Letting Schedule for January, 2022 County (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
January, 2022 (FY 2022) | (see Links) |
SEP 2021 | OCT 2021 | NOV 2021 | DEC 2021 | JAN 2022 | FEB 2022 | MAR 2022 | APR 2022 | MAY 2022 | AUG 2022 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0228-04-043 | Andrews/ Odessa | US 385 | Actual | $40,055,499 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0249-03-054 | Archer/ Wichita Falls | US 281 | Actual | $2,286,669 | 1 | SURFACING/ROADWAY RESTORATION | 3.5 |
0573-01-034 | Bastrop/ Austin | SH 304 | Actual | $8,588,390 | 1 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
0530-01-008 | Bastrop/ Austin | PR 1C | Actual | $467,070 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
2879-02-014 | Bowie/ Atlanta | FM 2240 | Actual | $636,712 | 1 | RESURFACE ROADWAY | 0.0 |
0049-09-090 | Brazos/ Bryan | US 190 | Actual | $1,834,314 | 8 | INSTALL RAISED MEDIAN | 0.0 |
0079-01-038 | Brown/ Brownwood | US 67 | Actual | $2,775,459 | 1 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0919-00-081 | Cass/ Atlanta | VA | Actual | $1,146,416 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0378-06-022 | Cherokee/ Tyler | SH 135 | Actual | $4,189,281 | 1 | BRIDGE REPLACEMENT | 3.5 |
0925-00-078 | Childress/ Childress | VA | Actual | $1,062,125 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0224-01-061 | Clay/ Wichita Falls | US 287 | Actual | $2,052,620 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0099-01-035 | Coleman/ Brownwood | US 283 | Actual | $2,950,130 | 1 | HIGHWAY IMPROVEMENT | 4.5 |
0918-24-263 | Collin/ Dallas | VA | Actual | $3,639,740 | 9 | TRANSPORTATION NON-ROADWAY | 0.0 |
0047-06-164 | Collin/ Dallas | US 75 | Actual | $3,327,650 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
0923-17-088 | Comanche/ Brownwood | CR | Actual | $1,822,621 | 6 | BRIDGE REPLACEMENT | 6.5 |
1356-01-029 | Cooke/ Wichita Falls | FM 1201 | Actual | $4,621,303 | 1 | SURFACING/ROADWAY RESTORATION | 8.0 |
0903-15-105 | Cooke/ Wichita Falls | CR | Actual | $1,592,070 | 6 | BRIDGE REPLACEMENT | 6.5 |
0238-04-038 | Dallam/ Amarillo | US 54 | Actual | $8,541,035 | 1 | HIGHWAY IMPROVEMENT | 3.0 |
0918-00-327 | Dallas/ Dallas | VA | Actual | $336,701 | 1 | REHAB OF DYNAMIC MESSAGE SIGN | 0.0 |
0918-48-004 | Dallas/ Dallas | VA | Actual | $10,501,990 | 1 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0195-03-101 | Denton/ Dallas | IH 35E | Actual | $7,176,948 | 8 | RESURFACE ROADWAY | 0.0 |
0195-03-096 | Denton/ Dallas | IH 35E | Actual | $2,624,043 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0913-00-120 | Dewitt/ Yoakum | VA | Actual | $663,720 | 1 | BRIDGE MAINTENANCE | 0.0 |
0127-01-037 | Eastland/ Brownwood | US 183 | Actual | $2,966,327 | 1 | RESURFACE ROADWAY | 2.5 |
0257-03-033 | Eastland/ Brownwood | SH 6 | Actual | $10,872,478 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0228-06-092 | Ector/ Odessa | US 385 | Actual | $7,403,043 | 1 | HIGHWAY IMPROVEMENT | 5.0 |
0906-00-204 | Ector/ Odessa | VA | Actual | $579,552 | 1 | BRIDGE MAINTENANCE | 0.0 |
0172-05-125 | Ellis/ Dallas | US 287 | Actual | $3,321,948 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0048-04-094 | Ellis/ Dallas | IH 35E | Actual | $41,579,487 | 1 | INTERCHANGE IMPROVEMENT | 0.0 |
0913-28-073 | Fayette/ Yoakum | CR | Actual | $1,425,164 | 6 | BRIDGE REPLACEMENT | 5.0 |
0267-01-033 | Fayette/ Yoakum | SH 237 | Actual | $908,268 | 6 | BRIDGE MAINTENANCE | 0.0 |
0228-02-049 | Gaines/ Lubbock | US 62 | Actual | $17,753,129 | 1 | REHABILITATE EXISTING ROADWAY | 7.0 |
0916-26-022 | Goliad/ Corpus Christi | CR | Actual | $397,364 | 6 | BRIDGE REPLACEMENT | 0.0 |
0516-02-031 | Goliad/ Corpus Christi | SH 239 | Actual | $10,169,973 | 1 | REHABILITATE EXISTING ROADWAY | 4.5 |
0901-19-195 | Grayson/ Paris | VA | Actual | $1,494,500 | 11 | PREVENTIVE MAINTENANCE | 0.0 |
2158-01-026 | Gregg/ Tyler | FM 2275 | Actual | $349,000 | 3 | INSTALL TRAFFIC SIGNAL | 0.0 |
0867-01-017 | Hamilton/ Waco | FM 932 | Actual | $13,725,256 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0043-02-077 | Hardeman/ Childress | US 287 | Actual | $2,606,752 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0271-14-239 | Harris/ Houston | IH 610 | Actual | $614,380 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0720-06-002 | Harris/ Houston | SH 249 | Actual | $388,176 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0912-00-559 | Harris/ Houston | VA | Actual | $8,000,000 | 3 | REGIONAL TRAVEL MANAGEMENT PROGRAM | 0.0 |
0912-00-586 | Harris/ Houston | VA | Actual | $1,000,000 | 1 | UPGRADE DYNAMIC MESSAGE SIGN BOARDS | 0.0 |
0919-03-061 | Harrison/ Atlanta | CR | Actual | $714,704 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0157-04-057 | Haskell/ Abilene | US 277 | Actual | $5,647,939 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0914-33-077 | Hays/ Austin | VA | Actual | $194,209 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0914-33-067 | Hays/ Austin | VA | Actual | $346,131 | 10 | STATE PARK IMPROVEMENTS | 0.0 |
1197-01-021 | Hays/ Austin | RM 150 | Actual | $3,079,453 | 8 | HAZARD ELIMINATION & SAFETY | 7.5 |
0914-33-064 | Hays/ Austin | CR | Actual | $1,614,622 | 6 | BRIDGE REPLACEMENT | 6.5 |
0198-01-032 | Henderson/ Tyler | BU 175G | Actual | $595,851 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0596-01-023 | Hill/ Waco | FM 66 | Actual | $2,407,365 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0668-02-022 | Howard/ Abilene | FM 700 | Actual | $578,447 | 1 | INSTALL TRAFFIC SIGNAL | 0.0 |
0901-22-117 | Hunt/ Paris | CR | Actual | $1,377,957 | 6 | BRIDGE REPLACEMENT | 4.0 |
0379-01-046 | Hutchinson/ Amarillo | SH 136 | Actual | $9,350,961 | 1 | REHABILITATE EXISTING ROADWAY | 4.0 |
0134-05-034 | Jack/ Ft Worth | SH 59 | Actual | $3,295,666 | 1 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0515-01-071 | Jackson/ Yoakum | FM 616 | Actual | $3,826,644 | 1 | SURFACING/ROADWAY RESTORATION | 4.0 |
0200-11-107 | Jefferson/ Beaumont | US 69 | Actual | $3,667,056 | 6 | BRIDGE MAINTENANCE | 4.5 |
2355-01-006 | Kaufman/ Dallas | FM 2451 | Actual | $7,524,107 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0915-11-032 | Kendall/ San Antonio | VA | Actual | $617,257 | 10 | STATE PARK IMPROVEMENTS | 0.0 |
0133-01-049 | King/ Childress | US 82 | Actual | $6,063,882 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0018-01-094 | La Salle/ Laredo | IH 35 | Actual | $4,596,124 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0905-00-109 | Lubbock/ Lubbock | VA | Actual | $2,844,892 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0179-06-044 | Matagorda/ Yoakum | SH 35 | Actual | $5,940,881 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0258-08-037 | Mclennan/ Waco | SH 6 | Actual | $881,233 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
2060-01-037 | Mclennan/ Waco | FM 2113 | Actual | $15,388,383 | 1 | WIDEN ROAD - ADD SHOULDERS | 10.0 |
0848-04-049 | Medina/ San Antonio | FM 462 | Actual | $2,908,909 | 6 | BRIDGE REPLACEMENT | 4.0 |
2296-02-026 | Midland/ Odessa | SH 191 | Actual | $27,487,949 | 1 | CONSTRUCT BRIDGE | 0.0 |
0185-06-012 | Milam/ Bryan | FM 845 | Actual | $4,104,532 | 1 | SURFACING/ROADWAY RESTORATION | 7.0 |
0118-08-075 | Nacogdoches/ Lufkin | SH 21 | Actual | $2,248,501 | 6 | BRIDGE REPLACEMENT | 3.5 |
0030-01-035 | Ochiltree/ Amarillo | US 83 | Actual | $5,554,805 | 1 | HIGHWAY IMPROVEMENT | 2.0 |
3516-01-019 | Parker/ Ft Worth | FM 3325 | Actual | $914,691 | 11 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0904-00-198 | Potter/ Amarillo | VA | Actual | $842,609 | 11 | HIGHWAY IMPROVEMENT | 0.0 |
0177-02-095 | San Jacinto/ Lufkin | US 59 | Actual | $1,597,055 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0916-28-077 | San Patricio/ Corpus Christi | CR | Actual | $654,387 | 6 | BRIDGE REPLACEMENT | 3.5 |
0296-01-038 | Scurry/ Abilene | US 180 | Actual | $7,954,819 | 1 | REHABILITATE EXISTING ROADWAY | 2.0 |
0910-16-147 | Smith/ Tyler | CS | Actual | $1,258,233 | 6 | BRIDGE REPLACEMENT | 3.0 |
0033-01-038 | Stonewall/ Abilene | US 83 | Actual | $14,213,349 | 1 | WIDEN ROAD - ADD LANES | 2.0 |
0032-07-029 | Stonewall/ Abilene | US 83 | Actual | $19,378,099 | 1 | WIDEN ROAD - ADD LANES | 2.0 |
0902-90-147 | Tarrant/ Ft Worth | VA | Actual | $1,632,388 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
0902-90-082 | Tarrant/ Ft Worth | VA | Actual | $2,189,054 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0902-00-234 | Tarrant/ Ft Worth | VA | Actual | $875,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0008-14-119 | Tarrant/ Ft Worth | IH 820 | Actual | $10,737,736 | 1 | RESURFACE ROADWAY | 2.5 |
0070-02-091 | Tom Green/ San Angelo | US 87 | Actual | $10,297,869 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0907-00-198 | Tom Green/ San Angelo | VA | Actual | $3,243,010 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
1378-01-040 | Travis/ Austin | RM 1431 | Actual | $856,550 | 1 | INFRASTRUCTURE IMPROVEMENTS | 0.0 |
0700-03-145 | Travis/ Austin | SH 71 | Actual | $12,843,171 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0337-03-019 | Williamson/ Austin | FM 1331 | Actual | $181,446 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0015-09-203 | Williamson/ Austin | IH 35 | Actual | $273,796 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
3417-02-024 | Williamson/ Austin | FM 734 | Actual | $1,575,284 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
|