Monthly State Let Construction Report For Amarillo District As Of Mar 10, 2015 Page 3 Of 3

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 6415741.73 99.9
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566706.77 99.9
Work Order 11-14-13
Work Began 04-15-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 7982448.50 99.9

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 0.00 0.00 0.0
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153029
Totals 2753946.73 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS IN AMARILLO
To (ON SYSTEM)
CSJ 0904-00-148
Proj ID STP 2012(052)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2062945.48 0.00 1733434.99 93.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-12
Work Began 01-23-12
Work Completed  
Time Computed 01-19-12
Contract Working Days 175
Addl Days Granted 32
Working Days Charged 459
Percent Time Used 221
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(5.28%)
RAY ELECTRIC COMPANY (7.14%)
SECRET GARDENER(1.63%)
SPEEDY PAVING(2.25%)
Contract # 10113013
Totals 2062945.48 0.00 1733434.99 93.7

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-153
Proj ID STP 2014(389)G
Work Type THERMOPLASTIC STRIPING
 
442.233 1171697.78 0.00 1165109.43 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-10-14
Work Began 06-16-14
Work Completed 10-31-14
Time Computed 05-12-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 105
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-153
TOTAL HIGHWAY MAINTENANCE, LLC (6.81%)
Contract # 02143220
Totals 1171697.78 0.00 1165109.43 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 7500.00 2254834.69 100.0
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 7500.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 145771.74 483920.18 76.0
Work Order 10-28-14
Work Began 11-17-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 118
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 145771.74 483920.18 76.0

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153026
Totals 2895601.55 0.00 0.00 0.0

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 6196.06 1206806.36 72.1
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 4
Working Days Charged 310
Percent Time Used 242
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 6196.06 1206806.36 72.1

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 0.00 1378618.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 06-03-13
Work Completed  
Time Computed 06-10-13
Contract Working Days 83
Addl Days Granted 10
Working Days Charged 196
Percent Time Used 210
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 0.00 1378618.18 99.9

CountyRANDALL
Highway CS
From ON 58TH AVE, FROM GEORGIA ST
To WASHINGTON ST
CSJ 0904-11-054
Proj ID STP 2014(606)
Work Type REHAB EXISTING ROADWAY
 
0.971 1999859.05 193429.25 767311.32 38.3
Work Order 07-29-14
Work Began 08-18-14
Work Completed  
Time Computed 08-14-14
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 71
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-054
ALAMO BROTHERS CONCRETE(7.50%)
BARRICADES UNLIMITED (2.85%)
Contract # 05143028
Totals 1999859.05 193429.25 767311.32 38.3

CountyGRAY
Highway CR
From ON SEMINOLE RD
To AT SOUTH FORK GRAPEVINE CREEK
CSJ 0904-13-022
Proj ID BR 2012(728)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.167 382540.00 73805.00 327280.00 85.5
Work Order 09-15-14
Work Began 10-20-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 87
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-13-022
BARRICADES UNLIMITED (1.17%)
LANCO TURF & SEEDING, INC. (1.58%)
Contract # 08143019
Totals 382540.00 73805.00 327280.00 85.5

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 262819.91 4049798.88 74.0
Work Order 11-19-12
Work Began 01-09-13
Work Completed  
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 131
Working Days Charged 401
Percent Time Used 105
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 48.75%)
RICE CONSTRUCTION( 19.87%)
Contract # 07123220
Totals 5502012.06 262819.91 4049798.88 74.0

CountyLIPSCOMB
Highway SH 23
From 11.05 MI N OF US 83
To US 83
CSJ 1337-02-010
Proj ID STP 2013(086)
Work Type REHAB & WIDEN EXISTING RDWY
 
11.050 6406551.08 0.00 6065392.63 96.7
Work Order 01-03-13
Work Began 01-07-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 190
Addl Days Granted 40
Working Days Charged 350
Percent Time Used 152
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-010
AMARILLO RMT ENTERPRISE(2.63%)
CUTRELL TRUCKING COMPANY, INC. (3.97%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.80%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.04%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.32%)
Contract # 10123014
Totals 6406551.08 0.00 6065392.63 96.7

CountyDALLAM
Highway SS 17
From US 87
To US 385
CSJ 1702-03-001
Proj ID STP 2011(992)
Work Type NEW LOCATION 2 LANE RDWY
 
1.866 1621574.25 0.00 1853975.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 02-06-12
Work Completed  
Time Computed 02-28-12
Contract Working Days 150
Addl Days Granted 17
Working Days Charged 174
Percent Time Used 104
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.37%)
SECRET GARDENER(0.94%)
Contract # 05113008
Totals 1621574.25 0.00 1853975.60 99.9

CountyLIPSCOMB
Highway RM 2248
From AT NORTH FORK KIOWA CREEK
To .
CSJ 2078-02-007
Proj ID BR 2012(478)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.227 1605360.30 771.60 1629740.77 99.9
Work Order 02-14-14
Work Began 03-04-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 84
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2078-02-007
ALAMO BROTHERS CONCRETE(2.24%)
BARRICADES UNLIMITED (1.94%)
E. DIAZ TRUCKING (0.00%)
HJC FARMS, INC.(1.99%)
SHINN & GREGORY, INC.(5.73%)
Contract # 11133011
Totals 1605360.30 771.60 1629740.77 99.9

CountyRANDALL
Highway LP 335
From IH 27, E
To BNSF RR
CSJ 2635-02-022
Proj ID DMO 2012(189)
Work Type ADDITIONAL 2 LANES AND BRIDGES
 
3.000 32232646.86 1191704.11 6719455.46 20.8
Work Order 03-04-14
Work Began 11-03-14
Work Completed  
Time Computed 03-20-14
Contract Working Days 645
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE(4.52%)
BARRICADES UNLIMITED (1.36%)
LONE STAR PRODUCTS (FLOWER MOUND)(0.00%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73%)
MCL CONTRACTING, LLC (0.04%)
PENHALL COMPANY (AUSTIN) (0.02%)
WILLIS ELECTRIC CO., LP(2.97%)
Contract # 12133202
Totals 32232646.86 1191704.11 6719455.46 20.8

page 1 | page 2 | page 3