Monthly State Let Construction Report For Amarillo District As Of Jan 11, 2016 Page 3 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCARSON
Highway IH 40
From 3.2 MI WEST OF CONWAY
To 1.6 MI EAST OF CONWAY
CSJ 0275-03-062
Proj ID IM 0401(211)
Work Type REHAB EXISTING ROADWAY
 
4.876 3604723.24 0.00 3641833.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 04-28-14
Work Completed 01-26-15
Time Computed 04-27-14
Contract Working Days 75
Addl Days Granted 44
Working Days Charged 130
Percent Time Used 109
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-062
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (1.10%)
HJC FARMS, INC.(0.95%)
TEX OP CONSTRUCTION, LP(1.58%)
WEST TEXAS RUMBLE STRIP(0.14%)
O. TREVINO CONSTRUCTION, LLC ( 10.62%)
BARRICADES UNLIMITED (0.00%)
Contract # 02143205
Totals 3604723.24 0.00 3641833.57 100.0

CountyGRAY
Highway IH 40
From ALANREED
To DONLEY COUNTY LINE
CSJ 0275-11-077
Proj ID NH 1502(079)
Work Type OVERLAY AND MINOR BRIDGE MAINTENANC
 
9.571 3565812.59 0.00 21000.00 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153223
Totals 3565812.59 0.00 21000.00 0.5

CountyLIPSCOMB
Highway SH 15
From FM 2172 IN DARROUZETT
To FM 1455
CSJ 0355-01-047
Proj ID STP 2015(639)
Work Type OVERLAY
 
6.099 1996781.26 0.00 1961845.61 98.2
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To FM 2172 IN DARROUZETT
CSJ 0355-02-030
Proj ID STP 2015(639)
Work Type OVERLAY
 
12.620 2960757.17 0.00 2955091.17 99.8
CountyOCHILTREE
Highway SH 15
From HANSFORD COUNTY LINE
To US 83 IN PERRYTON
CSJ 0355-04-039
Proj ID STP 2015(587)
Work Type RESTORATION OF EXISTING ROADWAY
 
18.117 8770353.11 0.00 8460687.81 96.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 06-02-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 122
Addl Days Granted 5
Working Days Charged 111
Percent Time Used 87
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-04-039
BARRICADES UNLIMITED (1.57%)
DUSTROL, INC.(0.60%)
HJC FARMS, INC.(0.90%)
O. TREVINO CONSTRUCTION, LLC (0.79%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.09%)
Contract # 01153026
Totals 13727891.54 0.00 13377624.59 97.4

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 4024531.77 100.0
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 08-28-13
Work Completed 02-24-14
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 0.00 5375125.89 100.0

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 0.00 2739865.08 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 07-30-13
Work Completed 05-19-15
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 170
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 0.00 2739865.08 100.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 324582.37 4061180.15 47.1
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 9
Working Days Charged 81
Percent Time Used 68
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 324582.37 4061180.15 47.1

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 0.00 3123999.64 46.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-15
Work Began 09-22-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 51
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
BARRICADES UNLIMITED (1.88%)
DUSTROL, INC.(0.41%)
HJC FARMS, INC.(4.71%)
Contract # 01153208
Totals 6779225.71 0.00 3123999.64 46.0

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 0.00 19055729.72 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-12
Work Began 11-19-12
Work Completed 11-13-15
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 19
Working Days Charged 529
Percent Time Used 135
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 0.00 19055729.72 100.0

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 1675915.25 32.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 105
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 1675915.25 32.8

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 0.00 3883594.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-04-13
Work Began 11-04-13
Work Completed 09-15-15
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 23
Working Days Charged 282
Percent Time Used 109
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 0.00 3883594.32 100.0

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 258581.31 2461122.17 65.3
Work Order 05-15-15
Work Began 06-08-15
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 5
Working Days Charged 122
Percent Time Used 51
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
Contract # 04153034
Totals 3768710.10 258581.31 2461122.17 65.3

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 6469334.09 100.0
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566712.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 04-15-14
Work Completed 02-12-15
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 8036046.42 100.0

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 80034.34 1772683.94 96.5
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 15799.20 1101432.32 99.9
Work Order 03-06-15
Work Began 03-19-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 105
Addl Days Granted 50
Working Days Charged 104
Percent Time Used 67
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
BARRICADES UNLIMITED (1.96%)
ALAMO BROTHERS CONCRETE(6.81%)
Contract # 01153029
Totals 2753946.73 95833.54 2874116.26 99.9

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-15-16
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73%)
LANCO TURF & SEEDING, INC. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
HJC FARMS, INC.(1.19%)
Contract # 06153218
Totals 6170063.74 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2254834.69 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 16093.30 1906300.95 90.6
Work Order 03-13-15
Work Began 06-16-15
Work Completed  
Time Computed 06-16-15
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 16093.30 1906300.95 90.6

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 0.00 634627.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 11-17-14
Work Completed 04-06-15
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 11
Working Days Charged 95
Percent Time Used 115
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 0.00 634627.32 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-157
Proj ID STP 2016(012)
Work Type CRACK SEAL
 
198.505 490788.01 0.00 483180.69 98.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-05-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 20
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-157
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153028
Totals 490788.01 0.00 483180.69 98.4

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 167622.71 1128369.11 38.9
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 42
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153026
Totals 2895601.55 167622.71 1128369.11 38.9

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMA DISTRIC
To .
CSJ 0904-00-161
Proj ID STP 2016(150)
Work Type CONSTUCT CURB RAMPS
 
0.001 1946236.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30%)
Contract # 10153022
Totals 1946236.07 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4