Monthly State Let Construction Report For Beaumont District As Of Jan 10, 2018 Page 2 Of 3

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARDIN
HighwaySH 105
FromEAST OF SH 326, EAST
ToJEFFERSON C/L
CSJ0339-04-035
Proj IDNH 1702(265)
Work TypePAVEMENT REPAIR, MILL, OCST, PFC
 
7.2332678096.512648444.2698.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-14-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged33
Percent Time Used55
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0339-04-035
CRABTREE BARRICADE SYSTEMS, INC. (3.91)
C PAVE, INC. (3.17)
Contract #06173022
Totals2678096.510.002648444.2698.8

CountyJEFFERSON
HighwaySH 124
From.20 MILES N OF FM 364
To.20 MILES S OF FM 364
CSJ0368-03-033
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.3781126428.360.000.0
CountyJEFFERSON
HighwayFM 364
From900 FT S OF IH-10
ToSH 124
CSJ0786-01-083
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.2912397066.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days177
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0368-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173218
Totals3523494.740.000.000.0

CountyCHAMBERS
HighwaySH 146
From@IH-10
To.
CSJ0389-02-051
Proj IDSTP 2017(491)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200223068.55216079.0597.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began10-23-17
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged40
Percent Time Used105
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-051
STRIPE LINES, INC. (1.62)
SOUTH RANGER CONSTRUCTION, INC. (4.01)
Contract #01173237
Totals223068.5541832.13216079.0597.3

CountyLIBERTY
HighwaySH 321
FromUPRR, SOUTH
ToFM 1960
CSJ0593-01-114
Proj IDSTP 1702(277)
Work TypeACP, STRIPE
 
3.1961050836.68103240.029.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days29
Addl Days Granted0
Working Days Charged15
Percent Time Used51
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-114
LONESTAR TRAFFIC SAFETY, LLC (0.10)
STRIPE-A-ZONE, INC. (0.41)
STRIPE LINES, INC. (4.55)
Contract #06173217
Totals1050836.6816320.00103240.029.8

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.428632914.3435.7
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.039648649.9250.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted0
Working Days Charged196
Percent Time Used28
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INFRASTRUCTURE SERVICES, INC. (0.04)
AGGREGATE TECHNOLOGIES, INC. (0.17)
Contract #09163201
Totals43169694.45604559.5918281564.2642.3

CountyJEFFERSON
HighwayIH 10
From0.64 MILES WEST OF HAMSHIRE RD,EAST
To0.76 MILES EAST OF FM 365
CSJ0739-02-161
Proj IDNH 1702(506)
Work TypeGR, BS, STR, PVMT
 
6.761108315367.9720786244.4319.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-17
Work Began09-26-17
Work Completed
Time Computed00-00-00
Contract Working Days770
Addl Days Granted0
Working Days Charged49
Percent Time Used6
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-161
ESSARY, HART & MACWILIAM,INC. (6.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.52)
PENHALL COMPANY (AUSTIN) (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.65)
BATTERSON,LLP (0.62)
SCOTT DERR PAINTING CO, LLC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
ANGEL BROTHERS ENTERPRISES, LTD. (0.91)
GULF COAST ASPHALT & PAVING, INC. (BAYTOWN) (0.00)
AMERICAN REMEDIATION OPTIONS, INC. (0.46)
HAYWOOD BAKER (0.02)
Contract #08173205
Totals108315367.971853176.1320786244.4319.1

CountyHARDIN
HighwayFM 421
From1.5 MI E OF FM 326
To4.1 MI W OF LUMBERTON
CSJ0813-03-043
Proj IDSTP 1702(114)HES
Work TypeSFTY TREAT FXD OBJ
 
6.5611375866.732198219.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-17
Work Began08-07-17
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged58
Percent Time Used116
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0813-03-043
AMERICAN REMEDIATION OPTIONS, INC. (4.98)
CRABTREE BARRICADE SYSTEMS, INC. (2.87)
TOTAL HIGHWAY MAINTENANCE, LLC (48.96)
WIDGEON CONSTRUCTION, INC. (2.72)
Contract #05173206
Totals1375866.73260748.632198219.7999.9

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-116
Proj IDSTP 2014(646)
Work TypeLANDSCAPE
 
3.428832522.01809876.2297.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-14
Work Began10-20-14
Work Completed
Time Computed00-00-00
Contract Working Days219
Addl Days Granted0
Working Days Charged198
Percent Time Used90
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
CLASSIC TEJAS CONSTRUCTION, INC. (3.46)
CRABTREE BARRICADE SYSTEMS, INC. (1.68)
Contract #05143219
Totals832522.010.00809876.2297.2

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-117
Proj IDSTP 1502(181)
Work TypeLANDSCAPE
 
1.000718877.79674604.0093.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-15
Work Began11-16-15
Work Completed
Time Computed08-20-15
Contract Working Days186
Addl Days Granted0
Working Days Charged100
Percent Time Used53
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-117
AMERICAN REMEDIATION OPTIONS, INC. (7.17)
CRABTREE BARRICADE SYSTEMS, INC. (1.28)
Contract #05153033
Totals718877.790.00674604.0093.8

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-118
Proj IDSTP 1602(155)
Work TypeLANDSCAPE
 
1.567706493.95678837.0096.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-16
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged29
Percent Time Used12
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-118
CRABTREE BARRICADE SYSTEMS, INC. (1.39)
HOLES INCORPORATED (0.00)
Contract #06163218
Totals706493.950.00678837.0096.0

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-119
Proj IDSTP 1702(116)
Work TypeLANDSCAPE
 
0.500624968.15537584.1686.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began10-09-17
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged32
Percent Time Used18
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-119
CRABTREE BARRICADE SYSTEMS, INC. (1.00)
Contract #05173019
Totals624968.1542107.00537584.1686.0

CountyNEWTON
HighwayCR
FromCR 4212 AT SABINE RIVER BRANCH
To(STR AA0507003)
CSJ0920-06-033
Proj IDBR 2017(547)
Work TypeSTR
 
0.100646004.20314924.2548.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began09-18-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted1
Working Days Charged44
Percent Time Used45
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-033
AMERICAN REMEDIATION OPTIONS, INC. (2.70)
CPAVE, INC. (1.08)
HOUSTON SAWING & DRILLING (0.33)
HUNTER DEMOLITION (6.03)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.82)
HEMPHILL WBE PILE DRIVING CO. (1.11)
ASHTON SAWING AND DRILLING LLC (0.92)
Contract #06173225
Totals646004.2081399.65314924.2548.7

CountyORANGE
HighwayCR
FromE ROUNDBUNCH RD AT COW BAYOU
To(STR AA2690006)
CSJ0920-30-077
Proj IDBR 2014(325)
Work TypeREHAB BRIDGE AND APPROACHES
 
0.26911399710.805515653.0048.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-30-17
Work Began07-06-17
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged109
Percent Time Used36
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-077
CRABTREE BARRICADE SYSTEMS, INC. (0.14)
HOUSTON SAWING & DRILLING (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.41)
MUSTANG COLT SERVICES, INC. (5.86)
PENINSULA MARINE, INC. (10.51)
CPAVE, INC. (0.05)
LONE STAR HIGHWAY PRODUCTS, INC. (5.10)
Contract #02173204
Totals11399710.80338892.205515653.0048.3

CountyORANGE
HighwayCS
FromOLD HWY 90 AT ANDERSON GULLY
To(STR C01835002)
CSJ0920-30-079
Proj IDBR 2014(324)
Work TypeSTR
 
0.100316837.10171067.7953.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-17
Work Began11-06-17
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged19
Percent Time Used38
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-079
CRABTREE BARRICADE SYSTEMS, INC. (2.61)
Contract #08173048
Totals316837.1021140.00171067.7953.9

CountyORANGE
HighwayCR
FromOLD HIGHWAY 90, S.OF I10 ACCESS RD.
ToEAST BANK OF NECHES RIVER
CSJ0920-30-081
Proj IDCM 2015(253)
Work TypeGR,BS,STR, PVMT,RR, SIGN
 
0.4208977087.388042044.7790.5
Work Order06-01-15
Work Began01-07-16
Work Completed
Time Computed06-17-15
Contract Working Days157
Addl Days Granted137
Working Days Charged372
Percent Time Used126
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-081
A. H. BECK FOUNDATION CO., INC. (14.83)
INDUS CONSTRUCTION, L.P. (1.81)
J & M CONTRACTING, COMPANY (0.88)
RIVER CITY RAILROAD TROLLEY & TRANSIT CONSULTANTS (1.60)
CRABTREE BARRICADE SYSTEMS, INC. (0.44)
AMERICAN REMEDIATION OPTIONS, INC. (1.11)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.90)
JA BRUMLEY ENTERPRISES, INC. DBA RAM INDUSTRIAL CONSTRUCTION (1.31)
Contract #10143215
Totals8977087.3850112.588042044.7790.5

CountyJEFFERSON
HighwayCS
FromON WASHINGTON BLVD, FROM LOMA LANE
ToIH-10
CSJ0920-38-187
Proj IDHP 2008(125)
Work TypePLANE, ACP
 
4.1001690881.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-187
AMERICAN REMEDIATION OPTIONS, INC. (1.58)
CPAVE, INC. (12.34)
DUSTROL, INC. (6.90)
CRABTREE BARRICADE SYSTEMS, INC. (2.53)
Contract #08173234
Totals1690881.520.000.000.0

CountyJEFFERSON
HighwayCS
FromLAUREL AVENUE AT DRAINAGE DITCH
To(STR B006-78-001)
CSJ0920-38-256
Proj IDBR 2017(503)
Work TypeSTR, BASE, CONC PAV
 
0.009225289.00208542.0192.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-17
Work Began09-18-17
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged54
Percent Time Used96
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-256
CRABTREE BARRICADE SYSTEMS, INC. (2.93)
Contract #07173239
Totals225289.0023876.58208542.0192.5

CountyCHAMBERS
HighwayVA
FromON FM 565 FROM FM 3360 TO FISHER RD
ToFM 3360 FROM CHERRY PT TO EAGLE PT
CSJ0920-39-023
Proj IDSTP 2017(422)TAPS
Work TypeGR, PVMT
 
1.733964954.45673159.8170.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged107
Percent Time Used118
Contractor(s)
DEZTEX INDUSTRIAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-39-023
PERFORMANCE SILT, LLC (1.57)
W. W. FOUNDATION DRILLING, LTD. (3.71)
Contract #12163037
Totals964954.45189469.59673159.8170.8

CountyJEFFERSON
HighwayFM 365
FromAT GROUND GULLY
To.
CSJ0932-02-053
Proj IDBR 1502(424)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.0361565852.571838267.8799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began10-26-16
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted46
Working Days Charged149
Percent Time Used110
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0932-02-053
AMERICAN REMEDIATION OPTIONS, INC. (3.62)
CRABTREE BARRICADE SYSTEMS, INC. (1.61)
DUSTROL, INC. (0.91)
HEMPHILL WBE PILE DRIVING CO. (5.03)
CPAVE, INC. (0.17)
HOUSTON SAWING & DRILLING (0.22)
Contract #08153263
Totals1565852.5749565.001838267.8799.9

CountyCHAMBERS
HighwayFM 1405
FromFM 565, SOUTH
To1.28 MILES SOUTH OF SH 99
CSJ1024-02-044
Proj IDSTP 1502(426)
Work TypeBS, PVMT, STRIPE
 
5.11610486302.4510240318.3997.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-16
Work Began03-14-16
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted15
Working Days Charged158
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1024-02-044
CRABTREE BARRICADE SYSTEMS, INC. (1.93)
WILLOW CITY SIGN & RAIL, INC. (1.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.47)
CPAVE, INC. (2.34)
Contract #08153059
Totals10486302.4592006.8510240318.3997.6

page 1 | page 2 | page 3