Monthly State Let Construction Report For Beaumont District As Of Dec 07, 2021 Page 2 Of 4

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNEWTON
HighwaySH 63
FromAT SABINE RIVER(BURRS FERRY)
To(STR_021404005)
CSJ0214-03-036
Proj IDBR 1802(764)
Work TypeRETROFIT BRIDGE BENTS
 
0.3562799157.503600009.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began11-14-18
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted25
Working Days Charged113
Percent Time Used93
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0214-03-036
AREA WIDE PROTECTIVE, INC. (0.15)
RUSSO CORPORATION (44.88)
BOWMAN ENGINEERING & CONSULTING, INC. (2.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.09)
Contract #08183058
Totals2799157.500.003600009.4099.9

CountyNEWTON
HighwaySH 87
From0.05 MI NORTH OF CR 4012, SOUTH
To0.05 MI NORTH OF CR 3038
CSJ0305-01-035
Proj IDSTP 2021(381)
Work TypeOVERLAY
 
1.655120619.35229173.4699.9
CountyNEWTON
HighwaySH 87
From0.277 MILES S. OF CR 3037
ToFM 363
CSJ0305-02-049
Proj IDSTP 2021(381)
Work TypeOVERLAY
 
4.1261378153.301368734.9099.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began08-23-21
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged40
Percent Time Used88
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0305-01-035
BARRICADES UNLIMITED (3.11)
WEST TEXAS ROCK RESOURCES, LLC (0.73)
Contract #02213023
Totals1498772.65129553.001597908.3699.9

CountyORANGE
HighwaySH 87
FromIH 10
ToSH 87
CSJ0305-07-071
Proj IDF 2021(757)
Work TypeOVERLAY
 
1.9401985537.22333056.6916.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-18-21
Work Began10-11-21
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged25
Percent Time Used33
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0305-07-071
AMERICAN REMEDIATION OPTIONS, INC. (0.46)
BARRICADES UNLIMITED (2.59)
CPAVE, INC. (20.39)
DUSTROL, INC. (8.49)
NORMAN HIGHWAY CONSTRUCTORS, INC. (5.89)
MOREAUX TRANSPORTATION SERVICES, INC. (1.56)
Contract #07213025
Totals1985537.22192542.31333056.6916.7

CountyJEFFERSON
HighwaySH 87
FromUS 69
ToTERMINAL RD.
CSJ0307-01-149
Proj IDC 307-1-149
Work TypeOVERLAY
 
2.6732734996.752098745.9676.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began03-15-21
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged120
Percent Time Used66
Contractor(s)
PTSS INVESTMENTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0307-01-149
DUSTROL, INC. (8.49)
CRABTREE BARRICADE SYSTEMS, INC. (2.06)
CPAVE, INC. (45.51)
Contract #10203227
Totals2734996.75212856.152098745.9676.7

CountyHARDIN
HighwaySH 105
FromAT OLD BATSON-SARATOGA ROAD
To.
CSJ0339-03-039
Proj IDSTP 2021(465)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.400645518.9442379.006.5
Work Order09-20-21
Work Began00-00-00
Work Completed
Time Computed10-20-21
Contract Working Days45
Addl Days Granted0
Working Days Charged20
Percent Time Used44
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0339-03-039
AMERICAN REMEDIATION OPTIONS, INC. (2.71)
BARRICADES UNLIMITED (2.00)
NORMAN HIGHWAY CONSTRUCTORS, INC. (52.44)
PINNACLE GRINDING AND GROOVING LLC (0.48)
MOREAUX TRANSPORTATION SERVICES, INC. (0.49)
Contract #08213055
Totals645518.9442379.0042379.006.5

CountyJEFFERSON
HighwaySH 124
From0.6 MI E OF FM 364, WEST
To0.289 MI E OF FM 364
CSJ0368-03-037
Proj IDSTP 2021(467)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.320220436.18178275.4980.8
CountyJEFFERSON
HighwaySH 124
From0.5 MI W OF BROOKS RD, WEST
To0.6 MI E OF FM 364
CSJ0368-04-032
Proj IDSTP 2021(467)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.276141581.23114879.3881.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began09-01-21
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged29
Percent Time Used64
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0368-03-037
AMERICAN REMEDIATION OPTIONS, INC. (3.11)
AREA WIDE PROTECTIVE, INC. (2.64)
PINNACLE GRINDING AND GROOVING LLC (0.91)
WEST TEXAS BARRICADE AND LIGHT CO. (5.54)
MOREAUX TRANSPORTATION SERVICES, INC. (0.41)
CPAVE, INC. (3.45)
Contract #04213017
Totals362017.41133881.22293154.8780.9

CountyJEFFERSON
HighwaySH 124
From@ HILLEBRANDT BAYOU-STR #201240036804036
To.
CSJ0368-04-033
Proj IDBR 2021(375)
Work TypeBRIDGE REPLACEMENT
 
0.1122659519.1532000.001.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0368-04-033
LONE STAR PAVING COMPANY (1.88)
LONESTAR TRAFFIC SAFETY, LLC (0.24)
SEMPER STRIPING LLC (0.15)
RDI FOUNDATION DRILLING (25.33)
LINDAMOOD DEMOLITION, INC. (3.85)
DARKHORSE INDUSTRIES, L.L.C. (1.11)
AGGREGATE TECHNOLOGIES, INC. (1.96)
Contract #03213013
Totals2659519.150.0032000.001.2

CountyLIBERTY
HighwaySH 146
From0.599 MI N OF FM 1011, SOUTH
To0.215 MI N OF FM 1011
CSJ0388-03-081
Proj IDSTP 2021(475)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.265352845.11317656.1190.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-21
Work Began09-01-21
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged31
Percent Time Used75
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0388-03-081
AMERICAN REMEDIATION OPTIONS, INC. (3.70)
AREA WIDE PROTECTIVE, INC. (1.01)
PINNACLE GRINDING AND GROOVING LLC (0.85)
BARRICADES UNLIMITED (3.09)
Contract #04213026
Totals352845.11215626.36317656.1190.0

CountyCHAMBERS
HighwaySH 146
FromAT HORSEPEN BAYOU
To(STR 200360038902028)
CSJ0389-02-048
Proj IDBR 2021(529)
Work TypeBRIDGE MAINTENANCE
 
0.07575084.0052325.0069.6
CountyLIBERTY
HighwaySH 105
FromAT TARKINGTON BAYOU RELIEF
To(STR 201460059301010)
CSJ0593-01-115
Proj IDBR 2021(528)
Work TypeBRIDGE MAINTENANCE
 
0.00531087.0021703.0069.8
CountyCHAMBERS
HighwayIH 10
FromAT DRAW
To(STR 200360073901030)
CSJ0739-01-047
Proj IDBR 2021(527)
Work TypeBRIDGE MAINTENANCE
 
0.006124153.002.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-24-21
Work Began10-13-21
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged26
Percent Time Used34
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213235
Totals230324.002.0074030.0032.1

CountyCHAMBERS
HighwaySH 146
FromIH-10
ToFM 1405
CSJ0389-02-052
Proj IDSTP 2B20(070)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.114758737.70512910.2467.6
CountyCHAMBERS
HighwaySH 146
From0.48 MI S OF IH10, SOUTH
To0.248 MI S OF IH 10
CSJ0389-02-055
Proj IDSTP 2B20(070)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200359108.00162838.9745.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-24-20
Work Began11-12-20
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted15
Working Days Charged145
Percent Time Used81
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-052
HIGHWAY 1 LLC (14.91)
GEORGE MEEKS LANDPRO, INC. (1.80)
WEBER-BALKE FOUNDATION COMPANY, INC (2.95)
REPUBLIC TRAFFIC SAFETY, INC. (0.55)
KLP COMMERCIAL, L.L.C. (0.54)
CURB PLANET INC. (0.21)
THIRD COAST SERVICES LLC (0.25)
TEXAS CONCRETE ENTERPRISE READY MIX, INC. (3.65)
Contract #08203253
Totals1117845.7076800.00675749.2160.4

CountyNEWTON
HighwaySH 12
FromSH 87, NORTH
ToLA STATE LINE
CSJ0499-02-031
Proj IDF 2021(723)
Work TypeOVERLAY
 
3.1301509217.560.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0499-02-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213228
Totals1509217.560.000.000.0

CountyCHAMBERS
HighwayIH 10
FromAT FM 3180
To.
CSJ0508-02-120
Proj IDSTP 2018(953)MM
Work TypeGR, BS, STR, PVMT, SIGN .
 
1.00031129641.4326555939.3883.7
CountyCHAMBERS
HighwayFM 3180
FromIH-10, SOUTH
To0.60 MILES SOUTH OF FM 565
CSJ3271-01-015
Proj IDSTP 2018(954)MM
Work TypeGR, STR, BS, PVMT, STRIPE
 
2.4643894277.533562306.1191.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-19
Work Began05-01-19
Work Completed
Time Computed00-00-00
Contract Working Days793
Addl Days Granted0
Working Days Charged709
Percent Time Used89
Contractor(s)
COPASA INC
SUBCONTRACTOR(S) FOR CCSJ: 0508-02-120
BUYERS BARRICADES HOUSTON, LLC. (0.06)
ALTUS CONSTRUCTION LLC (14.38)
PROFESSIONAL TRAFFIC CONTROL LLC (0.21)
SOUTHERN CRUSHED CONCRETE LLC (1.78)
GMJ PAVING CO. (14.29)
BELL BOTTOM FOUNDATION CO. (3.45)
FARR FOUNDATION, INC. (0.28)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.34)
CURB PLANET INC. (0.03)
ROYAL REBAR (0.64)
AARON CONCRETE CONTRACTORS, L.P. (0.65)
PENHALL COMPANY (0.11)
BATTERSON, LLP (0.33)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.99)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
CREATIVE PAVING CONCEPTS, LLC (0.58)
TEXAS MATERIALS GROUP, INC. (0.33)
MARTIN MARIETTA MATERIALS, INC. (1.63)
Contract #02193001
Totals35023918.96435648.3930118245.4984.5

CountyCHAMBERS
HighwaySH 73
FromFM 1663, EAST
To0.02 MILES WEST OF JEFFERSON CO/L
CSJ0508-03-098
Proj IDSTP 2013(577)
Work TypeGR, BS, PAV, STRIPE
 
1.5634865959.515012709.3199.9
CountyCHAMBERS
HighwaySH 73
From0.02 MILES WEST OF JEFFERSON CO/L
ToJEFFERSON CO/L
CSJ0508-03-099
Proj IDSTP 2018(755)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.021100971.77222343.9599.9
CountyJEFFERSON
HighwaySH 73
FromCHAMBERS COUNTY LINE, EAST
To0.6 MILES EAST OF SH 124
CSJ0508-04-162
Proj IDSTP 2013(576)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.85013780360.0613681761.7899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-18
Work Began11-12-18
Work Completed
Time Computed00-00-00
Contract Working Days410
Addl Days Granted0
Working Days Charged494
Percent Time Used120
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-03-098
AMERICAN REMEDIATION OPTIONS, INC. (2.07)
GMJ PAVING CO. (14.21)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
BREDA COMPANY, INC. (0.13)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.61)
HEMPHILL WBE PILE DRIVING CO. (0.58)
PMI PAVEMENT MARKING, LLC (0.90)
TEXAS MATERIALS GROUP, INC. (1.85)
CURB PLANET INC. (0.07)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
SCOTT DERR PAINTING CO, LLC (0.21)
Contract #04183002
Totals18747291.34209666.1118916815.0499.9

CountyLIBERTY
HighwaySH 105
From0.07 MI W OF CR 2247, EAST
To0.968 MI E OF CR 2247
CSJ0593-01-130
Proj IDSTP 2021(532)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.038856006.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-130
AMERICAN REMEDIATION OPTIONS, INC. (1.69)
BARRICADES UNLIMITED (1.24)
BATTERSON, LLP (1.90)
J & M CONTRACTING, COMPANY (13.27)
PINNACLE GRINDING AND GROOVING LLC (0.62)
Contract #08213253
Totals856006.940.000.000.0

CountyJEFFERSON ETC
HighwayFM 366 ETC
FromAT HOGABOOM RD
To.
CSJ0667-02-111
Proj IDSTP 2019(742)HES
Work TypeSFT
 
0.883785720.35790332.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-19
Work Began03-11-20
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged98
Percent Time Used95
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0667-02-111
STRIPE LINES, INC. (0.63)
Contract #07193257
Totals785720.350.00790332.6899.9

CountyTYLER
HighwayFM 92
FromHARDIN COUNTY LINE, NORTH
To2 MILES SOUTH OF FM 1013
CSJ0703-01-067
Proj IDSTP 2020(783)
Work TypeOVERLAY
 
7554649.357043981.5393.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-18-20
Work Began11-02-20
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted16
Working Days Charged100
Percent Time Used51
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0703-01-067
AMERICAN REMEDIATION OPTIONS, INC. (1.44)
CRABTREE BARRICADE SYSTEMS, INC. (1.48)
TEXOP CONSTRUCTION (0.35)
MTS E-TEX SERVICES, LLC (0.78)
AREA WIDE PROTECTIVE, INC. (0.06)
FREDONIA CONSTRUCTION SERVICES (0.13)
PINTO CONSTRUCTION CO., INC. (55.48)
WEST TEXAS ROCK RESOURCES, LLC (0.22)
Contract #04203213
Totals7554649.351742279.157043981.5393.2

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.4226913852.2899.9
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.0319616882.0499.9
CountyZERO COUNTIES
Highway
From
To
CSJ0920-00-144
Proj ID
Work Type
 
0.00690754.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted242
Working Days Charged894
Percent Time Used95
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
INFRASTRUCTURE SERVICES, INC. (0.04)
AGGREGATE TECHNOLOGIES, INC. (0.17)
RAY"S THREADING AND FAB SHOP (0.43)
Contract #09163201
Totals43169694.4546058.4347221488.3299.9

CountyJEFFERSON
HighwayIH 10
From0.64 MILES WEST OF HAMSHIRE RD,EAST
To0.76 MILES EAST OF FM 365
CSJ0739-02-161
Proj IDNH 1702(506)
Work TypeGR, BS, STR, PVMT
 
6.761108315367.9763519132.1858.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-17
Work Began09-26-17
Work Completed
Time Computed00-00-00
Contract Working Days770
Addl Days Granted214
Working Days Charged676
Percent Time Used68
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-161
ESSARY, HART & MACWILIAM,INC. (6.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.52)
PENHALL COMPANY (AUSTIN) (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.65)
BATTERSON,LLP (0.62)
SCOTT DERR PAINTING CO, LLC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
ANGEL BROTHERS ENTERPRISES, LTD. (0.91)
GULF COAST ASPHALT & PAVING, INC. (BAYTOWN) (0.00)
AMERICAN REMEDIATION OPTIONS, INC. (0.46)
HAYWOOD BAKER (0.02)
KMA CONTRACTORS SERVICES INC. (0.13)
AGGREGATE TECHNOLOGIES, INC. (0.00)
Contract #08173205
Totals108315367.9794600.9063519132.1858.6

CountyJEFFERSON
HighwayIH 10
FromFM 365, EAST
ToCR 131 (WALDEN ROAD)
CSJ0739-02-162
Proj IDNH 1802(413)
Work TypeGR, BS, STR, PVMT
 
9.936128399059.9162225564.4348.4
Work Order08-15-18
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days842
Addl Days Granted51
Working Days Charged483
Percent Time Used54
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-162
ANTIGO CONSTRUCTION, INC. (0.19)
CREACOM, INC. (3.61)
BUYERS BARRICADES HOUSTON, LLC. (0.01)
HAYWARD BAKER, INC. (0.23)
HEMPHILL WBE PILE DRIVING CO. (0.17)
JB PINNACLE GROUP, LLC (1.09)
J.H. PAINTING COMPANY (0.04)
JMHP, INC. (0.94)
(INACTIVE)PRIMATE CONSTRUCTION, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.46)
ROYAL REBAR (0.90)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.18)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.66)
W. W. FOUNDATION DRILLING, LTD. (1.14)
OVEMAN TRUCKING, LLC (0.77)
PANTHER CREEK TRANSPORTATION, INC. (1.55)
SB FLEET - LUBE, LLC (1.76)
SOLIS TRUCKING (0.63)
PLESSALA TRUCKING LLC (0.14)
KLP COMMERCIAL, L.L.C. (0.94)
HB FARMER FOUNDATION, LLC (1.14)
DORAN STEEL, INC. (0.05)
BRISTER"S TRANSPORT, LLC (0.55)
HERITAGE MATERIALS, LLC (1.17)
RAY"S THREADING AND FAB SHOP (0.44)
SIBONEY CONTRACTING CO. (0.77)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.13)
FLASHER EQUIPMENT COMPANY (0.55)
LINDAMOOD DEMOLITION, INC. (0.45)
Contract #07183201
Totals128399059.91930179.3862225564.4348.4

CountyJASPER
HighwayRE 255
From2.30 MILES WEST OF FM 1007
To0.11 MILES EAST OF FM 1007
CSJ0877-01-043
Proj IDF 2021(758)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.4372233852.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-18-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0877-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213033
Totals2233852.330.000.000.0