Monthly State Let Construction Report For Amarillo District As Of Aug 10, 2015 Page 3 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 4024531.77 100.0
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 08-28-13
Work Completed 02-24-14
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 0.00 5375125.89 100.0

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 0.00 2739865.08 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 07-30-13
Work Completed 05-19-15
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 170
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 0.00 2739865.08 100.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 0.00 983430.92 11.4
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 5
Working Days Charged 27
Percent Time Used 23
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 0.00 983430.92 11.4

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 0.00 35796.67 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153208
Totals 6779225.71 0.00 35796.67 0.5

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 922992.98 18712395.29 89.8
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 9
Working Days Charged 529
Percent Time Used 139
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 922992.98 18712395.29 89.8

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 1192709.00 23.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 74
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 1192709.00 23.2

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 7191.00 3847771.32 99.6
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 23
Working Days Charged 282
Percent Time Used 109
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 7191.00 3847771.32 99.6

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 370887.80 1006976.55 26.7
Work Order 05-15-15
Work Began 00-00-00
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 5
Working Days Charged 34
Percent Time Used 14
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
Contract # 04153034
Totals 3768710.10 370887.80 1006976.55 26.7

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 6469334.09 100.0
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566712.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 04-15-14
Work Completed 02-12-15
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 8036046.42 100.0

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 14090.00 799373.66 43.5
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 404370.72 404370.72 44.0
Work Order 03-06-15
Work Began 03-19-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 105
Addl Days Granted 40
Working Days Charged 70
Percent Time Used 48
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
BARRICADES UNLIMITED (1.96%)
ALAMO BROTHERS CONCRETE(6.81%)
Contract # 01153029
Totals 2753946.73 418460.72 1203744.38 43.7

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-15-16
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153218
Totals 6170063.74 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2254834.69 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 1218330.42 57.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 46
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 1218330.42 57.9

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 0.00 626419.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 11-17-14
Work Completed 04-06-15
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 11
Working Days Charged 95
Percent Time Used 115
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 0.00 626419.86 100.0

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 94380.19 94380.19 3.2
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 6
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153026
Totals 2895601.55 94380.19 94380.19 3.2

CountyHEMPHILL
Highway PW
From GENE HOWE WILDLIFE MANAGEMENT AREA
To .
CSJ 0904-03-017
Proj ID C 904-3-17
Work Type REHAB EXISTING RDWY
 
4.477 938346.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153063
Totals 938346.79 0.00 0.00 0.0

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 0.00 1394454.59 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 09-03-13
Work Completed 05-26-15
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 192
Working Days Charged 340
Percent Time Used 107
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 0.00 1394454.59 100.0

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 0.00 1410295.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 06-03-13
Work Completed 09-29-14
Time Computed 06-10-13
Contract Working Days 83
Addl Days Granted 26
Working Days Charged 196
Percent Time Used 179
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 0.00 1410295.60 100.0

CountyRANDALL
Highway CS
From ON 58TH AVE, FROM GEORGIA ST
To WASHINGTON ST
CSJ 0904-11-054
Proj ID STP 2014(606)
Work Type REHAB EXISTING ROADWAY
 
0.971 1999859.05 233746.62 2048503.02 99.9
Work Order 07-29-14
Work Began 08-18-14
Work Completed  
Time Computed 08-14-14
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 154
Percent Time Used 108
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-054
ALAMO BROTHERS CONCRETE(7.50%)
BARRICADES UNLIMITED (2.85%)
Contract # 05143028
Totals 1999859.05 233746.62 2048503.02 99.9

CountyGRAY
Highway CR
From ON SEMINOLE RD
To AT SOUTH FORK GRAPEVINE CREEK
CSJ 0904-13-022
Proj ID BR 2012(728)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.167 382540.00 0.00 371694.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-14
Work Began 10-20-14
Work Completed 04-01-15
Time Computed 10-01-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 98
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-13-022
BARRICADES UNLIMITED (1.17%)
LANCO TURF & SEEDING, INC. (1.58%)
Contract # 08143019
Totals 382540.00 0.00 371694.39 100.0

page 1 | page 2 | page 3 | page 4