The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Wichita Falls District (FY 2022)
Archer | Clay | Cooke | Montague | Wichita | Young |

Archer County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0156-05-063US 82TentativeMar 2022$6,000,00011RESURFACE ROADWAY0.0

Clay County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0903-06-022VATentativeJan 2022$1,604,11910SURFACING/ROADWAY RESTORATION0.0
0224-01-061US 287TentativeJan 2022$1,450,0001SURFACING/ROADWAY RESTORATION0.0
0391-04-030SH 148TentativeJul 2022$3,786,9131HAZARD ELIMINATION & SAFETY0.0

Cooke County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1356-01-029FM 1201TentativeDec 2021$3,570,0001SURFACING/ROADWAY RESTORATION0.0
0903-15-105CRTentativeJan 2022$1,285,0006BRIDGE REPLACEMENT0.0
0312-01-076FM 51TentativeApr 2022$3,750,0006BRIDGE REPLACEMENT0.0

Montague County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0013-13-005SH 101ApprovedNov 2021$7,485,6881SEAL COAT0.0

Wichita County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0802-02-070FM 369TentativeDec 2021$4,000,0001SURFACING/ROADWAY RESTORATION0.0
0249-11-012SL 473TentativeMar 2022$1,500,0001DRAINAGE IMPROVEMENTS0.0

Young County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0134-02-060US 380TentativeFeb 2022$3,055,17811RESURFACE ROADWAY0.0