Monthly State Let Construction Report For Beaumont District As Of Apr 10, 2018 Page 2 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARDIN
HighwaySH 105
FromEAST OF SH 326, EAST
ToJEFFERSON C/L
CSJ0339-04-035
Proj IDNH 1702(265)
Work TypePAVEMENT REPAIR, MILL, OCST, PFC
 
7.2332678096.512648444.2698.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began08-14-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged33
Percent Time Used55
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0339-04-035
CRABTREE BARRICADE SYSTEMS, INC. (3.91)
C PAVE, INC. (3.17)
Contract #06173022
Totals2678096.510.002648444.2698.8

CountyJEFFERSON
HighwaySH 124
From.20 MILES N OF FM 364
To.20 MILES S OF FM 364
CSJ0368-03-033
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.3781126428.360.000.0
CountyJEFFERSON
HighwayFM 364
From900 FT S OF IH-10
ToSH 124
CSJ0786-01-083
Proj IDSTP 2018(376)
Work TypeGR,STR,BS,PVMT,STRIPE
 
0.2912397066.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days177
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0368-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173218
Totals3523494.740.000.000.0

CountyCHAMBERS
HighwaySH 146
From@IH-10
To.
CSJ0389-02-051
Proj IDSTP 2017(491)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200223068.55231317.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began10-23-17
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged46
Percent Time Used121
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-02-051
STRIPE LINES, INC. (1.62)
SOUTH RANGER CONSTRUCTION, INC. (4.01)
Contract #01173237
Totals223068.5515238.55231317.6099.9

CountyORANGE
HighwaySH 12
FromEVANGELINE LN.
ToSH 62
CSJ0499-03-058
Proj IDSTP 2018(565)HES
Work TypeINST CONT TURN LANE & RUMBLE STRIPS
 
6.1626632538.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-058
CRABTREE BARRICADE SYSTEMS, INC. (3.91)
AMERICAN REMEDIATION OPTIONS, INC. (2.00)
CPAVE, INC. (0.36)
DUSTROL, INC. (6.95)
PENHALL COMPANY (0.15)
Contract #02183203
Totals6632538.480.000.000.0

CountyCHAMBERS
HighwayIH 10
FromSH 146
To0.25 MI. E. OF SH 146 (WB FRONTAGE
CSJ0508-02-121
Proj IDSTP 2018(754)MM
Work TypeEXTEND WB TURN LANE
 
0.190235049.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-02-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183041
Totals235049.180.000.000.0

CountyCHAMBERS
HighwaySH 73
FromFM 1663, EAST
To0.02 MILES WEST OF JEFFERSON CO/L
CSJ0508-03-098
Proj IDSTP 2013(577)
Work TypeGR, BS, PAV, STRIPE
 
1.5634865959.510.000.0
CountyCHAMBERS
HighwaySH 73
From0.02 MILES WEST OF JEFFERSON CO/L
ToJEFFERSON CO/L
CSJ0508-03-099
Proj IDSTP 2018(755)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.021100971.770.000.0
CountyJEFFERSON
HighwaySH 73
FromCHAMBERS COUNTY LINE, EAST
To0.6 MILES EAST OF SH 124
CSJ0508-04-162
Proj IDSTP 2013(576)HES
Work TypeCONSTRUCT GRADE SEPARATION
 
0.85013780360.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days410
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-03-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183002
Totals18747291.340.000.000.0

CountyLIBERTY
HighwaySH 321
FromUPRR, SOUTH
ToFM 1960
CSJ0593-01-114
Proj IDSTP 1702(277)
Work TypeACP, STRIPE
 
3.1961050836.68103240.029.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days29
Addl Days Granted0
Working Days Charged15
Percent Time Used51
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-114
LONESTAR TRAFFIC SAFETY, LLC (0.10)
STRIPE-A-ZONE, INC. (0.41)
STRIPE LINES, INC. (4.55)
Contract #06173217
Totals1050836.680.00103240.029.8

CountyLIBERTY
HighwaySH 321
From4.5 MI. NORTH OF FM 686
To0.1 MI. SOUTH OF FM 686
CSJ0593-01-120
Proj IDSTP 2018(566)HES
Work TypeINST CONT TURN LANE & RUMBLE STRIPS
 
4.5015234742.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days208
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183022
Totals5234742.150.000.000.0

CountyLIBERTY
HighwaySH 321
FromSL 573
ToSH 105
CSJ0593-01-123
Proj IDC 593-1-123
Work TypeLEVEL-UP/OVERLAY
 
2.005845384.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0593-01-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183043
Totals845384.550.000.000.0

CountyHARDIN
HighwayFM 92
FromTYLER C/L
ToFM 418
CSJ0703-02-059
Proj IDSTP 2018(655)HESG
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
11.59419476.060.000.0
CountyTYLER
HighwayFM 1943
From8.3 MILES WEST OF FM 92
ToFM 92
CSJ1828-01-026
Proj IDSTP 2018(656)HESG
Work TypeCENTERLINE TEXTURING
 
8.30041824.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days12
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0703-02-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183016
Totals61300.140.000.000.0

CountyCHAMBERS
HighwayIH 10
FromSH 73, EAST
ToJEFFERSON CO. LINE
CSJ0739-01-039
Proj IDNH 1602(470)
Work TypeRECONST GR, STRS BS & PAV
 
3.11324138551.4210123745.8741.9
CountyJEFFERSON
HighwayIH 10
FromCHAMBERS CO/L, EAST
ToHAMSHIRE RD
CSJ0739-02-160
Proj IDNH 1602(470)
Work TypeGR, BS, STR, PVMT
 
2.10219031143.039934911.8752.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days696
Addl Days Granted23
Working Days Charged227
Percent Time Used31
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-039
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
CPAVE, INC. (0.24)
SCOTT DERR PAINTING CO, LLC (0.05)
MESA ROD BUSTERS, INC. (5.50)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.69)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.92)
WEST TEXAS RUMBLE STRIP (0.11)
ANGEL BROTHERS ENTERPRISES, LTD. (1.65)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INFRASTRUCTURE SERVICES, INC. (0.04)
AGGREGATE TECHNOLOGIES, INC. (0.17)
Contract #09163201
Totals43169694.45217120.8320058657.7446.4

CountyJEFFERSON
HighwayIH 10
From0.64 MILES WEST OF HAMSHIRE RD,EAST
To0.76 MILES EAST OF FM 365
CSJ0739-02-161
Proj IDNH 1702(506)
Work TypeGR, BS, STR, PVMT
 
6.761108315367.9722333708.2220.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-17
Work Began09-26-17
Work Completed
Time Computed00-00-00
Contract Working Days770
Addl Days Granted0
Working Days Charged89
Percent Time Used11
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0739-02-161
ESSARY, HART & MACWILIAM,INC. (6.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.52)
PENHALL COMPANY (AUSTIN) (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.65)
BATTERSON,LLP (0.62)
SCOTT DERR PAINTING CO, LLC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
ANGEL BROTHERS ENTERPRISES, LTD. (0.91)
GULF COAST ASPHALT & PAVING, INC. (BAYTOWN) (0.00)
AMERICAN REMEDIATION OPTIONS, INC. (0.46)
HAYWOOD BAKER (0.02)
Contract #08173205
Totals108315367.97742679.3822333708.2220.6

CountyLIBERTY
HighwayFM 787
FromFM 2518
ToFM 223
CSJ0813-01-101
Proj IDSTP 2018(756)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.853539803.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183022
Totals539803.000.000.000.0

CountyHARDIN
HighwayFM 421
From1.5 MI E OF FM 326
To4.1 MI W OF LUMBERTON
CSJ0813-03-043
Proj IDSTP 1702(114)HES
Work TypeSFTY TREAT FXD OBJ
 
6.5611375866.732395366.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-17
Work Began08-07-17
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged70
Percent Time Used140
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0813-03-043
AMERICAN REMEDIATION OPTIONS, INC. (4.98)
CRABTREE BARRICADE SYSTEMS, INC. (2.87)
TOTAL HIGHWAY MAINTENANCE, LLC (48.96)
WIDGEON CONSTRUCTION, INC. (2.72)
Contract #05173206
Totals1375866.7398438.162395366.1499.9

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-117
Proj IDSTP 1502(181)
Work TypeLANDSCAPE
 
1.000718877.79676854.0094.1
Work Order07-20-15
Work Began11-16-15
Work Completed
Time Computed08-20-15
Contract Working Days186
Addl Days Granted0
Working Days Charged100
Percent Time Used53
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-117
AMERICAN REMEDIATION OPTIONS, INC. (7.17)
CRABTREE BARRICADE SYSTEMS, INC. (1.28)
Contract #05153033
Totals718877.79500.00676854.0094.1

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-118
Proj IDSTP 1602(155)
Work TypeLANDSCAPE
 
1.567706493.95679587.0096.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-16
Work Began10-01-16
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged29
Percent Time Used12
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-118
CRABTREE BARRICADE SYSTEMS, INC. (1.39)
HOLES INCORPORATED (0.00)
Contract #06163218
Totals706493.950.00679587.0096.1

CountyJEFFERSON
HighwayVA
FromDISTRICTWIDE
To.
CSJ0920-00-119
Proj IDSTP 1702(116)
Work TypeLANDSCAPE
 
0.500624968.15579698.1692.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began10-09-17
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged32
Percent Time Used18
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-119
CRABTREE BARRICADE SYSTEMS, INC. (1.00)
Contract #05173019
Totals624968.153500.00579698.1692.7

CountyNEWTON
HighwayCR
FromCR 4212 AT SABINE RIVER BRANCH
To(STR AA0507003)
CSJ0920-06-033
Proj IDBR 2017(547)
Work TypeSTR
 
0.100646004.20421432.1565.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began09-18-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted1
Working Days Charged78
Percent Time Used80
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-033
AMERICAN REMEDIATION OPTIONS, INC. (2.70)
CPAVE, INC. (1.08)
HOUSTON SAWING & DRILLING (0.33)
HUNTER DEMOLITION (6.03)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.82)
HEMPHILL WBE PILE DRIVING CO. (1.11)
ASHTON SAWING AND DRILLING LLC (0.92)
Contract #06173225
Totals646004.2017213.90421432.1565.2

CountyORANGE
HighwayCR
FromE ROUNDBUNCH RD AT COW BAYOU
To(STR AA2690006)
CSJ0920-30-077
Proj IDBR 2014(325)
Work TypeREHAB BRIDGE AND APPROACHES
 
0.26911399710.806679542.5058.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-30-17
Work Began07-06-17
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged170
Percent Time Used56
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-077
CRABTREE BARRICADE SYSTEMS, INC. (0.14)
HOUSTON SAWING & DRILLING (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.41)
MUSTANG COLT SERVICES, INC. (5.86)
PENINSULA MARINE, INC. (10.51)
CPAVE, INC. (0.05)
LONE STAR HIGHWAY PRODUCTS, INC. (5.10)
Contract #02173204
Totals11399710.80289328.006679542.5058.5

CountyORANGE
HighwayCS
FromOLD HWY 90 AT ANDERSON GULLY
To(STR C01835002)
CSJ0920-30-079
Proj IDBR 2014(324)
Work TypeSTR
 
0.100316837.10294071.5792.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-17
Work Began11-06-17
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted2
Working Days Charged35
Percent Time Used67
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-079
CRABTREE BARRICADE SYSTEMS, INC. (2.61)
OLDCASTLE MATERIALS TEXAS, INC. (0.00)
Contract #08173048
Totals316837.1039869.76294071.5792.8

page 1 | page 2 | page 3