Monthly State Let Construction Report For Beaumont District As Of Oct 16, 2017 Page 2 Of 4

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJASPER
HighwayUS 190
FromAT NECHES RIVER RELIEF
To(STR 021308068)
CSJ0213-08-077
Proj IDBR 1502(228)
Work TypeGR, BS, PVMT & STR
 
0.6027078117.165971582.4387.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-15
Work Began11-16-15
Work Completed
Time Computed00-00-00
Contract Working Days252
Addl Days Granted13
Working Days Charged381
Percent Time Used143
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0213-08-077
AMERICAN REMEDIATION OPTIONS, INC. (1.28)
CRABTREE BARRICADE SYSTEMS, INC. (0.92)
J & M CONTRACTING, COMPANY (4.19)
TEX OP CONSTRUCTION, LP (0.21)
CPAVE, INC. (0.34)
COASTAL PILE CUTTERS, LLC (0.40)
PRIMATE CONSTRUCTION, INC. (0.15)
Contract #06153039
Totals7078117.16308480.545971582.4387.8

CountyCHAMBERS
HighwaySH 61
FromLIBERTY C/L
ToFM 1663
CSJ0242-03-074
Proj IDSTP 2016(949)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
2.285889007.06924440.0399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged69
Percent Time Used102
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0242-03-074
CRABTREE BARRICADE SYSTEMS, INC. (2.29)
J & M CONTRACTING, COMPANY (26.00)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.62)
WEST TEXAS RUMBLE STRIP (0.54)
A-1 EROSION CONTROL, LLC (0.46)
Contract #04163228
Totals889007.060.00924440.0399.9

CountyCHAMBERS ETC
HighwaySH 61 ETC
FromIH 10
ToFM 563
CSJ0242-03-075
Proj IDSTP 2017(614)HES
Work TypeRUMBLE STRIPS
 
84.348244900.27231122.1294.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days31
Addl Days Granted0
Working Days Charged29
Percent Time Used93
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0242-03-075
WEST TEXAS RUMBLE STRIP (18.16)
Contract #02173032
Totals244900.2729878.34231122.1294.3

CountyJASPER
HighwaySH 62
From0.168 MILES SOUTH OF FM 253, SOUTH
To3.379 MILES NORTH OF NEWTON CO/L
CSJ0243-01-050
Proj IDSTP 1502(422)
Work TypeGR, BS, OV, STRIPE
 
9.0179416731.773865022.7041.0
CountyJASPER
HighwayFM 2246
From0.118 MILES WEST OF SH 62, EAST
ToSH 62
CSJ2120-01-027
Proj IDSTP 1502(666)
Work TypeGR, BS, OV, STRIPE
 
0.118139544.3432868.8023.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began08-30-16
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged173
Percent Time Used86
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0243-01-050
AMERICAN REMEDIATION OPTIONS, INC. (0.76)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95)
WEST TEXAS RUMBLE STRIP (0.11)
J & M CONTRACTING, COMPANY (6.40)
NIXON ENGINEERING, L.L.C. (0.05)
Contract #12153016
Totals9556276.1160907.043897891.5040.7

CountyNEWTON
HighwaySH 87
FromFM 253
To2.159 MILES SOUTH OF FM 253
CSJ0305-04-037
Proj IDSTP 2017(958)
Work TypeBASE REPAIR, 2" SMA
 
2.159957938.3040923.004.2
CountyNEWTON
HighwaySH 87
From2.159 MILES SOUTH OF FM 253
ToCYPRESS CREEK
CSJ0305-05-045
Proj IDSTP 2017(958)
Work TypeBASE REPAIR, 2" SMA
 
3.4041312390.4845499.003.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged2
Percent Time Used7
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0305-04-037
CRABTREE BARRICADE SYSTEMS, INC. (1.44)
DUSTROL, INC. (0.48)
DIAMOND SURFACE, INC. (0.51)
Contract #04173218
Totals2270328.7886422.0086422.003.8

CountyORANGE
HighwaySH 73
FromN. OF THE VETERANS BRIDGE
ToSHADY LANE
CSJ0306-02-069
Proj IDNH 2017(959)
Work TypeGR,BA, ACP
 
5.2985658758.05858923.8515.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged30
Percent Time Used18
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-02-069
DUSTROL, INC. (12.02)
CRABTREE BARRICADE SYSTEMS, INC. (5.00)
CPAVE, INC. (28.97)
Contract #04173221
Totals5658758.05275869.66858923.8515.1

CountyJEFFERSON
HighwaySH 73
FromAT RAINBOW BRIDGE
To(STR 030603015)
CSJ0306-03-123
Proj IDNH 2014(978)
Work TypeCLEAN AND REPAINT BRIDGE
 
1.46026599824.2028419789.00100.0
Work Order10-17-14
Work Began01-05-15
Work Completed08-21-17
Time Computed11-02-14
Contract Working Days614
Addl Days Granted0
Working Days Charged686
Percent Time Used111
Contractor(s)
SAFFO CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-123
CRABTREE BARRICADE SYSTEMS, INC. (0.14)
JMD BUILDING PRODUCTS LLC (5.07)
EMPIRE SCAFFOLD (6.33)
CEKRA INC. (3.08)
WIDGEON CONSTRUCTION, INC. (0.04)
Contract #07143202
Totals26599824.2058472.8128419789.00100.0

CountyJEFFERSON
HighwaySH 73
FromSH 87
To0.400 MILES EAST OF FM 366
CSJ0306-03-126
Proj IDNH 2017(301)
Work TypePVMT REPAIR, MILL, OCST, PFC
 
0.782649754.10346617.0453.3
CountyJEFFERSON
HighwaySH 73
From0.300 MILES WEST OF SPUR 215, EAST
ToSH 87
CSJ0508-04-166
Proj IDNH 2017(301)
Work TypePVMT REPAIR, MILL, OCST, PFC
 
6.1157596920.754738928.4262.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-27-17
Work Began05-09-17
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged78
Percent Time Used43
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-126
CRABTREE BARRICADE SYSTEMS, INC. (3.18)
CPAVE, INC. (15.10)
Contract #01173021
Totals8246674.85900540.095085545.4661.6

CountyHARDIN
HighwaySH 105
From1.169 MI E. OF FM 770 (S)
To1.07 MI W OF SH 326
CSJ0339-03-037
Proj IDSTP 1702(634)HES
Work TypeSFTY TREAT FXD OBJ.
 
13.262184403.520.000.0
CountyHARDIN
HighwaySH 105
From1.07 MI W OF SH 326
To1.095 MI W OF JEFFERSON C/L
CSJ0339-04-034
Proj IDSTP 1702(635)HES
Work TypeSFTY TREAT FXD OBJ
 
8.32536024.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0339-03-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173023
Totals220428.170.000.000.0

CountyHARDIN
HighwaySH 105
FromEAST OF SH 326, EAST
ToJEFFERSON C/L
CSJ0339-04-035
Proj IDNH 1702(265)
Work TypePAVEMENT REPAIR, MILL, OCST, PFC
 
7.2332678096.512614174.1797.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-14-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged21
Percent Time Used35
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0339-04-035
CRABTREE BARRICADE SYSTEMS, INC. (3.91)
C PAVE, INC. (3.17)
Contract #06173022
Totals2678096.511624713.432614174.1797.6

CountyCHAMBERS
HighwaySH 146
From@IH-10
To.
CSJ0389-02-051
Proj IDSTP 2017(491)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200223068.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-051
STRIPE LINES, INC. (1.62)
SOUTH RANGER CONSTRUCTION, INC. (0.00)
Contract #01173237
Totals223068.550.000.000.0

CountyLIBERTY
HighwaySH 321
FromUPRR, SOUTH
ToFM 1960
CSJ0593-01-114
Proj IDSTP 1702(277)
Work TypeACP, STRIPE
 
3.1961050836.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days29
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-114
LONESTAR TRAFFIC SAFETY, LLC (0.10)
STRIPE-A-ZONE, INC. (0.41)
STRIPE LINES, INC. (4.55)
Contract #06173217
Totals1050836.680.000.000.0

CountyLIBERTY
HighwaySH 105
From0.647 MILES EAST OF SH 321
To1.251 MILES EAST OF SH 321
CSJ0593-01-117
Proj IDSTP 1602(153)HES
Work TypeGR, BASE, STRIPE, ACP
 
0.6041388679.601790855.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted19
Working Days Charged120
Percent Time Used88
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-117
J & M CONTRACTING, COMPANY (14.84)
CEN TEX HYDROSEED, INC. (0.95)
WATERS CONSTRUCTION CO., INC. (2.17)
CRABTREE BARRICADE SYSTEMS, INC. (2.90)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.07)
COWBELL TRAFFIC SERVICES, INC. (0.43)
LONE STAR TRAFFIC SERVICE, INC. (0.33)
TEX OP CONSTRUCTION, LP (1.59)
JOHN REED AND COMPANY, LLC (19.47)
EROSION ABATEMENT, LLC (0.55)
CPAVE, INC. (1.34)
STRIPE-A-ZONE, INC. (0.43)
Contract #06163013
Totals1388679.60336543.261790855.1199.9

CountyJASPER
HighwayFM 105
FromUS 96
To2.0 MILES SOUTH OF US 96
CSJ0710-01-049
Proj IDSTP 2017(961)
Work TypeBASE REPAIR, 2" SMA
 
1.8721012112.49938340.8492.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began07-13-17
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged21
Percent Time Used65
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0710-01-049
CRABTREE BARRICADE SYSTEMS, INC. (2.24)
AMERICAN REMEDIATION OPTIONS, INC. (0.32)
TEXOP CONSTRUCTION (1.10)
Contract #04173017
Totals1012112.49665166.84938340.8492.7

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.426787482.5728.1
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.038724439.1245.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted0
Working Days Charged155
Percent Time Used22
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INFRASTRUCTURE SERVICES, INC. (0.04)
Contract #09163201
Totals43169694.45576539.3315511921.6935.9

CountyJEFFERSON
HighwayIH 10
From0.64 MILES WEST OF HAMSHIRE RD,EAST
To0.76 MILES EAST OF FM 365
CSJ0739-02-161
Proj IDNH 1702(506)
Work TypeGR, BS, STR, PVMT
 
6.761108315367.9718143384.2516.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-17
Work Began09-26-17
Work Completed
Time Computed00-00-00
Contract Working Days770
Addl Days Granted0
Working Days Charged4
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-161
ESSARY, HART & MACWILIAM,INC. (6.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.52)
PENHALL COMPANY (AUSTIN) (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.65)
BATTERSON,LLP (0.62)
SCOTT DERR PAINTING CO, LLC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.00)
ANGEL BROTHERS ENTERPRISES, LTD. (0.91)
GULF COAST ASPHALT & PAVING, INC. (BAYTOWN) (0.00)
Contract #08173205
Totals108315367.9718143384.2518143384.2516.7

CountyHARDIN
HighwayFM 418
FromFM 92, SOUTH
ToUS 96
CSJ0784-01-046
Proj IDSTP 1602(064)HES
Work TypeSFTY TRT FXD OBJ
 
1.6911031113.541004236.4397.3
CountyHARDIN
HighwayFM 1003
FromFM 1293
ToSOUTH, 2.5 MI
CSJ0811-02-028
Proj IDSTP 1602(065)HES
Work TypeSFTY TRT FXD OBJ
 
2.50046474.4043605.3093.8
CountyHARDIN
HighwayFM 787
FromFM 1293
ToSOUTH, 6.0 MI
CSJ0813-02-038
Proj IDSTP 1602(063)HES
Work TypeSFTY TRT FXD OBJ
 
6.000204002.85216816.7599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-29-16
Work Began01-03-17
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted4
Working Days Charged99
Percent Time Used52
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0784-01-046
AMERICAN REMEDIATION OPTIONS, INC. (5.30)
CRABTREE BARRICADE SYSTEMS, INC. (2.13)
NORMAN HIGHWAY CONSTRUCTORS, INC. (23.51)
Contract #05163229
Totals1281590.790.001264658.4898.6

CountyHARDIN
HighwayFM 421
From1.5 MI E OF FM 326
To4.1 MI W OF LUMBERTON
CSJ0813-03-043
Proj IDSTP 1702(114)HES
Work TypeSFTY TREAT FXD OBJ
 
6.5611375866.73313069.2522.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-17
Work Began08-07-17
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged14
Percent Time Used28
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0813-03-043
AMERICAN REMEDIATION OPTIONS, INC. (4.98)
CRABTREE BARRICADE SYSTEMS, INC. (2.87)
TOTAL HIGHWAY MAINTENANCE, LLC (48.96)
WIDGEON CONSTRUCTION, INC. (2.72)
Contract #05173206
Totals1375866.73194431.25313069.2522.7

CountyORANGE
HighwayFM 2177
From0.7 MILES NORTH OF FM 1006
ToFM 1006
CSJ0882-01-013
Proj IDSTP 2017(962)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE
 
0.700328092.65353018.3099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-17
Work Began06-10-17
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged37
Percent Time Used105
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0882-01-013
CRABTREE BARRICADE SYSTEMS, INC. (3.01)
AMERICAN REMEDIATION OPTIONS, INC. (4.27)
NORMAN HIGHWAY CONSTRUCTORS, INC. (8.77)
Contract #04173023
Totals328092.65164508.82353018.3099.9

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-116
Proj IDSTP 2014(646)
Work TypeLANDSCAPE
 
3.428832522.01809876.2297.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-14
Work Began10-20-14
Work Completed
Time Computed00-00-00
Contract Working Days219
Addl Days Granted0
Working Days Charged198
Percent Time Used90
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
CLASSIC TEJAS CONSTRUCTION, INC. (3.46)
CRABTREE BARRICADE SYSTEMS, INC. (1.68)
Contract #05143219
Totals832522.012000.00809876.2297.2

page 1 | page 2 | page 3 | page 4