits From:1800' E OF FM 530Fund Cat:1
Limits To:800' E OF CR 407ESTIMATE:$129,099
Length:2.0Actual$130,725
 
District:YOAKUMLet Date:Nov 2021
Highway:SL 526Let Status:Actual
Project ID:C 89-16-5CSJ:0089-16-005
Description:SEAL COATHandling
Code:
 
Limits From:US 59Fund Cat:1
Limits To:US 59 (PIERCE)ESTIMATE:$75,255
Length:1.3Actual$75,631
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 238Let Status:Actual
Project ID:F 2022(093)CSJ:0144-04-047
Description:SEAL COATHandling
Code:
 
Limits From:FM 2433Fund Cat:1
Limits To:SH 316ESTIMATE:$115,619
Length:1.6Actual$117,218
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 185Let Status:Actual
Project ID:F 2022(093)CSJ:0144-05-046
Description:SEAL COATHandling
Code:
 
Limits From:SH 238Fund Cat:1
Limits To:RAILROAD AVEESTIMATE:$134,183
Length:2.0Actual$135,286
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 36Let Status:Actual
Project ID:F 2022(094)CSJ:0187-02-069
Description:SEAL COATHandling
Code:
 
Limits From:FM 2429Fund Cat:1
Limits To:FM 949ESTIMATE:$361,934
Length:4.2Actual$375,453
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 36Let Status:Actual
Project ID:F 2022(094)CSJ:0187-03-073
Description:SEAL COATHandling
Code:
 
Limits From:FM 949Fund Cat:1
Limits To:FM 2187ESTIMATE:$508,429
Length:5.6Actual$525,331
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 36Let Status:Actual
Project ID:F 2022(094)CSJ:0187-04-034
Description:SEAL COATHandling
Code:
 
Limits From:FM 1952Fund Cat:1
Limits To:FORT BEND C/LESTIMATE:$108,837
Length:1.9Actual$109,621
 
District:YOAKUMLet Date:Nov 2021
Highway:US 77Let Status:Actual
Project ID:F 2022(094)CSJ:0211-06-065
Description:SEAL COATHandling
Code:
 
Limits From:LEE C/LFund Cat:1
Limits To:400 FT N OF SH 71 N SERVICE ROADESTIMATE:$471,749
Length:11.5Actual$495,203
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1482Let Status:Actual
Project ID:C 211-11-3CSJ:0211-11-003
Description:SEAL COATHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:END OF MAINTENANCEESTIMATE:$16,171
Length:0.4Actual$16,246
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1681Let Status:Actual
Project ID:F 2022(093)CSJ:0215-12-010
Description:SEAL COATHandling
Code:
 
Limits From:WILSON C/LFund Cat:1
Limits To:SH 80ESTIMATE:$56,074
Length:1.2Actual$56,402
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 60Let Status:Actual
Project ID:F 2022(093)CSJ:0241-02-055
Description:SEAL COATHandling
Code:
 
Limits From:FM 3156Fund Cat:1
Limits To:1.045 MI S OF SH 35ESTIMATE:$168,229
Length:3.3Actual$174,018
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 60Let Status:Actual
Project ID:F 2022(093)CSJ:0241-03-030
Description:SEAL COATHandling
Code:
 
Limits From:1.045 MI S OF SH 35Fund Cat:1
Limits To:0.46 MI N OF FM 2668ESTIMATE:$74,710
Length:1.5Actual$78,769
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 71Let Status:Actual
Project ID:F 2022(094)CSJ:0265-07-052
Description:SEAL COATHandling
Code:
 
Limits From:SH 71Fund Cat:1
Limits To:0.7 MI E (LADY BIRD LOOP)ESTIMATE:$41,396
Length:0.7Actual$42,122
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 71Let Status:Actual
Project ID:F 2022(094)CSJ:0265-08-070
Description:SEAL COATHandling
Code:
 
Limits From:2.66 MI W OF US 77 (W INTERCHANGE)Fund Cat:1
Limits To:US 77 (FRONTAGE ROAD)ESTIMATE:$195,723
Length:2.3Actual$199,633
 
District:YOAKUMLet Date:Nov 2021
Highway:SL 543Let Status:Actual
Project ID:F 2022(093)CSJ:0265-12-004
Description:SEAL COATHandling
Code:
 
Limits From:SH 71 W OF WEST POINTFund Cat:1
Limits To:SH 71 E OF WEST POINTESTIMATE:$63,928
Length:1.6Actual$67,067
 
District:YOAKUMLet Date:Nov 2021
Highway:SL 220Let Status:Actual
Project ID:F 2022(093)CSJ:0265-15-004
Description:SEAL COATHandling
Code:
 
Limits From:SH 71 W OF PLUMFund Cat:1
Limits To:SH 71 E OF PLUMESTIMATE:$56,852
Length:1.4Actual$59,690
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 71Let Status:Actual
Project ID:F 2022(094)CSJ:0266-01-087
Description:SEAL COATHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:3.66 MI E OF BU 71ESTIMATE:$188,913
Length:0.0Actual$192,376
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 389Let Status:Actual
Project ID:F 2022(093)CSJ:0315-11-011
Description:SEAL COATHandling
Code:
 
Limits From:FAYETTE C/LFund Cat:1
Limits To:WASHINGTON C/LESTIMATE:$168,930
Length:4.0Actual$170,148
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 154Let Status:Actual
Project ID:F 2022(093)CSJ:0334-08-038
Description:SEAL COATHandling
Code:
 
Limits From:2.70 MI N OF FM 2237 (BUCKNERS CREEK)Fund Cat:1
Limits To:SH 95ESTIMATE:$445,378
Length:10.0Actual$448,150
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2431Let Status:Actual
Project ID:F 2022(093)CSJ:0346-03-034
Description:SEAL COATHandling
Code:
 
Limits From:SH 71Fund Cat:1
Limits To:FM 1468ESTIMATE:$509,537
Length:8.8Actual$513,528
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 111Let Status:Actual
Project ID:F 2022(093)CSJ:0346-07-041
Description:SEAL COATHandling
Code:
 
Limits From:3.388 MI S OF LAVACA C/LFund Cat:1
Limits To:US 59ESTIMATE:$523,647
Length:12.8Actual$546,820
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 456Let Status:Actual
Project ID:C 346-12-10CSJ:0346-12-010
Description:SEAL COATHandling
Code:
 
Limits From:SH 71Fund Cat:1
Limits To:END OF MAINTENANCEESTIMATE:$82,133
Length:2.5Actual$82,446
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 172Let Status:Actual
Project ID:F 2022(093)CSJ:0420-02-050
Description:SEAL COATHandling
Code:
 
Limits From:FM 616Fund Cat:1
Limits To:CALHOUN C/LESTIMATE:$492,471
Length:9.7Actual$499,545
 
District:YOAKUMLet Date:Nov 2021
Highway:SH 185Let Status:Actual
Project ID:F 2022(093)CSJ:0432-01-068
Description:SEAL COATHandling
Code:
 
Limits From:SH 35Fund Cat:1
Limits To:SH 238ESTIMATE:$372,582
Length:5.4Actual$373,157
 
District:YOAKUMLet Date:Nov 2021
Highway:UA 90Let Status:Actual
Project ID:F 2022(093)CSJ:0446-01-052
Description:SEAL COATHandling
Code:
 
Limits From:FM 2314Fund Cat:1
Limits To:FM 3283ESTIMATE:$438,641
Length:7.7Actual$443,846
 
District:YOAKUMLet Date:Nov 2021
Highway:UA 90Let Status:Actual
Project ID:F 2022(093)CSJ:0446-02-039
Description:SEAL COATHandling
Code:
 
Limits From:0.27 MI W OF SKULL CREEKFund Cat:1
Limits To:SH 71ESTIMATE:$128,320
Length:2.4Actual$130,498
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 616Let Status:Actual
Project ID:F 2022(093)CSJ:0497-01-021
Description:SEAL COATHandling
Code:
 
Limits From:FM 1862Fund Cat:1
Limits To:SH 35ESTIMATE:$107,153
Length:2.7Actual$109,278
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 530Let Status:Actual
Project ID:F 2022(093)CSJ:0515-04-035
Description:SEAL COATHandling
Code:
 
Limits From:FM 2437Fund Cat:1
Limits To:JACKSON C/LESTIMATE:$261,706
Length:6.1Actual$263,450
 
District:YOAKUMLet Date:Nov 2021
Highway:IH 10Let Status:Actual
Project ID:F 2022(094)CSJ:0535-06-047
Description:SEAL COATHandling
Code:
 
Limits From:GONZALES C/LFund Cat:1
Limits To:0.25 MI W OF FM 2238 (FR RD)ESTIMATE:$404,839
Length:5.2Actual$410,646
 
District:YOAKUMLet Date:Nov 2021
Highway:IH 10Let Status:Actual
Project ID:F 2022(094)CSJ:0535-07-052
Description:SEAL COATHandling
Code:
 
Limits From:0.25 MI W OF FM 2238Fund Cat:1
Limits To:COLORADO C/LESTIMATE:$304,577
Length:5.7Actual$308,501
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 102Let Status:Actual
Project ID:F 2022(093)CSJ:0709-01-026
Description:SEAL COATHandling
Code:
 
Limits From:SENIOR BRIDGE RDFund Cat:1
Limits To:WHARTON C/LESTIMATE:$228,405
Length:5.1Actual$231,942
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 443Let Status:Actual
Project ID:F 2022(093)CSJ:0839-01-018
Description:SEAL COATHandling
Code:
 
Limits From:US 90AFund Cat:1
Limits To:DE WITT C/LESTIMATE:$389,633
Length:8.9Actual$392,289
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 444Let Status:Actual
Project ID:F 2022(093)CSJ:0840-01-016
Description:SEAL COATHandling
Code:
 
Limits From:US 59Fund Cat:1
Limits To:6.16 M E OF FM 1686ESTIMATE:$241,720
Length:6.1Actual$243,217
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 444Let Status:Actual
Project ID:F 2022(093)CSJ:0840-05-022
Description:SEAL COATHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:US 59ESTIMATE:$692,933
Length:17.6Actual$697,207
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 950Let Status:Actual
Project ID:F 2022(093)CSJ:0897-02-023
Description:SEAL COATHandling
Code:
 
Limits From:SH 71Fund Cat:1
Limits To:FM 102ESTIMATE:$292,163
Length:6.3Actual$296,048
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 530Let Status:Actual
Project ID:F 2022(093)CSJ:1090-01-026
Description:SEAL COATHandling
Code:
 
Limits From:LAVACA C/LFund Cat:1
Limits To:BAGBY RD (CR 274)ESTIMATE:$438,000
Length:10.9Actual$440,602
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 949Let Status:Actual
Project ID:C 1106-2-22CSJ:1106-02-022
Description:SEAL COATHandling
Code:
 
Limits From:COLORADO C/LFund Cat:1
Limits To:SH 36ESTIMATE:$485,984
Length:11.6Actual$489,261
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 794Let Status:Actual
Project ID:F 2022(093)CSJ:1133-02-033
Description:SEAL COATHandling
Code:
 
Limits From:US 90Fund Cat:1
Limits To:CR 235ESTIMATE:$184,961
Length:4.2Actual$186,226
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1163Let Status:Actual
Project ID:C 1260-2-17CSJ:1260-02-017
Description:SEAL COATHandling
Code:
 
Limits From:SH 71Fund Cat:1
Limits To:FM 441ESTIMATE:$333,329
Length:8.6Actual$336,165
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 953Let Status:Actual
Project ID:C 1263-1-13CSJ:1263-01-013
Description:SEAL COATHandling
Code:
 
Limits From:US 87Fund Cat:1
Limits To:FM 766ESTIMATE:$264,382
Length:6.6Actual$266,102
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1162Let Status:Actual
Project ID:F 2022(093)CSJ:1304-01-020
Description:SEAL COATHandling
Code:
 
Limits From:FM 653Fund Cat:1
Limits To:MATAGORDA C/LESTIMATE:$695,328
Length:16.2Actual$699,905
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1680Let Status:Actual
Project ID:F 2022(093)CSJ:1442-03-020
Description:SEAL COATHandling
Code:
 
Limits From:US 90Fund Cat:1
Limits To:LAVACA C/LESTIMATE:$410,433
Length:9.5Actual$413,214
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1680Let Status:Actual
Project ID:F 2022(093)CSJ:1442-04-011
Description:SEAL COATHandling
Code:
 
Limits From:GONZALES C/LFund Cat:1
Limits To:FM 532ESTIMATE:$122,461
Length:2.9Actual$123,271
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 1679Let Status:Actual
Project ID:C 1688-1-11CSJ:1688-01-011
Description:SEAL COATHandling
Code:
 
Limits From:.19 MI W OF FM 2433Fund Cat:1
Limits To:SH 35ESTIMATE:$155,992
Length:4.5Actual$158,514
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2175Let Status:Actual
Project ID:C 1985-2-5CSJ:1985-02-005
Description:SEAL COATHandling
Code:
 
Limits From:END OF STATE MAINTENANCEFund Cat:1
Limits To:FM 1468ESTIMATE:$82,859
Length:2.1Actual$83,407
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 3283Let Status:Actual
Project ID:C 2063-4-4CSJ:2063-04-004
Description:SEAL COATHandling
Code:
 
Limits From:US 90AFund Cat:1
Limits To:END STATE MAINTENANCEESTIMATE:$125,795
Length:4.0Actual$126,374
 
District:YOAKUMLet Date:Nov 2021
Highway:US 77Let Status:Actual
Project ID:F 2022(094)CSJ:2350-01-067
Description:SEAL COATHandling
Code:
 
Limits From:N OF COLETOVILLE RD EFund Cat:1
Limits To:US 59TESTIMATE:$137,641
Length:1.0Actual$140,549
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 444Let Status:Actual
Project ID:F 2022(093)CSJ:2516-01-011
Description:SEAL COATHandling
Code:
 
Limits From:6.16 MI E OF FM 1686Fund Cat:1
Limits To:FM 1686ESTIMATE:$235,037
Length:6.0Actual$236,460
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2546Let Status:Actual
Project ID:C 2517-1-38CSJ:2517-01-038
Description:SEAL COATHandling
Code:
 
Limits From:END OF MAINTENANCEFund Cat:1
Limits To:SH 71ESTIMATE:$279,420
Length:7.5Actual$283,559
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2540Let Status:Actual
Project ID:C 2525-2-7CSJ:2525-02-007
Description:SEAL COATHandling
Code:
 
Limits From:FM 457Fund Cat:1
Limits To:FM 521ESTIMATE:$289,082
Length:7.4Actual$290,934
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2614Let Status:Actual
Project ID:F 2022(093)CSJ:2599-01-009
Description:SEAL COATHandling
Code:
 
Limits From:FM 950Fund Cat:1
Limits To:WHARTON C/LESTIMATE:$103,328
Length:2.7Actual$103,966
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2760Let Status:Actual
Project ID:C 2714-2-5CSJ:2714-02-005
Description:SEAL COATHandling
Code:
 
Limits From:FM 2717Fund Cat:1
Limits To:INTERSECTION AT FM 2760ESTIMATE:$56,186
Length:1.9Actual$56,717
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2760Let Status:Actual
Project ID:C 2714-3-5CSJ:2714-03-005
Description:SEAL COATHandling
Code:
 
Limits From:SH 316Fund Cat:1
Limits To:END OF MAINTENANCEESTIMATE:$56,579
Length:1.0Actual$56,877
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2718Let Status:Actual
Project ID:C 2716-1-8CSJ:2716-01-008
Description:SEAL COATHandling
Code:
 
Limits From:US 183Fund Cat:1
Limits To:FM 237ESTIMATE:$292,483
Length:8.4Actual$293,908
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2814Let Status:Actual
Project ID:C 2828-1-6CSJ:2828-01-006
Description:SEAL COATHandling
Code:
 
Limits From:SH 97Fund Cat:1
Limits To:END OF STATE MAINTENANCEESTIMATE:$242,080
Length:5.6Actual$243,722
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 2541Let Status:Actual
Project ID:C 2914-1-5CSJ:2914-01-005
Description:SEAL COATHandling
Code:
 
Limits From:SH 35Fund Cat:1
Limits To:SH 238ESTIMATE:$159,973
Length:4.6Actual$162,492
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 3011Let Status:Actual
Project ID:C 3109-3-4CSJ:3109-03-004
Description:SEAL COATHandling
Code:
 
Limits From:END OF STATE MAINTENANCEFund Cat:1
Limits To:FM 2145ESTIMATE:$123,162
Length:3.2Actual$123,780
 
District:YOAKUMLet Date:Nov 2021
Highway:FM 3013Let Status:Actual
Project ID:F 2022(092)CSJ:3205-01-013
Description:SEAL COATHandling
Code:
 
Limits From:SH 36Fund Cat:1
Limits To:COLORADO C/LESTIMATE:$308,364
Length:8.4Actual$320,208
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0026-06-035
Length:314.7
Estimate:$16,412,400
Actual:$16,624,783

CCSJ: 0446-04-014

District:YOAKUMLet Date:Mar 2022
Highway:FM 1093Let Status:Actual
Project ID:F 2022(359)CSJ:0446-04-014
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:FM 3013 IN EAGLE LAKEFund Cat:1
Limits To:WHARTON COUNTY LINEESTIMATE:$5,918,232
Length:7.0Actual$5,576,114
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0446-04-014
Length:7
Estimate:$5,918,232
Actual:$5,576,114

CCSJ: 0535-08-089

District:YOAKUMLet Date:Dec 2021
Highway:IH 10Let Status:Actual
Project ID:F 2022(187)CSJ:0535-08-089
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:0.11 MI WEST OF HATTERMANN LANE (CR 219)Fund Cat:1
Limits To:0.09 MI EAST OF FM 2434ESTIMATE:$4,432,188
Length:3.6Actual$4,831,460
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0535-08-089
Length:3.6
Estimate:$4,432,188
Actual:$4,831,460

CCSJ: 0716-02-045

District:YOAKUMLet Date:Feb 2022
Highway:FM 109Let Status:Actual
Project ID:BR 2022(323)CSJ:0716-02-045
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT CUMMINS CR. & CUMMINS CR. RELIEFFund Cat:6
Limits To:STR # 0716-02-015 & 016ESTIMATE:$6,400,528
Length:0.0Actual$6,985,517
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0716-02-045
Length:0
Estimate:$6,400,528
Actual:$6,985,517

CCSJ: 0913-26-065

District:YOAKUMLet Date:Oct 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(658)TAPSCSJ:0913-26-065
Description:CONSTRUCT PEDESTRIAN INFRASTRUCTUREHandling
Code:
 
Limits From:RAMPART ST (IN COLUMBUS)Fund Cat:3
Limits To:PRAIRIE STREETESTIMATE:$311,972
Length:0.3Actual$411,526
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0913-26-065
Length:0.3
Estimate:$311,972
Actual:$411,526

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract