Monthly State Let Construction Report For Corpus Christi District As Of Sep 18, 2019 Page 3 Of 4

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwaySH 358
FromIH 37
ToWEST POINT RD.
CSJ0617-01-196
Proj IDNH 2018(843)
Work TypeNOVACHIP ROADWAY
 
4.1007489379.237116807.4595.9
Work Order06-22-18
Work Began08-28-18
Work Completed
Time Computed07-22-18
Contract Working Days117
Addl Days Granted2
Working Days Charged180
Percent Time Used151
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-196
AREA WIDE PROTECTIVE, INC. (7.82)
ANGEL BROTHERS ENTERPRISES, LTD. (11.04)
PRIMATE CONSTRUCTION, INC. (0.67)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.95)
HIGHWAY BARRICADES AND SERVICES, LLC (3.17)
PERFORMANCE EQUIPMENT SERVICE (0.72)
JHABORES CONSTRUCTION CO, INC. (0.69)
WEBBER BARRIER SERVICES, LLC. (2.12)
VIDEO PIPELINE INSPECTIONS, INC. (0.02)
THE LEVY COMPANY, INC. (8.07)
SOUTH TEXAS SOIL SERVICES, L.L.C. (7.87)
Contract #05183238
Totals7489379.232576365.037116807.4595.9

CountyKARNES
HighwayFM 81
FromON FM 81 AT CHICKEN CREEK STR2
ToAPPROX. 7.8 MI SE OF SH 72
CSJ0691-01-035
Proj IDC 691-1-35
Work TypeWIDEN OR REPLACE STRUCTURE
 
0.3264236890.732536870.1259.8
Work Order08-15-18
Work Began09-24-18
Work Completed
Time Computed09-14-18
Contract Working Days302
Addl Days Granted0
Working Days Charged176
Percent Time Used58
Contractor(s)
LISKA CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-035
SHINN AND GREGORY, INC. (4.77)
FLASHER EQUIPMENT COMPANY (1.15)
MCL CONTRACTING, LLC (0.46)
TIERRA LEASE SERVICE, LLC (2.90)
BEAVER BOYS SERVICES (5.19)
Contract #07183035
Totals4236890.73151386.232536870.1259.8

CountyKARNES
HighwayFM 81
FromINTERSECTION FM885/LYONS ST.
ToGOLIAD COUNTY LINE
CSJ0691-01-042
Proj IDSTP 2019(463)
Work TypeREHAB AND WIDEN ROADWAY
 
8.6005423457.23255773.174.7
CountyGOLIAD
HighwayFM 81
FromKARNES COUNTY LINE
ToSH 239
CSJ0691-02-015
Proj IDSTP 2019(463)
Work TypeREHAB AND WIDEN ROADWAY
 
3.0942470600.78453286.7618.3
Work Order02-20-19
Work Began04-15-19
Work Completed
Time Computed03-01-19
Contract Working Days226
Addl Days Granted0
Working Days Charged79
Percent Time Used34
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-042
DEPENDABLE FENCE & WELDING CO. INC. (0.60)
HIGHWAY BARRICADES AND SERVICES, LLC (0.59)
J & M CONTRACTING, COMPANY (10.52)
MURRAY CONSTRUCTION (0.66)
FLASHER EQUIPMENT COMPANY (1.91)
LONE STAR EROSION CONTROL (1.78)
BEAVER BOYS SERVICES (0.62)
Contract #01193041
Totals7894058.01128475.27709059.938.9

CountyREFUGIO
HighwayFM 136
FromAT COPANO BAY BRIDGE
To.
CSJ0738-01-001
Proj IDBR 2020(039)
Work TypeBRIDGE MAINTENANCE
 
0.398945880.000.000.0
CountySAN PATRICIO
HighwayFM 3512
FromAT MCCAMBELL SLOUGH BRIDGE
To.
CSJ3578-01-005
Proj IDBR 2020(039)
Work TypeBRIDGE MAINTENANCE
 
0.071191078.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0738-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193019
Totals1136958.000.000.000.0

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATION IN CC DISTRICT
To.
CSJ0916-00-086
Proj IDSTP 2018(844)
Work TypeDISTRICT WIDE SIGN REPLACEMENT
 
0.1001030468.53586332.3456.8
CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CC DISTRICT
ToON FM3035,FM1684,FM1257 ETC.
CSJ0916-00-218
Proj IDC 916-00-218
Work TypeDISTRICT WIDE SIGN REPLACEMENT
 
0.100101860.00104480.0099.9
Work Order06-14-18
Work Began03-25-19
Work Completed
Time Computed07-14-18
Contract Working Days153
Addl Days Granted0
Working Days Charged100
Percent Time Used65
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183223
Totals1132328.5355041.85690812.3461.0

CountyNUECES
HighwayVA
FromVARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-212
Proj IDSTP 2019(673)
Work TypeSIGN REPLACEMENT
 
0.1001847391.50168493.009.1
Work Order04-25-19
Work Began00-00-00
Work Completed
Time Computed05-24-19
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-212
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193229
Totals1847391.50168493.00168493.009.1

CountyNUECES
HighwayVA
FromVARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-215
Proj IDSTP 2019(780)
Work TypePAVEMENT MARKING AND MARKERS
 
0.1002803253.0926493.800.9
Work Order05-21-19
Work Began06-17-19
Work Completed
Time Computed06-03-19
Contract Working Days80
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-215
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193232
Totals2803253.090.0026493.800.9

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-221
Proj IDSTP 1902(109)
Work TypePED
 
2.0002575368.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days229
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLORE EQUIPMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-221
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193023
Totals2575368.870.000.000.0

CountyGOLIAD
HighwayCR
FromON DANFORTH RD(CR 171)_AT MILBY CR.
To6.3 MI N. OF FM 622
CSJ0916-26-019
Proj IDBR 2018(845)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100518768.35169892.6032.7
Work Order05-14-19
Work Began08-19-19
Work Completed
Time Computed06-01-19
Contract Working Days68
Addl Days Granted0
Working Days Charged8
Percent Time Used11
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0916-26-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193035
Totals518768.35169892.60169892.6032.7

CountyNUECES
HighwayCS
FromGLAZE BROOK
ToTEXAN TRAIL
CSJ0916-35-184
Proj IDSTP 2016(710)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
12.1413720169.052210304.3059.4
Work Order10-16-18
Work Began02-25-19
Work Completed
Time Computed11-15-18
Contract Working Days304
Addl Days Granted0
Working Days Charged135
Percent Time Used44
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-184
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183044
Totals3720169.05141051.742210304.3059.4

CountyNUECES
HighwayFM 624
FromCR 77
ToWILDCAT RD.
CSJ0989-02-048
Proj IDSTP 2016(719)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
4.705930860.74154424.3216.5
CountyNUECES
HighwaySH 357
From.2 MI W OF GREEN WOOD
To.2 MI E OF RODD FIELD ROAD
CSJ1069-01-035
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS & INTERCONN
 
7.5001565436.591368673.2087.4
CountyNUECES
HighwaySH 357
From1.7 MI S OF SH 358
To.3 MI S OF SH 358
CSJ1069-01-036
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
1.400498081.7399773.2420.0
CountyNUECES
HighwayFM 43
From.8 MI S OF SH 357
To.2 MI S OF SH 358
CSJ1557-01-042
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTER. SIG
 
2.377517428.2919777.493.8
Work Order03-18-19
Work Began07-08-19
Work Completed
Time Computed04-18-19
Contract Working Days275
Addl Days Granted0
Working Days Charged38
Percent Time Used13
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0989-02-048
HIGHWAY BARRICADES AND SERVICES, LLC (0.21)
AREA WIDE PROTECTIVE, INC. (1.01)
BATTEN DRILLING, INC. (2.32)
D&S TEXAS ICON CONSTRUCTION (1.30)
Contract #02193008
Totals3511807.35380086.421642648.2546.7

CountyJIM WELLS
HighwayFM 738
FromFM 534
To2.25 MI S OF FM 534
CSJ1087-01-014
Proj IDSTP 2020(040)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2521150495.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1087-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193224
Totals1150495.070.000.000.0

CountyNUECES
HighwayFM 892
FromFM 2826
ToFM 665
CSJ1088-04-025
Proj IDSTP 1902(110)
Work TypeRER
 
4.6603732484.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days151
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1088-04-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193237
Totals3732484.330.000.000.0

CountyLIVE OAK
HighwayFM 1358
FromIH 37
ToAPPROX 1.0 MI EAST OF IH 37
CSJ1206-01-018
Proj IDBR 1502(580)
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.1132572494.782493630.9096.9
Work Order06-14-18
Work Began08-01-18
Work Completed
Time Computed07-14-18
Contract Working Days202
Addl Days Granted0
Working Days Charged192
Percent Time Used95
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1206-01-018
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.74)
HIGHWAY BARRICADES AND SERVICES, LLC (0.31)
PRIMATE CONSTRUCTION, INC. (0.20)
AREA WIDE PROTECTIVE, INC. (0.34)
ROADWAY SPECIALTIES, INC. (3.38)
FLASHER LIMITED (0.29)
BOWMAN ENGINEERING & CONSULTING, INC. (0.34)
MCL CONTRACTING, LLC (0.84)
PENHALL COMPANY (0.19)
Contract #05183030
Totals2572494.7874341.542493630.9096.9

CountyREFUGIO
HighwayFM 1360
FromBOENIG RD.
ToFM 629
CSJ1423-01-034
Proj IDSTP 2018(978)HES
Work TypeSAFETY TRT FIXED OBJ, WIDEN ROADWAY
 
3.0501520495.771813158.6899.9
Work Order07-09-18
Work Began08-20-18
Work Completed
Time Computed08-20-18
Contract Working Days108
Addl Days Granted64
Working Days Charged101
Percent Time Used58
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1423-01-034
FUQUAY, INC. (0.88)
HIGHWAY BARRICADES AND SERVICES, LLC (3.87)
MURRAY CONSTRUCTION (0.26)
DEPENDABLE FENCE & WELDING CO. INC. (4.97)
STAFF CONCRETE (19.63)
REXCO CONSTRUCTION SERVICES, INC. (0.62)
Contract #06183237
Totals1520495.77399213.841813158.6899.9

CountyNUECES
HighwayFM 70
FromFM 1833
ToSH 44
CSJ1558-01-019
Proj IDC 1558-1-19
Work TypeCEMENT TRT BASE, SPOT BASE REP&SEAL
 
10.2594592254.65229470.004.9
Work Order06-21-19
Work Began08-12-19
Work Completed
Time Computed07-01-19
Contract Working Days180
Addl Days Granted0
Working Days Charged14
Percent Time Used7
Contractor(s)
TIERRA LEASE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1558-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193018
Totals4592254.65229470.00229470.004.9

CountyLIVE OAK
HighwayFM 2049
FromSH 72
ToIH 37
CSJ1959-01-014
Proj IDSTP 1702(645)
Work TypeREHAB AND WIDEN
 
10.4564076441.683961078.1698.7
CountyLIVE OAK
HighwayFM 3192
FromFM 2049
ToFM 882
CSJ3297-01-007
Proj IDSTP 1702(646)
Work TypeREHAB AND WIDEN
 
6.1171949404.382143819.9599.9
Work Order09-21-17
Work Began01-02-18
Work Completed
Time Computed10-21-17
Contract Working Days202
Addl Days Granted3
Working Days Charged261
Percent Time Used127
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1959-01-014
FLASHER EQUIPMENT COMPANY (1.74)
LONE STAR EROSION CONTROL (0.35)
RELMCO, INC. (15.93)
ROADWAY SPECIALTIES, INC. (1.04)
MURRAY CONSTRUCTION (0.95)
EGGEMEYER LAND CLEARING, LLC (1.06)
Contract #08173218
Totals6025846.0662571.046104898.1199.9

CountyNUECES
HighwaySH 361
FromAT FERRY LANDINGS IN PORT ARANSAS
To.
CSJ2263-02-089
Proj IDSTP 1902(242)
Work TypeWNF
 
8996758.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days377
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193061
Totals8996758.500.000.000.0

CountyNUECES
HighwaySH 361
FromAT THE PORT ARANSAS FERRY LANDING
To.
CSJ2263-02-096
Proj IDSTP 2017(157)
Work TypeCONSTRUCT NEW 28 CAR FERRY BOAT
 
0.1008195000.008194810.0099.9
CountyNUECES
HighwaySH 361
FromAT THE PORT ARANSAS FERRY LANDING
To.
CSJ2263-02-097
Proj IDFT 2263-2-97
Work TypeCONSTRUCT NEW 28 CAR FERRY BOAT
 
0.1008195000.007965540.0097.2
Work Order11-21-16
Work Began12-29-16
Work Completed
Time Computed12-01-16
Contract Working Days396
Addl Days Granted90
Working Days Charged444
Percent Time Used91
Contractor(s)
SOUTHWEST SHIPYARD, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-096
B & R SANDBLASTING & COATING, INC. (6.73)
RIO MARINE, INC. (6.73)
HUTCO (6.46)
MECHANICAL CONTRACTING SERVICES, INC. (1.43)
Contract #10163203
Totals16390000.000.0016160350.0098.5

CountyNUECES
HighwaySH 361
From370' W. OF SEA MIST DR (CONTROL BK)
To.6 MI E OF GIWW
CSJ2263-02-098
Proj IDBR 2019(165)
Work TypeBRIDGE REHABILITATION
 
1.0004671605.003444083.9373.7
Work Order12-17-18
Work Began03-25-19
Work Completed
Time Computed01-16-19
Contract Working Days159
Addl Days Granted34
Working Days Charged105
Percent Time Used54
Contractor(s)
SOUTHERN ROAD & BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2263-02-098
MOBILE ENTERPRISES, INC. (7.76)
ALAMO BRIDGE AND ROAD, LLC (13.86)
HIGHWAY BARRICADES AND SERVICES, LLC (0.95)
Contract #11183023
Totals4671605.00717931.443444083.9373.7