Monthly State Let Maintenance Report For Houston District As Of Aug 23, 2019 Page 1 Of 9

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
Highway0000000
From6810 OLD KATY ROAD, HOUTSON, TX. 77024
To6810 OLD KATY ROAD, HOUTSON, TX. 77024
CSJ4704-01-333
Proj IDCBC - 470401327
Work TypeADDITION TO FACILITY
 
0.0011353000.001295133.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-14
Work Began07-18-14
Work Completed
Time Computed07-18-14
Contract Working Days240
Addl Days Granted12
Working Days Charged252
Percent Time Used100
Contractor(s)
CONSTRUCTION LTD
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-333
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144036
Totals1353000.000.001295133.1099.9

CountyGALVESTON
HighwaySH0087
FromGALVESTON FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6195-11-001
Proj IDEMC - 619511001
Work TypeEMERGENCY DOLPHIN REPAIRS
 
1.0002872775.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06091240
Totals2872775.000.000.000.0

CountyHARRIS
HighwayIH0045
FromSH 87
ToWALKER/MONTGOMERY COUNTY LINE
CSJ6236-65-001
Proj IDRMC - 623665001
Work TypeROUTINE MAINTENANCE OF IH 45
 
100.81026974243.6725845488.9395.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days1,826
Addl Days Granted0
Working Days Charged1,825
Percent Time Used99
Contractor(s)
TRANSFIELD SERVICES INFRASTRUCTURE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6236-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06124003
Totals26974243.670.0025845488.9395.8

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN DISTRICT 12
ToVARIOUS HIGHWAYS IN DISTRICT 12
CSJ6253-64-001
Proj IDRMC - 625364001
Work TypeCALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.0012484500.0049690.002.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-14
Work Began00-00-00
Work Completed
Time Computed06-09-14
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04134018
Totals2484500.000.0049690.002.0

CountyWALLER
HighwayUS0290
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6262-30-001
Proj IDRMC - 626230001
Work TypeBRIDGE DECK REPAIR
 
0.001348750.00189255.89100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began03-30-15
Work Completed01-04-16
Time Computed01-05-15
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09144209
Totals348750.000.00189255.89100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS WITHIN THE HOUSTON
ToDISTRICT
CSJ6262-40-001
Proj IDRMC - 626240001
Work TypePAVEMENT MARKINGS AND OVERHEAD SIGNS
 
0.001663840.82736643.08100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-14
Work Began05-15-14
Work Completed12-14-15
Time Computed04-12-14
Contract Working Days152
Addl Days Granted0
Working Days Charged137
Percent Time Used90
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02144022
Totals663840.820.00736643.08100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HIGHWAYS
ToINSIDE LOOP 8
CSJ6262-50-001
Proj IDRMC - 626250001
Work TypePERFORMANCE BASED TOTAL MAINTENANCE
 
0.00123084824.0017620337.1076.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-03-14
Work Began06-01-14
Work Completed
Time Computed06-01-14
Contract Working Days731
Addl Days Granted0
Working Days Charged730
Percent Time Used99
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01144042
Totals23084824.000.0017620337.1076.3

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6264-07-001
Proj IDRMC - 626407001
Work TypeLOOP DET REP AND/OR REPLCMNT
 
0.0011241612.501241518.10100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-14
Work Began03-17-14
Work Completed05-23-16
Time Computed03-17-14
Contract Working Days731
Addl Days Granted90
Working Days Charged799
Percent Time Used97
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01144037
Totals1241612.500.001241518.10100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS HARRIS COUNTY
ToVARIOUS HWYS HARRIS COUNTY
CSJ6266-38-001
Proj IDRMC - 626638001
Work TypeRETRACE & REPL PAVEMENT MARKINGS
 
1.000385641.00728526.49100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-14
Work Began07-14-14
Work Completed12-11-15
Time Computed07-14-14
Contract Working Days731
Addl Days Granted0
Working Days Charged498
Percent Time Used68
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6266-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03144025
Totals385641.000.00728526.49100.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS HOUSTON DISTRICT
ToVARIOUS HWYS HOUSTON DISTRICT
CSJ6268-32-001
Proj IDRMC - 626832001
Work TypeMNT OF TRAFFIC SGNLS
 
0.0011554570.001565038.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-14
Work Began09-02-14
Work Completed05-20-16
Time Computed09-02-14
Contract Working Days731
Addl Days Granted0
Working Days Charged627
Percent Time Used85
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6268-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144007
Totals1554570.000.001565038.50100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6270-23-001
Proj IDRMC - 627023001
Work TypeREFL PAV MRKS (LONG LINE)
 
0.001294371.60250210.84100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-14
Work Completed06-30-15
Time Computed07-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6270-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144027
Totals294371.600.00250210.84100.0

CountyFORT BEND
HighwaySH0006
From500' SOUTH OF VOSS ROAD
To0.56 MILE NORTH OF US 90A
CSJ6272-84-001
Proj IDRMC - 627284001
Work TypeBASE REPAIR, PFC OVERLAY AND PAV MRKS
 
1.477878488.961170425.33100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-02-15
Work Completed10-05-15
Time Computed03-02-15
Contract Working Days30
Addl Days Granted4
Working Days Charged34
Percent Time Used100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6272-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10144203
Totals878488.960.001170425.33100.0

CountyFORT BEND
HighwayFM1952
FromAUSTIN COUNTY LINE
ToFM 1489
CSJ6274-32-001
Proj IDRMC - 627432001
Work TypeBASE REPAIR, ACP OVERLAY & PAV MARKINGS
 
5.596939544.851067850.53100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-04-15
Work Completed09-29-15
Time Computed05-04-15
Contract Working Days45
Addl Days Granted0
Working Days Charged31
Percent Time Used68
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6274-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01154202
Totals939544.850.001067850.53100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6278-04-001
Proj IDRMC - 627804001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001790000.00807825.00100.0
Work Order00-00-00
Work Began02-02-15
Work Completed02-02-17
Time Computed02-02-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6278-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144005
Totals790000.000.00807825.00100.0

CountyBRAZORIA
HighwayFM0522
FromSH 35
ToFM 1459
CSJ6279-23-001
Proj IDRMC - 627923001
Work TypeACP OVERLAY
 
0.001859300.98883379.58100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-15
Work Began04-01-15
Work Completed10-07-15
Time Computed04-01-15
Contract Working Days40
Addl Days Granted0
Working Days Charged36
Percent Time Used90
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6279-23-001
INTERSTATE BARRICADES & MARKINGS, INC. (4.87)
JMHP, INC. (7.57)
Contract #01154004
Totals859300.980.00883379.58100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6279-28-001
Proj IDRMC - 627928001
Work TypeMETAL BEAM FENCE UPGRADE
 
0.0011109749.69950300.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-15
Work Began06-17-15
Work Completed06-14-17
Time Computed06-22-15
Contract Working Days102
Addl Days Granted0
Working Days Charged372
Percent Time Used364
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02154204
Totals1109749.690.00950300.75100.0

CountyHARRIS
Highway146
FromSH 225
ToSPUR 330
CSJ6280-15-001
Proj IDRMC - 628015001
Work TypeRETRACE & REPL PAVEMENT MARKING
 
5.497439278.88471601.94100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-12-15
Work Completed02-26-16
Time Computed07-12-15
Contract Working Days100
Addl Days Granted0
Working Days Charged86
Percent Time Used86
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6280-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154024
Totals439278.880.00471601.94100.0

CountyWALLER
HighwayUS0290
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6280-22-001
Proj IDRMC - 628022001
Work TypeMOWING RIGHT OF WAY
 
0.001399535.43441012.8899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-22-15
Work Began05-04-15
Work Completed
Time Computed05-04-15
Contract Working Days182
Addl Days Granted0
Working Days Charged123
Percent Time Used67
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6280-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01154203
Totals399535.430.00441012.8899.9

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6281-76-001
Proj IDRMC - 628176001
Work TypeREFLECTIVE PAVEMENT MARKINGS
 
0.001389951.19475075.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-19-15
Work Began06-02-15
Work Completed04-28-16
Time Computed06-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged332
Percent Time Used90
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154007
Totals389951.190.00475075.50100.0

CountyBRAZORIA
HighwaySH0332
FromSH332(1360'W OF FM523 TO FM523),
ToFM528(BS35C TO SH35),SP273(BS35C TO SH6)
CSJ6281-79-001
Proj IDRMC - 628179001
Work TypeACP OVERLAY AND PAVEMENT MARKINGS
 
0.001449971.55631264.09100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-19-15
Work Completed01-27-16
Time Computed08-19-15
Contract Working Days26
Addl Days Granted6
Working Days Charged29
Percent Time Used90
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6281-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154021
Totals449971.550.00631264.09100.0