Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
County | HARRISON |
Highway |
CR |
From |
ON CR 2607 AT HARRISON BAYOU BRANCH |
To |
. |
CSJ |
0919-03-051 |
Proj ID |
BR 2012(677) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.058 |
309840.45 |
0.00 |
308928.97 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
07-22-14 |
Work Began |
09-03-14 |
Work Completed |
02-20-15 |
Time Computed |
09-03-14 |
Contract Working Days |
40 |
Addl Days Granted |
0 |
Working Days Charged |
36 |
Percent Time Used |
90 |
Contractor(s) |
PIERCE CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0919-03-051 PANOLA SIGN & BARRICADE, INC.(0.96%) ODUM SERVICES, L.P.(3.58%) SOUTHWEST ENVIRONMENT SERVICES LLC (1.49%) M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.19%) REDROD STEEL AND CABLE, LLC(0.49%)
|
Contract # |
06143054 |
|
Totals |
309840.45 |
0.00 |
308928.97 |
100.0 |
|
County | MARION |
Highway |
CR |
From |
ON CR 3306 AT HUNTS CREEK |
To |
. |
CSJ |
0919-22-031 |
Proj ID |
BR 1102(243) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.059 |
231033.00 |
0.00 |
228056.18 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
02-10-14 |
Work Began |
04-11-14 |
Work Completed |
09-17-14 |
Time Computed |
04-11-14 |
Contract Working Days |
50 |
Addl Days Granted |
0 |
Working Days Charged |
52 |
Percent Time Used |
104 |
Contractor(s) |
J.M. YANEZ CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 0919-22-031 SOUTHWEST ENVIRONMENT SERVICES LLC (1.37%) DUSTIN ALLEN, INC. (3.80%) TOTAL HIGHWAY MAINTENANCE, LLC (0.87%) WILDER BROTHERS CONSTRUCTION, INC. (3.22%) FRITCHER CONSTRUCTION SERVICES (3.02%)
|
Contract # |
01143217 |
|
Totals |
231033.00 |
0.00 |
228056.18 |
100.0 |
|
County | UPSHUR |
Highway |
FM 555 |
From |
SH 155 |
To |
SH 154 |
CSJ |
1018-02-017 |
Proj ID |
STP 1502(227)HES |
Work Type |
GR, BS, SURF, HFST & PAV MRKS |
|
|
10.673 |
1904823.20 |
0.00 |
0.00 |
0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
08-26-15 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
00-00-00 |
Contract Working Days |
77 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
H. H. HOWARD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1018-02-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # |
06153224 |
|
Totals |
1904823.20 |
0.00 |
0.00 |
0.0 |
|
County | MARION |
Highway |
FM 805 |
From |
CR 3410 |
To |
1.3 MI. E. OF SH 43 |
CSJ |
1101-01-013 |
Proj ID |
STP 1502(014)HES |
Work Type |
SAFE TREAT FIXED OBJECTS & WIDEN LN |
|
|
7.199 |
1172292.91 |
479.81 |
662101.21 |
56.4 |
Work Order |
06-01-15 |
Work Began |
07-06-15 |
Work Completed |
|
Time Computed |
07-02-15 |
Contract Working Days |
95 |
Addl Days Granted |
0 |
Working Days Charged |
60 |
Percent Time Used |
63 |
Contractor(s) |
H. V. CAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1101-01-013 PANOLA SIGN & BARRICADE, INC.(0.76%) SOUTHWEST ENVIRONMENT SERVICES LLC (4.55%) JM YANEZ CONSTRUCTION(7.74%) STRIPING TECHNOLOGY, L.P.(2.51%)
|
Contract # |
04153228 |
|
Totals |
1172292.91 |
479.81 |
662101.21 |
56.4 |
|
County | TITUS |
Highway |
FM 1402 |
From |
1.2 MI N OF IH 30 |
To |
1.8 MI N OF IH 30 |
CSJ |
1384-01-021 |
Proj ID |
C 1384-1-21 |
Work Type |
GR, BASE, SURF & PM |
|
|
0.622 |
1351578.66 |
112.50 |
1404900.23 |
99.9 |
Work Order |
01-17-14 |
Work Began |
02-24-14 |
Work Completed |
|
Time Computed |
03-01-14 |
Contract Working Days |
95 |
Addl Days Granted |
0 |
Working Days Charged |
63 |
Percent Time Used |
66 |
Contractor(s) |
TEXANA LAND & ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1384-01-021 BAHENA CONSTRUCTION CO.,INC. (9.74%) GIST ENTERPRISES, INC. (1.45%) LYON BARRICADE AND CONSTRUCTION CO.(0.76%) SAMMY G. SMALLWOOD (0.50%) STRIPING TECHNOLOGY, L.P.(4.23%) TURF WORKZ (2.28%) MOORE CONSTRUCTION, INC. (3.27%)
|
Contract # |
10133211 |
|
Totals |
1351578.66 |
112.50 |
1404900.23 |
99.9 |
|
County | UPSHUR |
Highway |
SH 300 |
From |
0.2 MI S OF US 271 |
To |
3.0 MI N OF FM 726 |
CSJ |
1385-01-034 |
Proj ID |
NH 1502(053) |
Work Type |
CMT TRT BASE, ACP & PVMT MARKINGS |
|
|
4.729 |
5991672.88 |
0.00 |
6352155.33 |
99.9 |
Work Order |
04-07-15 |
Work Began |
06-04-15 |
Work Completed |
|
Time Computed |
05-08-15 |
Contract Working Days |
125 |
Addl Days Granted |
0 |
Working Days Charged |
118 |
Percent Time Used |
94 |
Contractor(s) |
H. H. HOWARD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1385-01-034 PANOLA SIGN & BARRICADE, INC.(0.24%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.44%) STRIPING TECHNOLOGY, L.P.(1.09%) TEXOP CONSTRUCTION (1.43%) WEST TEXAS RUMBLE STRIP(0.13%) RK HALL, LLC ( 54.98%)
|
Contract # |
03153235 |
|
Totals |
5991672.88 |
0.00 |
6352155.33 |
99.9 |
|
County | MARION |
Highway |
FM 726 |
From |
AT BRUSHY CREEK |
To |
. |
CSJ |
1895-03-019 |
Proj ID |
BR 1502(018) |
Work Type |
REPLACE BRIDGE AND APPROACHES |
|
|
0.185 |
1614012.00 |
0.00 |
1651604.12 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
05-15-15 |
Work Began |
06-08-15 |
Work Completed |
12-01-15 |
Time Computed |
06-15-15 |
Contract Working Days |
85 |
Addl Days Granted |
0 |
Working Days Charged |
91 |
Percent Time Used |
107 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1895-03-019 PANOLA SIGN & BARRICADE, INC.(0.33%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.88%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.59%) ODUM SERVICES, L.P.(1.49%) STRIPING TECHNOLOGY, L.P.(0.66%) MCL CONTRACTING, LLC (0.20%) SOUTHEAST GRINDING & GROOVING, LLC (0.33%)
|
Contract # |
04153237 |
|
Totals |
1614012.00 |
0.00 |
1651604.12 |
100.0 |
|
County | BOWIE |
Highway |
FM 2253 |
From |
IH 30 |
To |
US 82 |
CSJ |
2048-01-014 |
Proj ID |
STP 2014(596) |
Work Type |
GRADING, BASE, SURFACING & PAV MARKS |
|
|
0.383 |
2250079.40 |
50454.30 |
2240429.63 |
99.9 |
Work Order |
06-18-14 |
Work Began |
08-18-14 |
Work Completed |
|
Time Computed |
08-18-14 |
Contract Working Days |
100 |
Addl Days Granted |
67 |
Working Days Charged |
190 |
Percent Time Used |
113 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2048-01-014 MAC TRANSPORTATION, LTD, L.L.P.(1.98%) STRIPING TECHNOLOGY, L.P.(1.08%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%) ODUM SERVICES, L.P.(1.02%) PANOLA SIGN & BARRICADE, INC.(0.23%) N-LINE TRAFFIC MAINTENANCE, L.P. (2.12%) RICK HARGROVE TRUCKING (1.98%) TEXOP CONSTRUCTION (1.14%) RK HALL, LLC ( 12.79%) SOUTHEAST GRINDING & GROOVING, LLC (0.06%)
|
Contract # |
04143206 |
|
Totals |
2250079.40 |
50454.30 |
2240429.63 |
99.9 |
|
County | HARRISON |
Highway |
FM 2625 |
From |
FM 31 |
To |
FM 9 |
CSJ |
3283-01-014 |
Proj ID |
STP 1502(055) |
Work Type |
CEMENT TRT, FL BS, SURF & PAV MARKS |
|
|
8.690 |
4532166.52 |
1200.00 |
1808689.76 |
39.9 |
Work Order |
05-15-15 |
Work Began |
06-15-15 |
Work Completed |
|
Time Computed |
01-30-16 |
Contract Working Days |
225 |
Addl Days Granted |
0 |
Working Days Charged |
53 |
Percent Time Used |
23 |
Contractor(s) |
H. V. CAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3283-01-014 PANOLA SIGN & BARRICADE, INC.(0.45%) STRIPING TECHNOLOGY, L.P.(2.27%) SOUTHWEST ENVIRONMENT SERVICES LLC (1.14%) JOHNSON CONSTRUCTION SERVICES, LLC.(0.45%)
|
Contract # |
04153253 |
|
Totals |
4532166.52 |
1200.00 |
1808689.76 |
39.9 |
|
County | UPSHUR |
Highway |
FM 3245 |
From |
US 259 |
To |
SH 154 |
CSJ |
3344-03-003 |
Proj ID |
STP 2014(793)HES |
Work Type |
CONSTRUCT PAVED SHOULDERS |
|
|
1.994 |
527788.66 |
0.00 |
479362.56 |
100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order |
07-18-14 |
Work Began |
09-02-14 |
Work Completed |
08-06-15 |
Time Computed |
09-02-14 |
Contract Working Days |
70 |
Addl Days Granted |
0 |
Working Days Charged |
37 |
Percent Time Used |
52 |
Contractor(s) |
H. H. HOWARD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3344-03-003 DUSTIN ALLEN, INC. (3.91%) PANOLA SIGN & BARRICADE, INC.(1.63%) SOUTHWEST ENVIRONMENT SERVICES LLC (0.78%) STRIPING TECHNOLOGY, L.P.(4.76%)
|
Contract # |
05143011 |
|
Totals |
527788.66 |
0.00 |
479362.56 |
100.0 |
|