Monthly State Let Construction Report For Amarillo District As Of Jul 13, 2015 Page 3 Of 4

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 5867.10 2739865.08 100.0
Work Order 05-06-13
Work Began 07-30-13
Work Completed 05-19-15
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 170
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 5867.10 2739865.08 100.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 0.00 983430.92 11.4
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 5
Working Days Charged 27
Percent Time Used 23
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 0.00 983430.92 11.4

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 0.00 35796.67 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153208
Totals 6779225.71 0.00 35796.67 0.5

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 1553722.42 17789402.31 85.4
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 9
Working Days Charged 519
Percent Time Used 136
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 1553722.42 17789402.31 85.4

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 1164779.00 22.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 70
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 1164779.00 22.6

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 0.00 3840580.32 99.4
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 23
Working Days Charged 282
Percent Time Used 109
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 0.00 3840580.32 99.4

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 636088.75 636088.75 16.8
Work Order 05-15-15
Work Began 00-00-00
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 5
Working Days Charged 16
Percent Time Used 6
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
Contract # 04153034
Totals 3768710.10 636088.75 636088.75 16.8

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 6469334.09 100.0
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566712.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 04-15-14
Work Completed 02-12-15
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 8036046.42 100.0

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 134364.03 785283.66 42.7
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 0.00 0.00 0.0
Work Order 03-06-15
Work Began 03-19-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 60
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
BARRICADES UNLIMITED (1.96%)
ALAMO BROTHERS CONCRETE(6.81%)
Contract # 01153029
Totals 2753946.73 134364.03 785283.66 28.5

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153218
Totals 6170063.74 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2254834.69 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 1051683.56 49.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 18
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 1051683.56 49.9

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 -8207.43 626419.86 100.0
Work Order 10-28-14
Work Began 11-17-14
Work Completed 04-06-15
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 11
Working Days Charged 95
Percent Time Used 115
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 8207.43 626419.86 100.0

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 0.00 0.00 0.0
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153026
Totals 2895601.55 0.00 0.00 0.0

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 3437.15 1394454.59 100.0
Work Order 07-31-13
Work Began 09-03-13
Work Completed 05-26-15
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 192
Working Days Charged 340
Percent Time Used 107
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 3437.15 1394454.59 100.0

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 1155.24 1410295.60 100.0
Work Order 01-04-13
Work Began 06-03-13
Work Completed 09-29-14
Time Computed 06-10-13
Contract Working Days 83
Addl Days Granted 26
Working Days Charged 196
Percent Time Used 179
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 1155.24 1410295.60 100.0

CountyRANDALL
Highway CS
From ON 58TH AVE, FROM GEORGIA ST
To WASHINGTON ST
CSJ 0904-11-054
Proj ID STP 2014(606)
Work Type REHAB EXISTING ROADWAY
 
0.971 1999859.05 305037.87 1814756.40 90.7
Work Order 07-29-14
Work Began 08-18-14
Work Completed  
Time Computed 08-14-14
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 98
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-054
ALAMO BROTHERS CONCRETE(7.50%)
BARRICADES UNLIMITED (2.85%)
Contract # 05143028
Totals 1999859.05 305037.87 1814756.40 90.7

CountyGRAY
Highway CR
From ON SEMINOLE RD
To AT SOUTH FORK GRAPEVINE CREEK
CSJ 0904-13-022
Proj ID BR 2012(728)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.167 382540.00 0.00 371694.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-14
Work Began 10-20-14
Work Completed 04-01-15
Time Computed 10-01-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 98
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-13-022
BARRICADES UNLIMITED (1.17%)
LANCO TURF & SEEDING, INC. (1.58%)
Contract # 08143019
Totals 382540.00 0.00 371694.39 100.0

CountyPOTTER
Highway RM 1061
From FM 2381
To 7.5 MILES NORTH OF FM 2381
CSJ 1245-02-043
Proj ID STP 1502(299)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
10.539 7907537.75 0.00 0.00 0.0
CountyPOTTER
Highway RM 1061
From 10.50 MILES NORTH OF FM 2381
To OLDHAM COUNTY LINE
CSJ 1245-02-044
Proj ID STP 1502(355)
Work Type ADD PASSING LANES FOR SAFETY
 
12.837 2230786.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153245
Totals 10138324.09 0.00 0.00 0.0

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 116161.17 4901420.95 90.0
Work Order 11-19-12
Work Began 01-09-13
Work Completed  
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 166
Working Days Charged 464
Percent Time Used 111
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 64.57%)
RICE CONSTRUCTION( 19.87%)
Contract # 07123220
Totals 5502012.06 116161.17 4901420.95 90.0

page 1 | page 2 | page 3 | page 4