Monthly State Let Construction Report For Corpus Christi District As Of Jan 16, 2020 Page 3 Of 4

Last Update: Friday, January 17, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKLEBERG
HighwaySH 141
FromON SH 141 FROM BU77-V INTER.
ToUS 77
CSJ0383-04-061
Proj IDSTP 1802(405)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.917773864.23886412.7199.9
CountyNUECES
HighwayVA
FromAT VARIOUS LOCATION IN
ToKLEBERG & JIM WELLS COUNTIES
CSJ0916-00-080
Proj IDSTP 1802(405)
Work TypeCONSTRUCT CURB RAMPS
 
0.1002080518.382611893.7699.9
CountyJIM WELLS
HighwayFM 2508
FromUS 281
To3RD ST. IN BEN BOLT
CSJ2429-01-012
Proj IDSTP 1802(405)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.271232628.31222248.4295.5
Work Order08-16-18
Work Began11-20-18
Work Completed
Time Computed09-17-18
Contract Working Days174
Addl Days Granted0
Working Days Charged165
Percent Time Used94
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0383-04-061
HIGHWAY BARRICADES AND SERVICES, LLC (0.79)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.51)
SOIL-TECH, INC. (0.96)
Contract #07183045
Totals3087010.920.003720554.8999.9

CountyGOLIAD
HighwaySH 239
FromN INTERS. OF FM 2043
ToBAKER RD.
CSJ0516-02-030
Proj IDC 516-2-30
Work TypeREHABILITATION OF EXISTING ROAD
 
5.19011249526.451102093.499.7
Work Order07-16-19
Work Began08-19-19
Work Completed
Time Computed08-01-19
Contract Working Days219
Addl Days Granted15
Working Days Charged70
Percent Time Used29
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0516-02-030
FLASHER EQUIPMENT COMPANY (0.57)
H J HENKE, LLC (0.65)
HIGHWAY BARRICADES AND SERVICES, LLC (0.23)
RELMCO, INC. (21.17)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
BLACKTOP INDUSTRIES LLC (0.80)
LONE STAR EROSION CONTROL (1.17)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.12)
BOWMAN ENGINEERING & CONSULTING, INC. (0.09)
Contract #06193020
Totals11249526.45125909.381102093.499.7

CountyARANSAS
HighwayPR 13B
FromON PR 13B .757 MI S OF PR13A
To1.263 MI S OF PR13A INTERS.
CSJ0585-01-016
Proj IDER 1802(687)
Work TypeEMERGENCY RELIEF PROJECTS
 
0.532540816.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0585-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203029
Totals540816.300.000.000.0

CountyNUECES
HighwaySH 358
FromNILE STREET
ToAYERS STREET
CSJ0617-01-170
Proj IDNH 1602(259)
Work TypeGRADE,BASE,SURF,STRS
 
3.99142716098.6723257420.9054.4
CountyNUECES
HighwaySH 358
From.2 MI N OF LEOPARD
To.2 MI E OF FLOUR BLUFF DRIVE
CSJ0617-01-189
Proj IDSTP 1602(260)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
14.9733940168.901253245.4031.8
CountyNUECES
HighwaySH 358
From180 FT W OF DODDS ST.
ToCLARE DR.
CSJ0617-01-191
Proj IDSTP 1602(261)HES
Work TypeIMPROVE MEDIAN BARR, SFT LIGHTING
 
4.8603158509.10223402.007.0
CountyNUECES
HighwayPR 22
FromINTERSECTION OF SH 358
To0.1 MI E OF WALDRON RD.
CSJ0617-02-071
Proj IDSTP 1602(406)HES
Work TypeIMPROVE TRAFFIC SIGNAL & INTER SIGN
 
0.670145374.80207.000.1
Work Order10-25-17
Work Began01-15-18
Work Completed
Time Computed12-24-17
Contract Working Days871
Addl Days Granted77
Working Days Charged402
Percent Time Used42
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-170
PERFORMANCE EQUIPMENT SERVICE (0.41)
SOIL-TECH, INC. (0.21)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (9.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.23)
TAHOE TRUCKING, INC. (0.86)
ANGEL BROTHERS ENTERPRISES, LTD. (1.49)
D & C CONCRETE CUTTING, INC. (0.00)
FARR FOUNDATION, INC. (3.19)
SCR CONSTRUCTION CO., INC. (0.24)
LIGHT IT UP ELECTRIC (1.62)
W. W. FOUNDATION DRILLING, LTD. (1.25)
WOODSTOCK TREE SURGEONS (0.01)
ATS DRILLING, INC. (0.25)
G & E ESCOBEDO CONSTRUCTION, INC. (0.38)
ACME READY MIX LTD., LLP (6.84)
SCOTT DERR PAINTING CO, LLC (0.10)
WEBBER BARRIER SERVICES, LLC. (1.92)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
HB FARMER FOUNDATION, LLC (1.66)
A.Z. REBAR CONSTRUCTION, INC. (0.09)
MUNOZ FOUNDATION DRILLING, INC. (0.12)
CAMACHO DEMOLITION, LLC (0.05)
SOIL TECH ADVANCE INC. (0.14)
Contract #05173002
Totals49960151.47743722.2424734275.3049.5

CountyNUECES
HighwaySH 358
FromIH 37
ToWEST POINT RD.
CSJ0617-01-196
Proj IDNH 2018(843)
Work TypeNOVACHIP ROADWAY
 
4.1007489379.237716876.5699.9
Work Order06-22-18
Work Began08-28-18
Work Completed
Time Computed07-22-18
Contract Working Days117
Addl Days Granted2
Working Days Charged207
Percent Time Used173
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-196
AREA WIDE PROTECTIVE, INC. (7.82)
ANGEL BROTHERS ENTERPRISES, LTD. (11.04)
PRIMATE CONSTRUCTION, INC. (0.67)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.95)
HIGHWAY BARRICADES AND SERVICES, LLC (3.17)
PERFORMANCE EQUIPMENT SERVICE (0.72)
JHABORES CONSTRUCTION CO, INC. (0.69)
WEBBER BARRIER SERVICES, LLC. (2.12)
VIDEO PIPELINE INSPECTIONS, INC. (0.02)
THE LEVY COMPANY, INC. (8.07)
SOUTH TEXAS SOIL SERVICES, L.L.C. (7.87)
Contract #05183238
Totals7489379.23158435.907716876.5699.9

CountyKARNES
HighwayFM 81
FromON FM 81 AT CHICKEN CREEK STR2
ToAPPROX. 7.8 MI SE OF SH 72
CSJ0691-01-035
Proj IDC 691-1-35
Work TypeWIDEN OR REPLACE STRUCTURE
 
0.3264236890.733310428.6978.1
Work Order08-15-18
Work Began09-24-18
Work Completed
Time Computed09-14-18
Contract Working Days302
Addl Days Granted0
Working Days Charged237
Percent Time Used78
Contractor(s)
LISKA CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-035
SHINN AND GREGORY, INC. (4.77)
FLASHER EQUIPMENT COMPANY (1.15)
MCL CONTRACTING, LLC (0.46)
TIERRA LEASE SERVICE, LLC (2.90)
BEAVER BOYS SERVICES (5.19)
Contract #07183035
Totals4236890.73122814.873310428.6978.1

CountyKARNES
HighwayFM 81
FromINTERSECTION FM885/LYONS ST.
ToGOLIAD COUNTY LINE
CSJ0691-01-042
Proj IDSTP 2019(463)
Work TypeREHAB AND WIDEN ROADWAY
 
8.6005423457.23643827.9311.8
CountyGOLIAD
HighwayFM 81
FromKARNES COUNTY LINE
ToSH 239
CSJ0691-02-015
Proj IDSTP 2019(463)
Work TypeREHAB AND WIDEN ROADWAY
 
3.0942470600.781524130.6361.6
Work Order02-20-19
Work Began04-15-19
Work Completed
Time Computed03-01-19
Contract Working Days226
Addl Days Granted0
Working Days Charged143
Percent Time Used63
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0691-01-042
DEPENDABLE FENCE & WELDING CO. INC. (0.60)
HIGHWAY BARRICADES AND SERVICES, LLC (0.59)
J & M CONTRACTING, COMPANY (10.52)
MURRAY CONSTRUCTION (0.66)
FLASHER EQUIPMENT COMPANY (1.91)
LONE STAR EROSION CONTROL (1.78)
BEAVER BOYS SERVICES (0.62)
Contract #01193041
Totals7894058.01808450.432167958.5627.4

CountyREFUGIO
HighwayFM 136
FromAT COPANO BAY BRIDGE
To.
CSJ0738-01-001
Proj IDBR 2020(039)
Work TypeBRIDGE MAINTENANCE
 
0.398945880.000.000.0
CountySAN PATRICIO
HighwayFM 3512
FromAT MCCAMBELL SLOUGH BRIDGE
To.
CSJ3578-01-005
Proj IDBR 2020(039)
Work TypeBRIDGE MAINTENANCE
 
0.071191078.000.000.0
Work Order10-21-19
Work Began00-00-00
Work Completed
Time Computed11-01-19
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0738-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193019
Totals1136958.000.000.000.0

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATION IN CC DISTRICT
To.
CSJ0916-00-086
Proj IDSTP 2018(844)
Work TypeDISTRICT WIDE SIGN REPLACEMENT
 
0.1001030468.53725731.6670.5
CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CC DISTRICT
ToON FM3035,FM1684,FM1257 ETC.
CSJ0916-00-218
Proj IDC 916-00-218
Work TypeDISTRICT WIDE SIGN REPLACEMENT
 
0.100101860.00104480.0099.9
Work Order06-14-18
Work Began03-25-19
Work Completed
Time Computed07-14-18
Contract Working Days153
Addl Days Granted0
Working Days Charged155
Percent Time Used101
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183223
Totals1132328.5328071.48830211.6673.4

CountyNUECES
HighwayVA
FromVARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-212
Proj IDSTP 2019(673)
Work TypeSIGN REPLACEMENT
 
0.1001847391.50401985.3821.7
Work Order04-25-19
Work Began10-01-19
Work Completed
Time Computed05-24-19
Contract Working Days120
Addl Days Granted0
Working Days Charged56
Percent Time Used46
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-212
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193229
Totals1847391.5067301.10401985.3821.7

CountyNUECES
HighwayVA
FromVARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-215
Proj IDSTP 2019(780)
Work TypePAVEMENT MARKING AND MARKERS
 
0.1002803253.091767016.1963.0
Work Order05-21-19
Work Began06-17-19
Work Completed
Time Computed06-03-19
Contract Working Days80
Addl Days Granted0
Working Days Charged55
Percent Time Used68
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-215
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193232
Totals2803253.09491962.601767016.1963.0

CountyNUECES
HighwayVA
FromAT VARIOUS LOCATIONS IN CC DISTRICT
To.
CSJ0916-00-221
Proj IDSTP 1902(109)
Work TypePED
 
2.0002575368.87165337.006.4
Work Order09-16-19
Work Began11-04-19
Work Completed
Time Computed10-16-19
Contract Working Days229
Addl Days Granted0
Working Days Charged27
Percent Time Used11
Contractor(s)
CLORE EQUIPMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-221
SOIL TECH ADVANCE INC. (5.00)
HIGHWAY BARRICADES AND SERVICES, LLC (4.16)
Contract #07193023
Totals2575368.87161497.24165337.006.4

CountyGOLIAD
HighwayCR
FromON DANFORTH RD(CR 171)_AT MILBY CR.
To6.3 MI N. OF FM 622
CSJ0916-26-019
Proj IDBR 2018(845)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100518768.35446546.8886.0
Work Order05-14-19
Work Began08-19-19
Work Completed
Time Computed06-01-19
Contract Working Days68
Addl Days Granted0
Working Days Charged63
Percent Time Used92
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0916-26-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193035
Totals518768.3568440.00446546.8886.0

CountySAN PATRICIO
HighwayCS
FromAT VARIOUS LOCATIONS IN TAFT
ToON GREEN AVE. AND HARDING ST.
CSJ0916-28-073
Proj IDSTP 2019(801)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.800499231.800.000.0
Work Order11-20-19
Work Began00-00-00
Work Completed
Time Computed12-01-19
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0916-28-073
DIAMOND X CONTRACTING, INC (39.05)
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (10.79)
Contract #10193219
Totals499231.800.000.000.0

CountyNUECES
HighwayCS
FromGLAZE BROOK
ToTEXAN TRAIL
CSJ0916-35-184
Proj IDSTP 2016(710)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
12.1413720169.052864251.6476.9
Work Order10-16-18
Work Began02-25-19
Work Completed
Time Computed11-15-18
Contract Working Days304
Addl Days Granted0
Working Days Charged204
Percent Time Used67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-35-184
USA AMTECH, INC. (0.85)
HIGHWAY BARRICADES AND SERVICES, LLC (0.25)
EPIC ENERGY SERVICES LLC (0.37)
Contract #08183044
Totals3720169.05105768.522864251.6476.9

CountyNUECES
HighwayFM 624
FromCR 77
ToWILDCAT RD.
CSJ0989-02-048
Proj IDSTP 2016(719)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
4.705930860.74252345.7527.1
CountyNUECES
HighwaySH 357
From.2 MI W OF GREEN WOOD
To.2 MI E OF RODD FIELD ROAD
CSJ1069-01-035
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS & INTERCONN
 
7.5001565436.591771879.2499.9
CountyNUECES
HighwaySH 357
From1.7 MI S OF SH 358
To.3 MI S OF SH 358
CSJ1069-01-036
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTERC SIG
 
1.400498081.73117946.4923.6
CountyNUECES
HighwayFM 43
From.8 MI S OF SH 357
To.2 MI S OF SH 358
CSJ1557-01-042
Proj IDSTP 2019(572)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTER. SIG
 
2.377517428.29134729.9126.0
Work Order03-18-19
Work Began07-08-19
Work Completed
Time Computed04-18-19
Contract Working Days275
Addl Days Granted0
Working Days Charged104
Percent Time Used37
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0989-02-048
HIGHWAY BARRICADES AND SERVICES, LLC (0.21)
AREA WIDE PROTECTIVE, INC. (1.01)
BATTEN DRILLING, INC. (2.32)
D&S TEXAS ICON CONSTRUCTION (1.30)
TX DOWN UNDER CONSTRUCTION, LLC (0.84)
Contract #02193008
Totals3511807.35290376.542276901.3964.8

CountyJIM WELLS
HighwayFM 2044
FromROSITA CREEK BRIDGE STR 1 ON FM 204
To4.0 MI N OF SH 44
CSJ1086-01-019
Proj IDBR 2020(466)
Work TypeBRIDGE REPLACEMENT
 
0.070750501.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1086-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203026
Totals750501.860.000.000.0

CountyJIM WELLS
HighwayFM 738
FromFM 534
To2.25 MI S OF FM 534
CSJ1087-01-014
Proj IDSTP 2020(040)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2521150495.07140377.6012.2
Work Order10-21-19
Work Began12-02-19
Work Completed
Time Computed11-01-19
Contract Working Days68
Addl Days Granted0
Working Days Charged7
Percent Time Used10
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1087-01-014
HIGHWAY BARRICADES AND SERVICES, LLC (4.44)
FLASHER EQUIPMENT COMPANY (3.64)
MALDONADO-BURKETT, LLP (4.84)
H J HENKE, LLC (2.54)
SOIL TECH ADVANCE INC. (0.35)
Contract #09193224
Totals1150495.07130269.23140377.6012.2

CountyNUECES
HighwayFM 892
FromFM 2826
ToFM 665
CSJ1088-04-025
Proj IDSTP 1902(110)
Work TypeRER
 
4.6603732484.33217724.595.8
Work Order08-16-19
Work Began10-14-19
Work Completed
Time Computed10-01-19
Contract Working Days151
Addl Days Granted0
Working Days Charged25
Percent Time Used16
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1088-04-025
HIGHWAY BARRICADES AND SERVICES, LLC (2.98)
LONE STAR EROSION CONTROL (0.32)
Contract #07193237
Totals3732484.33197063.19217724.595.8

CountyBEE
HighwayFM 797
From4.06 MI W OF FM 888
To0.4 MI W OF FM 888
CSJ1119-01-013
Proj IDSTP 2020(448)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.7001364407.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIERRA LEASE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1119-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203208
Totals1364407.900.000.000.0