Letting Schedule for San Angelo District (FY 2022)
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
San Angelo District (FY 2022) |
Coke | Crockett | Reagan | Runnels | Sutton | Tom Green | | |||||||
Coke County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
2467-01-012 | RM 2059 | Tentative | Dec 2021 | $463,686 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0907-14-010 | CR | Tentative | Jul 2022 | $523,900 | 6 | BRIDGE REPLACEMENT | 0.0 |
Crockett County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0140-10-034 | IH 10 | Tentative | May 2022 | $6,455,441 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
Reagan County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0494-10-017 | SH 137 | Tentative | Jun 2022 | $25,742,500 | 11 | HIGHWAY IMPROVEMENT | 0.0 |
Runnels County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0034-06-014 | FM 2887 | Tentative | May 2022 | $7,706,646 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
Sutton County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0141-03-062 | IH 10 | Tentative | Jan 2022 | $9,452,850 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
Tom Green County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0907-00-177 | VA | Tentative | May 2022 | $600,000 | 11 | HAZARD ELIMINATION & SAFETY | 0.0 |
0907-00-176 | VA | Tentative | May 2022 | $600,000 | 11 | HAZARD ELIMINATION & SAFETY | 0.0 |
0077-09-010 | BU 67-H | Tentative | May 2022 | $3,721,430 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0264-06-043 | US 277 | Tentative | Feb 2022 | $11,658,600 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0907-00-178 | VA | Tentative | Apr 2022 | $1,500,000 | 11 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0907-00-195 | VA | Tentative | Dec 2021 | $12,000,000 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0907-00-198 | VA | Tentative | Jan 2022 | $1,500,000 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
|