Monthly Local Let Maintenance Report For Brownwood District As Of Jul 14, 2017 Page 1 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN SABA
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6204-26-001
Proj IDRMC - 620426001
Work TypeROADSIDE MOWING WILL CALL AS NEEDED
 
213.000106575.90207223.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-10
Work Began07-22-10
Work Completed
Time Computed07-29-10
Contract Working Days55
Addl Days Granted55
Working Days Charged30
Percent Time Used27
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6204-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11092306
Totals106575.900.00207223.4199.9

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6209-79-001
Proj IDRMC - 620979001
Work TypeROADSIDE MOWING (WILL-CALL)
 
206.820132474.19303968.5399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-12-10
Work Began07-12-10
Work Completed
Time Computed07-19-10
Contract Working Days60
Addl Days Granted83
Working Days Charged23
Percent Time Used16
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05102301
Totals132474.190.00303968.5399.9

CountySTEPHENS
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6224-87-001
Proj IDRMC - 622487001
Work TypeROADSIDE MOWING
 
261.110178895.71327882.1399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-11
Work Began07-25-11
Work Completed
Time Computed08-01-11
Contract Working Days55
Addl Days Granted55
Working Days Charged52
Percent Time Used47
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6224-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04112304
Totals178895.710.00327882.1399.9

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6228-83-001
Proj IDRMC - 622883001
Work TypeROADSIDE MOWING
 
286.300156557.76288260.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-11
Work Began08-04-11
Work Completed
Time Computed08-02-11
Contract Working Days55
Addl Days Granted55
Working Days Charged74
Percent Time Used67
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6228-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06112302
Totals156557.760.00288260.6499.9

CountySAN SABA
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6234-21-001
Proj IDSUP - 623421001
Work TypeSTATE USE PICNIC AREA MAINTENACE
 
0.00166080.00125880.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-11
Work Began11-01-11
Work Completed
Time Computed11-01-11
Contract Working Days730
Addl Days Granted730
Working Days Charged1,481
Percent Time Used101
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11112330
Totals66080.000.00125880.0099.9

CountyBROWN
HighwayUS0377
FromVARIOUS
ToVARIOUS
CSJ6242-78-001
Proj IDRMC - 624278001
Work TypeREPAIR MBGF & CABLE BARRIER AS NEEDED
 
0.001293875.00721092.56100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-12
Work Began07-26-12
Work Completed09-01-15
Time Computed07-26-12
Contract Working Days100
Addl Days Granted160
Working Days Charged229
Percent Time Used88
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05122303
Totals293875.000.00721092.56100.0

CountyBROWN
HighwayUS0183
FromN/A
ToN/A
CSJ6251-88-001
Proj IDSUP - 625188001
Work TypeSTATE USE JANITORIAL - DISTRICT COMPLEX
 
0.00161461.7176368.55100.0
Work Order11-15-12
Work Began11-15-12
Work Completed08-01-15
Time Computed11-15-12
Contract Working Days745
Addl Days Granted180
Working Days Charged870
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6251-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11122330
Totals61461.710.0076368.55100.0

CountyMCCULLOCH
HighwayUS0087
FromVARIOUS
ToVARIOUS
CSJ6253-00-001
Proj IDSUP - 625300001
Work TypeSTATE USE LITTER REMOVAL
 
0.00161617.7619898.2432.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-13
Work Began02-01-13
Work Completed
Time Computed02-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged360
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11122332
Totals61617.760.0019898.2432.2

CountyMILLS
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6253-04-001
Proj IDSUP - 625304001
Work TypeSTATE USE LITTER REMOVAL
 
0.00114841.3013841.3093.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-13
Work Began09-01-13
Work Completed
Time Computed09-01-13
Contract Working Days735
Addl Days Granted0
Working Days Charged118
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04132330
Totals14841.300.0013841.3093.2

CountySAN SABA
HighwaySH0016
FromVARIOUS
ToVARIOUS
CSJ6253-05-001
Proj IDSUP - 625305001
Work TypeSTATE USE LITTER REMOVAL
 
0.00130575.1628575.1693.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-13
Work Began05-01-13
Work Completed
Time Computed05-15-13
Contract Working Days735
Addl Days Granted0
Working Days Charged293
Percent Time Used39
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04132331
Totals30575.160.0028575.1693.4

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6253-60-001
Proj IDSUP - 625360001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00135050.0031165.0088.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-13
Work Began03-01-13
Work Completed
Time Computed03-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged790
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01132333
Totals35050.000.0031165.0088.9

CountySTEPHENS
HighwayUS0180
FromVARIOUS
ToVARIOUS
CSJ6253-61-001
Proj IDSUP - 625361001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00168800.0044640.0064.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-13
Work Began03-01-13
Work Completed
Time Computed03-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged791
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01132332
Totals68800.000.0044640.0064.8

CountyEASTLAND
HighwaySH0112
FromN/A
ToN/A
CSJ6254-27-001
Proj IDSUP - 625427001
Work TypeSTATE USE JANITORIAL
 
0.00145026.2047413.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-13
Work Began01-01-13
Work Completed02-01-16
Time Computed01-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged1,066
Percent Time Used146
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6254-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01132330
Totals45026.200.0047413.90100.0

CountyBROWN
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6256-19-001
Proj IDSUP - 625619001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.001110815.0084200.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-13
Work Began03-01-13
Work Completed05-01-15
Time Computed03-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged791
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132331
Totals110815.000.0084200.00100.0

CountyEASTLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6256-20-001
Proj IDSUP - 625620001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.001156100.00124380.0079.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-13
Work Began03-01-13
Work Completed
Time Computed03-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged790
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132332
Totals156100.000.00124380.0079.6

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY MAINTENACE OFFICE
To"
CSJ6256-21-001
Proj IDSUP - 625621001
Work TypeSTATE USE JANITORIAL & CUSTODIAL SERVICE
 
0.00116723.5211780.9670.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-13
Work Began03-01-13
Work Completed
Time Computed03-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged699
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6256-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132333
Totals16723.520.0011780.9670.4

CountyCOLEMAN
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6259-65-001
Proj IDSUP - 625965001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00182500.0063600.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-13
Work Began09-01-13
Work Completed09-01-15
Time Computed09-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132330
Totals82500.000.0063600.00100.0

CountyMCCULLOCH
HighwayUS0377
FromVARIOUS
ToVARIOUS
CSJ6259-66-001
Proj IDSUP - 625966001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00191100.0072445.0079.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-13
Work Began09-01-13
Work Completed
Time Computed09-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged656
Percent Time Used89
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132331
Totals91100.000.0072445.0079.5

CountyBROWN
HighwayUS0183
FromN/A
ToN/A
CSJ6259-67-001
Proj IDSUP - 625967001
Work TypeSTATE USE JANITORIAL BWD AREA OFC
 
0.00114258.7213050.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed10-01-15
Time Computed10-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132332
Totals14258.720.0013050.52100.0

CountyBROWN
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6259-68-001
Proj IDSUP - 625968001
Work TypeSTATE USE JANITORIAL BROWN CO MAINT OFC
 
0.00113816.8011821.8085.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-13
Work Began10-01-13
Work Completed
Time Computed10-01-13
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6259-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08132333
Totals13816.800.0011821.8085.5