Letting Schedule for Ft Worth District (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Ft Worth District (FY 2022) |
Erath | Jack | Johnson | Palo Pinto | Parker | Tarrant | Wise | | |||||||
Erath County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0080-02-061 | US 377 | Actual | May 2022 | $399,231 | 6 | REHABILITATE BRIDGE | 0.0 |
0079-05-061 | US 67 | Actual | Dec 2021 | $11,795,878 | 1 | SEAL COAT | 0.0 |
0774-01-019 | FM 219 | Actual | Apr 2022 | $9,105,558 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
Jack County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0249-05-031 | US 281 | Actual | Apr 2022 | $24,258,988 | 11 | CONSTRUCT NEW ROADWAY LANES | 0.0 |
0902-40-021 | CR | Actual | Apr 2022 | $802,366 | 6 | BRIDGE REPLACEMENT | 4.5 |
0134-05-034 | SH 59 | Actual | Jan 2022 | $3,295,666 | 1 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
Johnson County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0260-01-058 | US 67 | Actual | Feb 2022 | $7,535,333 | 1 | RESURFACE ROADWAY | 0.0 |
0712-01-041 | FM 4 | Actual | Sep 2021 | $2,160,707 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0014-03-101 | IH 35W | Actual | Nov 2021 | $1,216,227 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0014-03-087 | IH 35W | Approved | Aug 2022 | $10,507,755 | 6 | RECONSTRUCT EXISTING ROADWAY | 0.0 |
1181-02-040 | FM 917 | Approved | Aug 2022 | $2,321,531 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
1181-03-040 | FM 917 | Approved | Aug 2022 | $4,096,825 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
Palo Pinto County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0008-01-046 | US 180 | Actual | Feb 2022 | $4,960,204 | 11 | RESURFACE ROADWAY | 0.0 |
Parker County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
2737-01-020 | FM 2257 | Approved | Aug 2022 | $165,821 | 1 | INSTALL ILLUMINATION | 0.0 |
0008-02-077 | US 180 | Approved | Aug 2022 | $135,318 | 1 | INSTALL FLASHING BEACON | 0.0 |
3516-01-019 | FM 3325 | Actual | Jan 2022 | $914,691 | 11 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
1468-01-026 | FM 1189 | Actual | Feb 2022 | $450,469 | 1 | CONSTRUCT NEW ROADWAY LANES | 0.0 |
0008-03-134 | US 180 | Approved | Aug 2022 | $579,601 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0314-07-080 | IH 20 | Approved | Aug 2022 | $395,689 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0902-38-138 | VA | Approved | Aug 2022 | $2,664,031 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0314-07-076 | IH 20 | Actual | Dec 2021 | $6,980,425 | 1 | RESURFACE ROADWAY | 3.0 |
0314-07-075 | IH 20 | Actual | Dec 2021 | $7,785,696 | 1 | PREVENTIVE MAINTENANCE | 4.5 |
Tarrant County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0902-00-301 | VA | Actual | Mar 2022 | $1 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0008-13-125 | IH 820 | Actual | Feb 2022 | $1,591,245,174 | 12 | RECONSTRUCT EXISTING ROADWAY | 0.0 |
0014-15-080 | US 81 | Actual | Mar 2022 | $599,442 | 1 | EMBANKMENT STABILIZATION | 0.0 |
0902-90-147 | VA | Actual | Jan 2022 | $1,632,388 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
0902-90-084 | VA | Actual | Dec 2021 | $1,377,142 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0902-90-083 | VA | Actual | Dec 2021 | $1,438,206 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0902-90-119 | CS | Approved | Aug 2022 | $1,309,032 | 3 | INSTALL TRAFFIC SIGNAL | 0.0 |
0902-90-082 | VA | Actual | Jan 2022 | $2,189,054 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0902-00-234 | VA | Actual | Jan 2022 | $875,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0008-14-119 | IH 820 | Actual | Jan 2022 | $10,737,736 | 1 | RESURFACE ROADWAY | 2.5 |
0172-01-054 | BU 287P | Actual | Apr 2022 | $881,110 | 1 | INSTALL TRAFFIC SIGNAL | 4.0 |
0081-02-076 | US 377 | Approved | Aug 2022 | $400,000 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0014-16-283 | IH 35W | Approved | Aug 2022 | $9,938,744 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0094-02-143 | SH 183 | Approved | Aug 2022 | $294,823 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0902-00-321 | VA | Tentative | Aug 2022 | $29,000,000 | 3 | BRIDGE REPLACEMENT | 0.0 |
0747-04-078 | FM 157 | Approved | Aug 2022 | $270,435 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0013-10-089 | BU 287P | Approved | Aug 2022 | $356,669 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0008-15-059 | IH 820 | Actual | May 2022 | $413,725 | 1 | LANDSCAPE DEVELOPMENT | 0.0 |
0902-90-057 | CS | Actual | Apr 2022 | $1,434,417 | 6 | BRIDGE REPLACEMENT | 6.0 |
0902-00-250 | VA | Actual | May 2022 | $0 | 3 | MAINTENANCE & OPERATIONS PROJECT | 0.0 |
0008-14-134 | IH 820 | Tentative | Aug 2022 | $1,985,605 | 3 | CONSTRUCT RAMPS | 0.0 |
0902-00-314 | VA | Actual | May 2022 | $3,727,666 | 1 | INSTALL/REPLACE SIGNS | 0.0 |
0902-90-146 | VA | Actual | Nov 2021 | $1,078,180 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0902-90-117 | CS | Actual | Nov 2021 | $6,003,910 | 3 | RECONSTRUCT EXISTING ROADWAY | 8.0 |
0902-00-269 | VA | Actual | Sep 2021 | $520,000 | 7 | MAINTENANCE & OPERATIONS PROJECT | 0.0 |
1330-02-050 | FM 1187 | Actual | Sep 2021 | $835,253 | 1 | RESURFACE ROADWAY | 0.0 |
0902-00-300 | VA | Actual | Sep 2021 | $10,200,000 | 3 | MAINTENANCE & OPERATIONS PROJECT | 0.0 |
0902-00-260 | VA | Actual | Sep 2021 | $975,000 | 3 | MAINTENANCE & OPERATIONS PROJECT | 0.0 |
0902-00-256 | VA | Actual | Sep 2021 | $1,300,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
Wise County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0902-20-102 | CR | Approved | Aug 2022 | $679,389 | 6 | BRIDGE REPLACEMENT | 0.0 |
0353-01-027 | SH 114 | Approved | Aug 2022 | $894,818 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0902-20-110 | CR | Actual | Sep 2021 | $689,206 | 6 | BRIDGE REPLACEMENT | 6.0 |
0352-01-063 | SH 114 | Actual | Dec 2021 | $5,727 | 3 | INSTALL/REPLACE SIGNS | 0.0 |
|