Letting Schedule for August, 2022 County (FY 2022)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
August, 2022 (FY 2022) | (see Links) |
SEP 2021 | OCT 2021 | NOV 2021 | DEC 2021 | JAN 2022 | FEB 2022 | MAR 2022 | APR 2022 | MAY 2022 | AUG 2022 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0520-09-054 | Anderson/ Tyler | SL 256 | Approved | $42,940 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0354-06-030 | Andrews/ Odessa | SH 115 | Approved | $25,469,835 | 1 | CONSTRUCT BRIDGE | 0.0 |
0911-00-124 | Angelina/ Lufkin | VA | Approved | $886,598 | 8 | INTERSECTION IMPROVEMENT | 0.0 |
0176-02-125 | Angelina/ Lufkin | BU 59-G | Approved | $1,116,133 | 8 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0114-17-010 | Bastrop/ Austin | SL 109 | Approved | $671,429 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
1186-02-025 | Bastrop/ Austin | FM 969 | Approved | $2,292,119 | 8 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
0101-02-039 | Bee/ Corpus Christi | US 181 | Approved | $11,662,579 | 1 | RESURFACE ROADWAY | 0.0 |
0836-02-078 | Bell/ Waco | SH 195 | Approved | $536,740 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
2057-01-012 | Bell/ Waco | FS 439 | Approved | $705,337 | 9 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0015-14-131 | Bell/ Waco | IH 35 | Approved | $3,000,000 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
0320-01-078 | Bell/ Waco | SS 290 | Approved | $384,701 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0231-16-035 | Bell/ Waco | FM 436 | Approved | $1,891,533 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0915-00-214 | Bexar/ San Antonio | VA | Tentative | $6,231,500 | 1 | HERO PROGRAM | 0.0 |
0073-08-203 | Bexar/ San Antonio | US 281 | Approved | $979,127 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0915-12-574 | Bexar/ San Antonio | VA | Approved | $2,014,138 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0915-12-684 | Bexar/ San Antonio | VA | Tentative | $129,225 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
1155-04-013 | Borden/ Abilene | FM 1785 | Approved | $3,266,877 | 8 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
0188-06-046 | Brazoria/ Houston | SH 36 | Approved | $42,018,666 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0598-02-125 | Brazoria/ Houston | SH 288 | Approved | $52,645,072 | 1 | WIDEN BRIDGE | 0.0 |
0188-04-035 | Brazoria/ Houston | SH 36 | Approved | $90,425,009 | 1 | WIDEN ROAD - ADD LANES | 8.0 |
0598-02-111 | Brazoria/ Houston | SH 288 | Approved | $39,154,628 | 7 | CONSTRUCT BRIDGE | 0.0 |
0598-02-116 | Brazoria/ Houston | SH 288 | Approved | $37,990,079 | 1 | CONSTRUCT BRIDGE | 0.0 |
0049-09-089 | Brazos/ Bryan | US 190 | Approved | $4,374,161 | 8 | WIDEN ROAD - ADD LANES | 0.0 |
0049-09-076 | Brazos/ Bryan | BS 6-R | Approved | $4,347,245 | 1 | INSTALL RAISED MEDIAN | 0.0 |
3093-01-002 | Cameron/ Pharr | FM 3069 | Approved | $4,967,569 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-06-312 | Cameron/ Pharr | CS | Approved | $574,485 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0704-02-022 | Childress/ Childress | FM 268 | Approved | $14,085,422 | 1 | WIDEN ROAD - ADD SHOULDERS | 5.0 |
0918-24-265 | Collin/ Dallas | CS | Approved | $30,000,000 | 3 | CONSTRUCT NEW ROAD | 0.0 |
0918-24-270 | Collin/ Dallas | VA | Tentative | $800,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0047-05-059 | Collin/ Dallas | SH 5 | Tentative | $2,000,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0140-13-025 | Crockett/ San Angelo | IH 10 | Approved | $1,421,600 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0918-00-324 | Dallas/ Dallas | VA | Tentative | $250,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-311 | Dallas/ Dallas | VA | Tentative | $1,524,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-314 | Dallas/ Dallas | VA | Tentative | $1,695,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0008-08-077 | Dallas/ Dallas | SH 180 | Approved | $500,000 | 3 | INSTALL/REHABILITATE ITS | 0.0 |
0918-47-382 | Dallas/ Dallas | VA | Tentative | $150,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-47-373 | Dallas/ Dallas | VA | Tentative | $300,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
1068-04-176 | Dallas/ Dallas | IH 30 | Approved | $500,600 | 3 | INSTALL/REHABILITATE ITS | 0.0 |
0918-47-385 | Dallas/ Dallas | VA | Tentative | $4,000,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-47-361 | Dallas/ Dallas | CS | Tentative | $400,000 | 5 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-47-277 | Dallas/ Dallas | VA | Tentative | $13,500,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-47-204 | Dallas/ Dallas | VA | Approved | $859,100 | 3 | INSTALL/UPGRADE ROADWAY LIGHTING | 0.0 |
0918-00-350 | Dallas/ Dallas | VA | Tentative | $2,701,961 | 9 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0918-00-348 | Dallas/ Dallas | VA | Tentative | $312,000 | 5 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-364 | Dallas/ Dallas | VA | Tentative | $1,000,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-369 | Dallas/ Dallas | VA | Tentative | $120,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-366 | Dallas/ Dallas | VA | Tentative | $10,000,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-337 | Dallas/ Dallas | VA | Tentative | $19,435,515 | 9 | FEDERAL TRANSIT ADMINISTRATION TRANSFER | 0.0 |
0918-00-318 | Dallas/ Dallas | VA | Tentative | $2,594,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-372 | Dallas/ Dallas | VA | Tentative | $120,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-374 | Dallas/ Dallas | VA | Tentative | $200,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-373 | Dallas/ Dallas | VA | Tentative | $2,500,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-375 | Dallas/ Dallas | VA | Tentative | $6,200,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-370 | Dallas/ Dallas | VA | Tentative | $1,000,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-371 | Dallas/ Dallas | VA | Tentative | $600,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-376 | Dallas/ Dallas | VA | Tentative | $5,000,000 | 7 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-46-330 | Denton/ Dallas | VA | Approved | $994,511 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0918-46-303 | Denton/ Dallas | CS | Tentative | $300,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0918-46-313 | Denton/ Dallas | VA | Tentative | $409,500 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0143-08-098 | Dewitt/ Yoakum | US 87 | Approved | $4,825,792 | 6 | BRIDGE MAINTENANCE | 0.0 |
0924-06-620 | El Paso/ El Paso | VA | Approved | $11,685,270 | 11 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0924-06-612 | El Paso/ El Paso | VA | Tentative | $1,000,000 | 3 | TRANSPORTATION SERVICE OPERATIONS | 0.0 |
0924-06-604 | El Paso/ El Paso | CS | Approved | $1,048,110 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0924-06-643 | El Paso/ El Paso | CS | Approved | $450,718 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
2552-03-070 | El Paso/ El Paso | SL 375 | Approved | $782,400 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0924-06-652 | El Paso/ El Paso | VA | Tentative | $2,461,146 | 1 | HIGHWAY OPERATIONS PROGRAM | 0.0 |
0674-01-071 | El Paso/ El Paso | FM 76 | Approved | $2,286,929 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0924-06-558 | El Paso/ El Paso | CS | Tentative | $250,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0167-01-126 | El Paso/ El Paso | US 54 | Approved | $1,563,337 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
1482-03-002 | Fannin/ Paris | FM 1550 | Tentative | $7,824,730 | 3 | CONSTRUCT NEW ROAD | 0.0 |
0913-28-070 | Fayette/ Yoakum | CR | Approved | $1,248,823 | 6 | BRIDGE REPLACEMENT | 0.0 |
3510-04-019 | Fort Bend/ Houston | SH 99 | Approved | $98,807,708 | 7 | WIDEN ROAD - ADD LANES | 0.0 |
0188-09-051 | Fort Bend/ Houston | FM 723 | Approved | $117,941,356 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0122-03-033 | Freestone/ Bryan | US 287 | Approved | $1,672,989 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0017-06-091 | Frio/ San Antonio | IH 35 | Approved | $1,608,895 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0051-09-126 | Galveston/ Houston | FM 3005 | Approved | $681,072 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0051-03-119 | Galveston/ Houston | SH 3 | Approved | $1,281,785 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0367-06-066 | Galveston/ Houston | SH 87 | Approved | $6,783,196 | 10 | FERRY OPERATION PROJECTS | 0.0 |
0912-73-223 | Galveston/ Houston | VA | Approved | $4,269,906 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0045-18-044 | Grayson/ Paris | US 82 | Approved | $1,195,069 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0081-07-027 | Grayson/ Paris | US 377 | Approved | $332,872 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0915-46-045 | Guadalupe/ San Antonio | CS | Approved | $6,316,658 | 3 | WIDEN ROAD - ADD LANES | 0.0 |
1650-01-010 | Hall/ Childress | FM 1619 | Approved | $1,306,328 | 6 | BRIDGE REPLACEMENT | 4.0 |
0271-17-176 | Harris/ Houston | IH 610 | Approved | $2,014,433 | 6 | BRIDGE REPLACEMENT | 0.0 |
0500-03-629 | Harris/ Houston | IH 45 | Approved | $2,059,656 | 6 | BRIDGE REPLACEMENT | 0.0 |
0912-00-534 | Harris/ Houston | VA | Tentative | $1,000,000 | 1 | REPLACE DYNAMIC MESSAGE SIGNS | 0.0 |
0912-00-595 | Harris/ Houston | VA | Tentative | $1,445,649 | 11 | TRANSPORTATION SYSTEM SENSORS | 0.0 |
0912-00-600 | Harris/ Houston | VA | Tentative | $3,917,545 | 3 | REGIONAL COMMUTE ALTERNATIVES PROGRAM | 0.0 |
0912-00-601 | Harris/ Houston | VA | Tentative | $2,400,000 | 3 | REGIONAL COMMUTE ALTERNATIVES PROGRAM | 0.0 |
0912-00-589 | Harris/ Houston | VA | Tentative | $4,160,000 | 1 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
0912-00-539 | Harris/ Houston | VA | Tentative | $8,000,000 | 7 | REGIONAL TRAVEL MANAGEMENT PROGRAM | 0.0 |
0912-00-548 | Harris/ Houston | VA | Tentative | $3,750,000 | 3 | REGIONAL COMMUTE ALTERNATIVES PROGRAM | 0.0 |
0912-00-568 | Harris/ Houston | VA | Tentative | $1,250,000 | 3 | REGIONAL COMMUTE ALTERNATIVES PROGRAM | 0.0 |
0050-06-089 | Harris/ Houston | US 290 | Approved | $3,295,431 | 1 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
0912-00-662 | Harris/ Houston | VA | Tentative | $1,500,000 | 7 | ENGINEERING DESIGN/STUDY | 0.0 |
0976-01-043 | Harris/ Houston | FM 865 | Approved | $6,489,076 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0912-72-397 | Harris/ Houston | VA | Approved | $1,134,185 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0912-72-650 | Harris/ Houston | VA | Approved | $5,522,872 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0976-01-045 | Harris/ Houston | FM 865 | Approved | $554,971 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0912-72-654 | Harris/ Houston | Approved | $2,349,375 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 | |
0106-07-030 | Haskell/ Abilene | SH 6 | Approved | $1,753,759 | 6 | BRIDGE MAINTENANCE | 0.0 |
0511-03-013 | Hays/ Austin | RM 32 | Approved | $947,264 | 8 | INTERSECTION IMPROVEMENT | 0.0 |
0987-03-014 | Hays/ Austin | FM 621 | Approved | $2,765,187 | 1 | WIDEN ROAD - ADD LANES AND SHOULDERS | 3.5 |
0285-03-062 | Hays/ Austin | RM 12 | Approved | $4,135,673 | 8 | WIDEN ROAD - ADD LANES | 0.0 |
0164-01-075 | Henderson/ Tyler | BS 31-H | Approved | $2,036,274 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
1586-01-089 | Hidalgo/ Pharr | FM 907 | Approved | $1,228,090 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0921-02-445 | Hidalgo/ Pharr | CR | Approved | $1,390,253 | 6 | BRIDGE REPLACEMENT | 0.0 |
0921-02-393 | Hidalgo/ Pharr | VA | Approved | $1,085,788 | 3 | HIKE AND/OR BIKE | 0.0 |
0621-01-109 | Hidalgo/ Pharr | SH 336 | Tentative | $250,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0909-37-071 | Hill/ Waco | VA | Approved | $434,815 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0121-02-062 | Hill/ Waco | SH 22 | Approved | $362,099 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0019-03-028 | Hill/ Waco | SH 171 | Approved | $6,082,873 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0130-04-035 | Hockley/ Lubbock | SH 114 | Approved | $1,865,723 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0400-03-015 | Hopkins/ Paris | SL 301 | Approved | $1,394,680 | 6 | BRIDGE REPLACEMENT | 0.0 |
0002-04-033 | Hudspeth/ El Paso | SH 20 | Approved | $3,497,073 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0901-22-123 | Hunt/ Paris | CS | Approved | $65,276 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0420-02-051 | Jackson/ Yoakum | SH 172 | Approved | $2,443,489 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0920-38-280 | Jefferson/ Beaumont | CS | Approved | $585,628 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0200-14-093 | Jefferson/ Beaumont | US 69 | Approved | $7,881,376 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0014-03-087 | Johnson/ Ft Worth | IH 35W | Approved | $10,507,755 | 6 | RECONSTRUCT EXISTING ROADWAY | 0.0 |
1181-02-040 | Johnson/ Ft Worth | FM 917 | Approved | $2,321,531 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
1181-03-040 | Johnson/ Ft Worth | FM 917 | Approved | $4,096,825 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0095-05-063 | Kaufman/ Dallas | US 80 | Approved | $1,597,067 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0136-07-052 | Lamar/ Paris | US 271 | Approved | $1,255,719 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0272-05-033 | Lampasas/ Brownwood | US 190 | Approved | $2,830,494 | 8 | PREVENTIVE MAINTENANCE | 0.0 |
0269-02-068 | Lavaca/ Yoakum | US 77 | Approved | $2,098,279 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0446-01-053 | Lavaca/ Yoakum | UA 90 | Approved | $1,349,956 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0028-03-109 | Liberty/ Beaumont | US 90 | Approved | $1,925,169 | 11 | HAZARD ELIMINATION & SAFETY | 0.0 |
0093-05-053 | Limestone/ Waco | SH 14 | Approved | $135,795 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0905-00-112 | Lubbock/ Lubbock | VA | Approved | $2,376,264 | 11 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0015-01-252 | Mclennan/ Waco | IH 35 | Approved | $791,881 | 8 | RESURFACE ROADWAY | 0.0 |
0909-00-051 | Mclennan/ Waco | VA | Approved | $480,706 | 8 | INTERSECTION IMPROVEMENT | 0.0 |
0005-02-113 | Midland/ Odessa | BI 20-E | Tentative | $1,800,000 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0005-03-073 | Midland/ Odessa | BI 20-E | Tentative | $500,000 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0906-32-059 | Midland/ Odessa | CS | Approved | $206,088 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0005-03-070 | Midland/ Odessa | BI 20-E | Tentative | $800,000 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0005-03-071 | Midland/ Odessa | BI 20-E | Tentative | $500,000 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0005-03-072 | Midland/ Odessa | BI 20-E | Tentative | $800,000 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
1400-04-040 | Montgomery/ Houston | FM 1774 | Approved | $2,672,523 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0338-04-060 | Montgomery/ Houston | SH 105 | Approved | $38,272,653 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
2744-01-032 | Montgomery/ Houston | FM 2854 | Approved | $14,281,140 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0338-04-065 | Montgomery/ Houston | SH 105 | Approved | $75,862,145 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0092-06-109 | Navarro/ Dallas | IH 45 | Approved | $133,751 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
0006-02-114 | Nolan/ Abilene | IH 20 | Approved | $74,427,332 | 4 | INTERCHANGE IMPROVEMENT (NEW OR UPDATE) | 0.0 |
0916-35-233 | Nueces/ Corpus Christi | CR | Approved | $125,823 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0916-35-243 | Nueces/ Corpus Christi | CS | Approved | $106,988 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0989-02-054 | Nueces/ Corpus Christi | FM 624 | Approved | $12,301,153 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0916-00-224 | Nueces/ Corpus Christi | VA | Approved | $2,722,811 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0028-14-116 | Orange/ Beaumont | IH 10 | Approved | $6,695,116 | 3 | BRIDGE MAINTENANCE | 0.0 |
2737-01-020 | Parker/ Ft Worth | FM 2257 | Approved | $165,821 | 1 | INSTALL ILLUMINATION | 0.0 |
0008-02-077 | Parker/ Ft Worth | US 180 | Approved | $135,318 | 1 | INSTALL FLASHING BEACON | 0.0 |
0008-03-134 | Parker/ Ft Worth | US 180 | Approved | $579,601 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0314-07-080 | Parker/ Ft Worth | IH 20 | Approved | $395,689 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0902-38-138 | Parker/ Ft Worth | VA | Approved | $2,664,031 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0904-00-212 | Potter/ Amarillo | VA | Approved | $289,135 | 3 | INSTALL TRAFFIC SIGNAL | 0.0 |
0772-01-034 | Red River/ Paris | FM 410 | Approved | $1,226,551 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0049-08-074 | Robertson/ Bryan | US 190 | Approved | $4,453,249 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0180-10-081 | San Patricio/ Corpus Christi | SH 361 | Tentative | $30,000 | 1 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
2893-01-018 | Shelby/ Lufkin | FM 947 | Approved | $1,891,800 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0190-05-074 | Smith/ Tyler | US 69 | Approved | $1,278,488 | 8 | INTERSECTION IMPROVEMENT | 0.0 |
0910-00-134 | Smith/ Tyler | VA | Approved | $435,667 | 8 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0910-00-135 | Smith/ Tyler | VA | Approved | $653,255 | 8 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0910-16-165 | Smith/ Tyler | CS | Approved | $163,757 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
0910-00-133 | Smith/ Tyler | VA | Approved | $419,806 | 8 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0245-06-087 | Smith/ Tyler | SH 64 | Approved | $1,767,280 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0522-04-032 | Smith/ Tyler | FM 16 | Approved | $35,600,919 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0910-00-131 | Smith/ Tyler | VA | Approved | $2,270,791 | 10 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0106-04-036 | Stonewall/ Abilene | US 380 | Approved | $16,680,277 | 6 | BRIDGE REPLACEMENT | 0.0 |
0902-90-119 | Tarrant/ Ft Worth | CS | Approved | $1,309,032 | 3 | INSTALL TRAFFIC SIGNAL | 0.0 |
0081-02-076 | Tarrant/ Ft Worth | US 377 | Approved | $400,000 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0014-16-283 | Tarrant/ Ft Worth | IH 35W | Approved | $9,938,744 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0094-02-143 | Tarrant/ Ft Worth | SH 183 | Approved | $294,823 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0902-00-321 | Tarrant/ Ft Worth | VA | Tentative | $29,000,000 | 3 | BRIDGE REPLACEMENT | 0.0 |
0747-04-078 | Tarrant/ Ft Worth | FM 157 | Approved | $270,435 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0013-10-089 | Tarrant/ Ft Worth | BU 287P | Approved | $356,669 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0008-14-134 | Tarrant/ Ft Worth | IH 820 | Tentative | $1,985,605 | 3 | CONSTRUCT RAMPS | 0.0 |
0006-18-064 | Taylor/ Abilene | BI 20-R | Approved | $989,712 | 8 | INSTALL ILLUMINATION | 0.0 |
0908-33-105 | Taylor/ Abilene | CS | Approved | $82,262 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0907-24-054 | Tom Green/ San Angelo | VA | Approved | $945,881 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0914-04-318 | Travis/ Austin | CS | Approved | $21,364,000 | 3 | HIGHWAY IMPROVEMENT | 0.0 |
0914-04-313 | Travis/ Austin | VA | Approved | $6,600,000 | 3 | HIKE AND/OR BIKE | 0.0 |
0015-10-062 | Travis/ Austin | IH 35 | Approved | $525,645,438 | 1 | WIDEN ROAD - ADD LANES | 10.0 |
3136-01-193 | Travis/ Austin | SL 1 | Approved | $5,800,000 | 3 | CONSTRUCT RAMPS | 0.0 |
0931-04-034 | Trinity/ Lufkin | FS 357 | Approved | $1,317,723 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
1171-01-022 | Van Zandt/ Tyler | FM 859 | Approved | $3,198,530 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0913-27-089 | Victoria/ Yoakum | CS | Approved | $51,910 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0114-11-086 | Waller/ Houston | US 290 | Approved | $9,575,974 | 3 | CONSTRUCT FRONTAGE ROADS | 0.0 |
0543-01-067 | Waller/ Houston | FM 359 | Approved | $14,024,312 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0086-01-099 | Webb/ Laredo | SH 359 | Approved | $1,186,114 | 8 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0922-33-159 | Webb/ Laredo | CR | Approved | $3,720,253 | 6 | BRIDGE REPLACEMENT | 0.0 |
0832-02-029 | Wilbarger/ Wichita Falls | FM 925 | Approved | $983,955 | 6 | BRIDGE REPLACEMENT | 0.0 |
3486-01-008 | Williamson/ Austin | FM 3349 | Approved | $67,120,000 | 3 | WIDEN ROAD - ADD LANES AND SHOULDERS | 0.0 |
0337-01-049 | Williamson/ Austin | SH 29 | Approved | $279,673 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0914-05-198 | Williamson/ Austin | VA | Approved | $2,672,408 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0902-20-102 | Wise/ Ft Worth | CR | Approved | $679,389 | 6 | BRIDGE REPLACEMENT | 0.0 |
0353-01-027 | Wise/ Ft Worth | SH 114 | Approved | $894,818 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
|