Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BRAZOS |
Highway | SH0006 |
From | S HEADER OF SH 40 |
To | CR 317 |
CSJ | 6452-83-001 |
Proj ID | RMC - 645283001 |
Work Type | THERMOPLASTIC PAVEMENT MARKINGS |
|
| 0.010 | 421204.29 | | 916205.00 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-08-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 20 |
Addl Days Granted | 12 |
Working Days Charged | 23 |
Percent Time Used | 71 |
Contractor(s) |
INTERSTATE BARRICADES & MARKINGS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6452-83-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234007 |
| Totals | 421204.29 | 491042.69 | 916205.00 | 99.9 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-43-001 |
Proj ID | RMC - 645643001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 440007.00 | | 24396.00 | 5.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-06-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 55 |
Percent Time Used | 15 |
Contractor(s) |
T&L CLEANING SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-43-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234006 |
| Totals | 440007.00 | 5639.00 | 24396.00 | 5.5 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6457-61-001 |
Proj ID | MMC - 645761001 |
Work Type | HOT MIX |
|
| 0.010 | 519900.00 | | 12367.00 | 2.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 30 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234012 |
| Totals | 519900.00 | 12367.00 | 12367.00 | 2.3 |
|
County | GRIMES |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6458-83-001 |
Proj ID | RMC - 645883001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 296255.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6458-83-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244005 |
| Totals | 296255.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-15-001 |
Proj ID | RMC - 645915001 |
Work Type | THERMOPLASTIC PAVEMENT MARKINGS |
|
| 0.010 | 3575281.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 14 |
Contractor(s) |
STRIPE LINES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234014 |
| Totals | 3575281.00 | 0.00 | 0.00 | 0.0 |
|
County | MILAM |
Highway | FM0486 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-21-001 |
Proj ID | RMC - 645921001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 226589.04 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 14 |
Contractor(s) |
ABESCAPE LANDSCAPING, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234204 |
| Totals | 226589.04 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-55-001 |
Proj ID | MMC - 645955001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 292965.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 46 |
Percent Time Used | 25 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-55-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234205 |
| Totals | 292965.00 | 0.00 | 0.00 | 0.0 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-57-001 |
Proj ID | MMC - 645957001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 418245.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 30 |
Contractor(s) |
MARTIN MARIETTA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234015 |
| Totals | 418245.00 | 0.00 | 0.00 | 0.0 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-67-001 |
Proj ID | MMC - 646067001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 281900.00 | | 33827.21 | 11.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 30 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-67-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234016 |
| Totals | 281900.00 | 33827.21 | 33827.21 | 11.9 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-95-001 |
Proj ID | MMC - 646095001 |
Work Type | HYDRAULIC CEMENT |
|
| 0.010 | 400399.20 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-09-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 12 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244007 |
| Totals | 400399.20 | 0.00 | 0.00 | 0.0 |
|
County | BURLESON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6462-10-001 |
Proj ID | RMC - 646210001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 285360.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-05-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-10-001 TEAL ARROW LLC (0.00)
|
Contract # | 02244227 |
| Totals | 285360.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6462-12-001 |
Proj ID | RMC - 646212001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 491400.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
REPUBLIC TRAFFIC SAFETY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6462-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244030 |
| Totals | 491400.00 | 0.00 | 0.00 | 0.0 |
|