Monthly Local Let Maintenance Report For Brownwood District As Of Dec 10, 2014 Page 1 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN SABA
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6204-26-001
Proj ID RMC - 620426001
Work Type ROADSIDE MOWING WILL CALL AS NEEDED
 
213.000 106575.90 0.00 183459.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-10
Work Began 07-22-10
Work Completed  
Time Computed 07-29-10
Contract Working Days 55
Addl Days Granted 55
Working Days Charged 22
Percent Time Used 20
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6204-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11092306
Totals 106575.90 0.00 183459.18 99.9

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6209-79-001
Proj ID RMC - 620979001
Work Type ROADSIDE MOWING (WILL - CALL)
 
206.820 132474.19 0.00 267155.58 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-10
Work Began 07-12-10
Work Completed  
Time Computed 07-19-10
Contract Working Days 60
Addl Days Granted 83
Working Days Charged 22
Percent Time Used 15
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05102301
Totals 132474.19 0.00 267155.58 99.9

CountyCOLEMAN
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6224-85-001
Proj ID RMC - 622485001
Work Type ROADSIDE MOWING
 
328.700 190058.49 0.00 384725.85 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-28-11
Work Began 07-28-11
Work Completed  
Time Computed 08-04-11
Contract Working Days 65
Addl Days Granted 65
Working Days Charged 59
Percent Time Used 45
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6224-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112302
Totals 190058.49 0.00 384725.85 99.9

CountyLAMPASAS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6224-86-001
Proj ID RMC - 622486001
Work Type ROADSIDE MOWING
 
220.940 170503.33 54211.29 292731.64 99.9
Work Order 12-01-11
Work Began 12-06-11
Work Completed  
Time Computed 12-08-11
Contract Working Days 55
Addl Days Granted 55
Working Days Charged 26
Percent Time Used 23
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6224-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112303
Totals 170503.33 54211.29 292731.64 99.9

CountySTEPHENS
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6224-87-001
Proj ID RMC - 622487001
Work Type ROADSIDE MOWING
 
261.110 178895.71 0.00 277429.30 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-11
Work Began 07-25-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 55
Addl Days Granted 55
Working Days Charged 48
Percent Time Used 43
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6224-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04112304
Totals 178895.71 0.00 277429.30 99.9

CountyCOMANCHE
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6228-82-001
Proj ID RMC - 622882001
Work Type ROADSIDE MOWING
 
345.560 206743.47 0.00 403962.99 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-07-11
Work Began 11-07-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 65
Addl Days Granted 60
Working Days Charged 45
Percent Time Used 36
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6228-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06112301
Totals 206743.47 0.00 403962.99 99.9

CountyMCCULLOCH
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6228-83-001
Proj ID RMC - 622883001
Work Type ROADSIDE MOWING
 
286.300 156557.76 0.00 288260.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-26-11
Work Began 08-04-11
Work Completed  
Time Computed 08-02-11
Contract Working Days 55
Addl Days Granted 55
Working Days Charged 74
Percent Time Used 67
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6228-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06112302
Totals 156557.76 0.00 288260.64 99.9

CountySAN SABA
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6234-21-001
Proj ID SUP - 623421001
Work Type STATE USE PICNIC AREA MAINTENACE
 
0.001 66080.00 2255.00 94315.00 99.9
Work Order 11-01-11
Work Began 11-01-11
Work Completed  
Time Computed 11-01-11
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 1,126
Percent Time Used 77
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11112330
Totals 66080.00 2255.00 94315.00 99.9

CountyBROWN
Highway US0377
From VARIOUS
To VARIOUS
CSJ 6242-78-001
Proj ID RMC - 624278001
Work Type REPAIR MBGF & CABLE BARRIER AS NEEDED
 
0.001 293875.00 24051.00 600356.24 99.9
Work Order 07-19-12
Work Began 07-26-12
Work Completed  
Time Computed 07-26-12
Contract Working Days 100
Addl Days Granted 100
Working Days Charged 183
Percent Time Used 91
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05122303
Totals 293875.00 24051.00 600356.24 99.9

CountyBROWN
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6246-07-001
Proj ID RMC - 624607001
Work Type MICROSURFACING
 
0.001 334500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07122303
Totals 334500.00 0.00 0.00 0.0

CountyBROWN
Highway US0183
From N/A
To N/A
CSJ 6251-88-001
Proj ID SUP - 625188001
Work Type STATE USE JANITORIAL - DISTRICT COMPLEX
 
0.001 61461.71 2250.23 57564.26 93.6
Work Order 11-15-12
Work Began 11-15-12
Work Completed  
Time Computed 11-15-12
Contract Working Days 745
Addl Days Granted 180
Working Days Charged 627
Percent Time Used 67
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6251-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122330
Totals 61461.71 2250.23 57564.26 93.6

CountyCOLEMAN
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6252-23-001
Proj ID SUP - 625223001
Work Type STATE USE LITTER
 
0.001 33705.06 0.00 42208.43 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-13
Work Began 02-01-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122331
Totals 33705.06 0.00 42208.43 99.9

CountyMCCULLOCH
Highway US0087
From VARIOUS
To VARIOUS
CSJ 6253-00-001
Proj ID SUP - 625300001
Work Type STATE USE LITTER REMOVAL
 
0.001 61617.76 0.00 14712.41 23.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-13
Work Began 02-01-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122332
Totals 61617.76 0.00 14712.41 23.8

CountyCOMANCHE
Highway US0067
From VARIOUS
To VARIOUS
CSJ 6253-01-001
Proj ID SUP - 625301001
Work Type STATE USE LITTER REMOVAL
 
0.001 61617.76 0.00 61287.76 99.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-01-13
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 448
Percent Time Used 61
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122333
Totals 61617.76 0.00 61287.76 99.4

CountyEASTLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6253-02-001
Proj ID SUP - 625302001
Work Type STATE USE LITTER REMOVAL
 
0.001 146133.26 0.00 136528.52 93.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-12
Work Began 12-01-12
Work Completed  
Time Computed 12-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 568
Percent Time Used 77
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122334
Totals 146133.26 0.00 136528.52 93.4

CountyLAMPASAS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6253-03-001
Proj ID SUP - 625303001
Work Type STATE USE LITTER REMOVAL
 
0.001 83461.42 0.00 79464.98 95.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-13
Work Began 02-01-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 380
Percent Time Used 52
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11122335
Totals 83461.42 0.00 79464.98 95.2

CountyMILLS
Highway US0183
From VARIOUS
To VARIOUS
CSJ 6253-04-001
Proj ID SUP - 625304001
Work Type STATE USE LITTER REMOVAL
 
0.001 14841.30 0.00 13841.30 93.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 735
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04132330
Totals 14841.30 0.00 13841.30 93.2

CountySAN SABA
Highway SH0016
From VARIOUS
To VARIOUS
CSJ 6253-05-001
Proj ID SUP - 625305001
Work Type STATE USE LITTER REMOVAL
 
0.001 30575.16 7143.79 28575.16 93.4
Work Order 05-08-13
Work Began 05-01-13
Work Completed  
Time Computed 05-15-13
Contract Working Days 735
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 19
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04132331
Totals 30575.16 7143.79 28575.16 93.4

CountyCOMANCHE
Highway SH0036
From VARIOUS
To VARIOUS
CSJ 6253-59-001
Proj ID SUP - 625359001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 45000.00 0.00 20016.00 44.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 610
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132331
Totals 45000.00 0.00 20016.00 44.4

CountyMILLS
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6253-60-001
Proj ID SUP - 625360001
Work Type STATE USE PICNIC AREA MAINTENANCE
 
0.001 35050.00 0.00 23360.00 66.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 609
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132333
Totals 35050.00 0.00 23360.00 66.6