Monthly State Let Construction Report For Beaumont District As Of Nov 13, 2018 Page 2 Of 3

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJASPER
HighwaySH 62
From0.168 MILES SOUTH OF FM 253, SOUTH
To3.379 MILES NORTH OF NEWTON CO/L
CSJ0243-01-050
Proj IDSTP 1502(422)
Work TypeGR, BS, OV, STRIPE
 
9.0179416731.779656980.0199.9
CountyJASPER
HighwayFM 2246
From0.118 MILES WEST OF SH 62, EAST
ToSH 62
CSJ2120-01-027
Proj IDSTP 1502(666)
Work TypeGR, BS, OV, STRIPE
 
0.118139544.34214775.9499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began08-30-16
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted76
Working Days Charged329
Percent Time Used119
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0243-01-050
AMERICAN REMEDIATION OPTIONS, INC. (0.76)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95)
WEST TEXAS RUMBLE STRIP (0.11)
J & M CONTRACTING, COMPANY (6.40)
NIXON ENGINEERING, L.L.C. (0.05)
A. L. CONSTRUCTION, LLC (0.33)
Contract #12153016
Totals9556276.11305154.939871755.9599.9

CountyORANGE
HighwaySH 87
FromNEWTON CO/L,SOUTH
ToIH-10
CSJ0305-07-062
Proj IDC 305-7-62
Work TypeBASE REPAIR, OCST, ACP, STRIPE
 
8.5362890127.641059973.9036.6
CountyORANGE
HighwaySH 87
From4.2 MILES N OF FM 3247
To1.0 MILES N OF FM 3247
CSJ0305-07-064
Proj IDSTP 2018(752)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.203323408.0066171.5020.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-18
Work Began07-09-18
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged54
Percent Time Used60
Contractor(s)
PTSS INVESTMENTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0305-07-062
SIMCO ENTERPRISES, LTD. (6.78)
WEST TEXAS RUMBLE STRIP (0.35)
DUSTROL, INC. (14.96)
CRABTREE BARRICADE SYSTEMS, INC. (3.80)
AMERICAN REMEDIATION OPTIONS, INC. (1.10)
Contract #04183225
Totals3213535.6495165.081126145.4035.0

CountyORANGE
HighwaySH 73
FromN. OF THE VETERANS BRIDGE
ToSHADY LANE
CSJ0306-02-069
Proj IDNH 2017(959)
Work TypeGR,BA, ACP
 
5.2985658758.054869288.2386.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted39
Working Days Charged180
Percent Time Used90
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-02-069
DUSTROL, INC. (12.02)
CRABTREE BARRICADE SYSTEMS, INC. (5.00)
CPAVE, INC. (28.97)
STRIPE-A-ZONE, INC. (0.26)
Contract #04173221
Totals5658758.05403178.354869288.2386.0

CountyHARDIN
HighwaySH 105
From1.169 MI E. OF FM 770 (S)
To1.07 MI W OF SH 326
CSJ0339-03-037
Proj IDSTP 1702(634)HES
Work TypeSFTY TREAT FXD OBJ.
 
13.262184403.52182605.4999.0
CountyHARDIN
HighwaySH 105
From1.07 MI W OF SH 326
To1.095 MI W OF JEFFERSON C/L
CSJ0339-04-034
Proj IDSTP 1702(635)HES
Work TypeSFTY TREAT FXD OBJ
 
8.32536024.6546940.5699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-17
Work Began05-14-18
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted10
Working Days Charged35
Percent Time Used66
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0339-03-037
AREA WIDE PROTECTIVE, INC. (14.63)
WEST TEXAS RUMBLE STRIP (6.87)
Contract #08173023
Totals220428.170.00229546.0599.9

CountyJEFFERSON
HighwaySH 124
From.20 MILES N OF FM 364
To.20 MILES S OF FM 364
CSJ0368-03-033
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.3781126428.360.000.0
CountyJEFFERSON
HighwayFM 364
From900 FT S OF IH-10
ToSH 124
CSJ0786-01-083
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.2912397066.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days177
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0368-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173218
Totals3523494.740.000.000.0

CountyCHAMBERS
HighwaySH 146
From@IH-10
To.
CSJ0389-02-051
Proj IDSTP 2017(491)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200223068.55231317.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began10-23-17
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged46
Percent Time Used121
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-051
STRIPE LINES, INC. (1.62)
SOUTH RANGER CONSTRUCTION, INC. (4.01)
Contract #01173237
Totals223068.550.00231317.6099.9

CountyORANGE
HighwaySH 12
FromEVANGELINE LN.
ToSH 62
CSJ0499-03-058
Proj IDSTP 2018(565)HES
Work TypeINST CONT TURN LANE & RUMBLE STRIPS
 
6.1626632538.481159376.2517.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-18
Work Began04-18-18
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted3
Working Days Charged44
Percent Time Used23
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-058
CRABTREE BARRICADE SYSTEMS, INC. (3.91)
AMERICAN REMEDIATION OPTIONS, INC. (2.00)
CPAVE, INC. (0.36)
DUSTROL, INC. (6.95)
PENHALL COMPANY (0.15)
Contract #02183203
Totals6632538.4844177.501159376.2517.4

CountyCHAMBERS
HighwayIH 10
FromSH 146
To0.25 MI. E. OF SH 146 (WB FRONTAGE
CSJ0508-02-121
Proj IDSTP 2018(754)MM
Work TypeEXTEND WB TURN LANE
 
0.190235049.18202565.2886.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-18
Work Began07-03-18
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged32
Percent Time Used72
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-02-121
STRIPE LINES, INC. (3.14)
LONE STAR PAVING COMPANY (1.31)
LONESTAR TRAFFIC SAFETY, LLC (0.75)
A-1 EROSION CONTROL, LLC (0.46)
HOUSTON SAWING & DRILLING (2.76)
Contract #03183041
Totals235049.18107786.21202565.2886.1

CountyCHAMBERS
HighwaySH 73
FromFM 1663, EAST
To0.02 MILES WEST OF JEFFERSON CO/L
CSJ0508-03-098
Proj IDSTP 2013(577)
Work TypeGR, BS, PAV, STRIPE
 
1.5634865959.510.000.0
CountyCHAMBERS
HighwaySH 73
From0.02 MILES WEST OF JEFFERSON CO/L
ToJEFFERSON CO/L
CSJ0508-03-099
Proj IDSTP 2018(755)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.021100971.770.000.0
CountyJEFFERSON
HighwaySH 73
FromCHAMBERS COUNTY LINE, EAST
To0.6 MILES EAST OF SH 124
CSJ0508-04-162
Proj IDSTP 2013(576)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.85013780360.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-18
Work Began11-12-18
Work Completed
Time Computed00-00-00
Contract Working Days410
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-03-098
AMERICAN REMEDIATION OPTIONS, INC. (2.07)
GMJ PAVING CO. (14.21)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
BREDA COMPANY, INC. (0.14)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.61)
HEMPHILL WBE PILE DRIVING CO. (0.58)
PAVEMENT MARKINGS INC. (0.90)
Contract #04183002
Totals18747291.340.000.000.0

CountyCHAMBERS
HighwayIH 10
FromSH 61
ToFM 1406
CSJ0508-03-104
Proj IDSTP 2019(188)HES
Work TypeRUMBLE STRIPS
 
14.905342090.000.000.0
CountyLIBERTY
HighwayFM 1409
From0.146 MI N OF CR 444
ToCHAMBER COUNTY LINE
CSJ0762-02-049
Proj IDSTP 2019(188)HES
Work TypeRUMBLE STRIPS
 
4.77627998.280.000.0
CountyLIBERTY
HighwayFM 1008
From1.8 MI S OF FM 2797
To2.2 MI S OF FM 2797
CSJ0952-01-058
Proj IDSTP 2019(188)HES
Work TypeACP, RUMBLE STRIPS
 
0.400101219.000.000.0
CountyORANGE
HighwayFM 1442
FromJEWEL DR
ToS TERRY RD
CSJ1284-01-078
Proj IDSTP 2019(188)HES
Work TypeINSTALL CHEVRONS (CURVE)
 
0.70613550.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-03-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11183025
Totals484857.280.000.000.0

CountyLIBERTY
HighwaySH 321
FromUPRR, SOUTH
ToFM 1960
CSJ0593-01-114
Proj IDSTP 1702(277)
Work TypeACP, STRIPE
 
3.1961050836.681012405.3097.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began10-18-17
Work Completed
Time Computed00-00-00
Contract Working Days29
Addl Days Granted4
Working Days Charged58
Percent Time Used175
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-114
LONESTAR TRAFFIC SAFETY, LLC (0.10)
STRIPE-A-ZONE, INC. (0.41)
STRIPE LINES, INC. (4.55)
Contract #06173217
Totals1050836.685760.001012405.3097.9

CountyLIBERTY
HighwaySH 321
From4.5 MI. NORTH OF FM 686
To0.1 MI. SOUTH OF FM 686
CSJ0593-01-120
Proj IDSTP 2018(566)HES
Work TypeINST CONT TURN LANE & RUMBLE STRIPS
 
4.5015234742.153043892.4958.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-18
Work Began05-31-18
Work Completed
Time Computed00-00-00
Contract Working Days208
Addl Days Granted0
Working Days Charged96
Percent Time Used46
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-120
CRABTREE BARRICADE SYSTEMS, INC. (2.88)
J & M CONTRACTING COMPANY (7.99)
WILLOW CITY SIGN & RAIL, INC. (0.77)
STRIPE-A-ZONE, INC. (0.27)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.01)
MURRAY CONSTRUCTION (0.32)
Contract #02183022
Totals5234742.15375542.733043892.4958.1

CountyLIBERTY
HighwaySH 321
FromSL 573
ToSH 105
CSJ0593-01-123
Proj IDC 593-1-123
Work TypeLEVEL-UP/OVERLAY
 
2.005845384.55801782.2394.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-18
Work Began07-05-18
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged29
Percent Time Used96
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-123
STRIPE LINES, INC. (4.96)
INTERSTATE BARRICADES & MARKINGS, INC. (0.59)
TEXOP CONSTRUCTION (4.70)
Contract #03183043
Totals845384.550.00801782.2394.8

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.4212563832.4952.0
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.0311286221.9559.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted55
Working Days Charged319
Percent Time Used42
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
INFRASTRUCTURE SERVICES, INC. (0.04)
AGGREGATE TECHNOLOGIES, INC. (0.17)
RAY"S THREADING AND FAB SHOP (0.43)
Contract #09163201
Totals43169694.45403724.5823850054.4455.2

CountyJEFFERSON
HighwayIH 10
From0.64 MILES WEST OF HAMSHIRE RD,EAST
To0.76 MILES EAST OF FM 365
CSJ0739-02-161
Proj IDNH 1702(506)
Work TypeGR, BS, STR, PVMT
 
6.761108315367.9727520164.6125.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-17
Work Began09-26-17
Work Completed
Time Computed00-00-00
Contract Working Days770
Addl Days Granted0
Working Days Charged174
Percent Time Used22
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-161
ESSARY, HART & MACWILIAM,INC. (6.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.52)
PENHALL COMPANY (AUSTIN) (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.65)
BATTERSON,LLP (0.62)
SCOTT DERR PAINTING CO, LLC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
ANGEL BROTHERS ENTERPRISES, LTD. (0.91)
GULF COAST ASPHALT & PAVING, INC. (BAYTOWN) (0.00)
AMERICAN REMEDIATION OPTIONS, INC. (0.46)
HAYWOOD BAKER (0.02)
KMA CONTRACTORS SERVICES INC. (0.13)
Contract #08173205
Totals108315367.97905766.0627520164.6125.4

CountyJEFFERSON
HighwayIH 10
FromFM 365, EAST
ToCR 131 (WALDEN ROAD)
CSJ0739-02-162
Proj IDNH 1802(413)
Work TypeGR, BS, STR, PVMT
 
9.936128399059.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days842
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183201
Totals128399059.910.000.000.0

CountyLIBERTY
HighwayFM 787
FromFM 2518
ToFM 223
CSJ0813-01-101
Proj IDSTP 2018(756)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.853539803.00308786.6657.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-18
Work Began06-11-18
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged78
Percent Time Used86
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-101
DUSTIN ALLEN, INC. (8.92)
Contract #04183022
Totals539803.0024786.20308786.6657.2

CountyTYLER
HighwayFM 256
FromAT BELT CREEK
To(STR 087703003)
CSJ0877-03-025
Proj IDBR 2018(849)
Work TypeSTR, GR, BS, PVMT
 
0.125539688.90242565.4244.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-18
Work Began09-10-18
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged24
Percent Time Used32
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0877-03-025
AMERICAN REMEDIATION OPTIONS, INC. (7.87)
CRABTREE BARRICADE SYSTEMS, INC. (1.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.57)
HEMPHILL WBE PILE DRIVING CO. (4.76)
MILLER TRANSPORTATION (0.86)
Contract #05183046
Totals539688.9080846.54242565.4244.9

CountyORANGE
HighwayFM 105
From0.09 MI E OF BYRON RD, EAST
To0.02 MI E OF FM 1135
CSJ0883-02-086
Proj IDSSW 883-2-86
Work TypeBS, ACP, MILLED RUMBLE STRIPS
 
2.1911139721.42120312.5010.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-18
Work Began08-13-18
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged31
Percent Time Used63
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0883-02-086
AMERICAN REMEDIATION OPTIONS, INC. (2.19)
AREA WIDE PROTECTIVE, INC. (0.23)
CRABTREE BARRICADE SYSTEMS, INC. (1.19)
NORMAN HIGHWAY CONSTRUCTORS, INC. (5.44)
PENHALL COMPANY (0.57)
Contract #05183241
Totals1139721.4220625.00120312.5010.5

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-119
Proj IDSTP 1702(116)
Work TypeLANDSCAPE
 
0.500624968.15614706.3298.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began10-09-17
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged32
Percent Time Used18
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-119
CRABTREE BARRICADE SYSTEMS, INC. (2.11)
Contract #05173019
Totals624968.152500.00614706.3298.3