Monthly State Let Construction Report For Corpus Christi District As Of May 10, 2016 Page 1 Of 4

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIVE OAK
Highway IH 37
From US 281
To ATASCOSA COUNTY LINE
CSJ 0073-07-060
Proj ID NH 1502(238)
Work Type SPOT BASE REPAIR AND OVERLAY
 
11.048 6295218.90 288775.00 328755.00 5.2
Work Order 07-15-15
Work Began 03-11-16
Work Completed  
Time Computed 10-14-15
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 23
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-060
ENVIRONMENTAL SAFETY SERVICES, INC.(0.87%)
CHEROKEE SERVICES(0.51%)
WEST TX RUMBLE STRIP (0.25%)
FLASHER EQUIPMENT COMPANY(2.80%)
Contract # 06153047
Totals 6295218.90 288775.00 328755.00 5.2

CountyLIVE OAK
Highway IH 37
From 3 MI N. OF FM 2049
To 5.5 MI N. OF FM 2049
CSJ 0073-07-061
Proj ID STP 1502(068)HES
Work Type GRADE, BASE, SURF
 
40.732 12504557.22 244640.01 1967152.97 15.7
Work Order 04-20-15
Work Began 08-10-15
Work Completed  
Time Computed 05-21-15
Contract Working Days 119
Addl Days Granted 139
Working Days Charged 117
Percent Time Used 45
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-061
HIGHWAY BARRICADES AND SERVICES, LLC (0.22%)
LONE STAR EROSION CONTROL(0.23%)
MURRAY CONSTRUCTION(0.34%)
ROADWAY SPECIALTIES, INC.(0.14%)
COX PAVING COMPANY OF TEXAS, INC.( 10.68%)
DIAMOND SURFACE, INC.(0.28%)
PAVEMENT MARKINGS INC. (1.87%)
PRIMATE CONSTRUCTION, INC. (0.77%)
Contract # 03153202
Totals 12504557.22 244640.01 1967152.97 15.7

CountyLIVE OAK
Highway IH 37
From US 59
To SAN PAT COUNTY LINE
CSJ 0074-02-070
Proj ID NH 2015(576)
Work Type SPOT BASE REPAIR AND OVERLAY
 
24.883 7901610.43 0.00 1683693.14 21.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 10-01-15
Work Completed  
Time Computed 04-03-15
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 118
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-070
MV HENKE COMPANY, LLC(0.10%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.83%)
CHEROKEE SERVICES(0.41%)
WEST TEXAS RUMBLE STRIP(0.21%)
ROADWAY SPECIALTIES, INC.(1.07%)
Contract # 02153213
Totals 7901610.43 0.00 1683693.14 21.7

CountyLIVE OAK
Highway IH 37
From .7 MI N OF US 59 INTERS.
To SAN PATRICIO COUNTY LINE
CSJ 0074-02-072
Proj ID NH 2015(883)
Work Type NOVACHIP ROADWAY
 
17.785 3901795.11 1377167.51 1377167.51 35.2
Work Order 05-21-15
Work Began 04-01-16
Work Completed  
Time Computed 06-21-15
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 33
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-072
DIAMOND SURFACE, INC.(0.49%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80%)
PAVEMENT MARKINGS INC. (2.26%)
PRIMATE CONSTRUCTION, INC. (1.75%)
Contract # 04153026
Totals 3901795.11 1377167.51 1377167.51 35.2

CountyNUECES
Highway IH 37
From NUECES BAY BLVD
To SH 358
CSJ 0074-06-222
Proj ID NH 2015(885)
Work Type MILL, UNDERSEAL AND OVERLAY
 
2.500 5938687.40 26460.00 6293678.34 99.9
Work Order 05-21-15
Work Began 09-18-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 90
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-222
STAR OPERATIONS, INC.(2.44%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.50%)
K.L. DURHAM CONSTRUCTION, LLC(2.98%)
SCR CONSTRUCTION CO., INC. (0.80%)
Contract # 04153030
Totals 5938687.40 26460.00 6293678.34 99.9

CountyJIM WELLS
Highway FM 665
From 15OOFT W. OF FM 1931
To INTERSECTION OF FM 1931
CSJ 0086-19-031
Proj ID STP 2016(960)
Work Type WIDEN EXISTING BRIDGE
 
0.290 642139.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0086-19-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163221
Totals 642139.91 0.00 0.00 0.0

CountyJIM WELLS
Highway SH 359 ETC
From ELIZABETH ST.
To CONTROL BREAK
CSJ 0087-02-050
Proj ID STP 2016(347)
Work Type SEAL COAT ROADWAY
 
107.862 3670300.25 0.00 303003.38 8.2
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0087-02-050
VIZCAINO, L.P. ( 13.09%)
FLASHER EQUIPMENT COMPANY(1.24%)
Contract # 11153033
Totals 3670300.25 0.00 303003.38 8.2

CountySAN PATRICIO
Highway SH 359
From JIM WELLS COUNTY LINE
To INTERSECTION WITH FM 666
CSJ 0087-03-030
Proj ID STP 1502(429)HES
Work Type GRADE, BASE, SURF
 
4.530 46821.19 2940.00 35661.01 76.1
CountySAN PATRICIO
Highway SH 359
From INTERSECTION WITH FM 666
To BEE COUNTY LINE
CSJ 0087-04-038
Proj ID STP 1502(430)HES
Work Type GRADE, BASE, SURF
 
6.884 915521.99 147406.60 550839.33 60.1
CountyBEE
Highway SH 359
From SAN PATRICIO COUNTY LINE
To US 181
CSJ 0087-05-027
Proj ID STP 1502(431)HES
Work Type GRADE, BASE, SURF
 
7.294 1080657.82 379175.30 959750.35 88.8
CountySAN PATRICIO
Highway SH 188
From US 181/SH 89
To ARANSAS COUNTY LINE
CSJ 0507-03-042
Proj ID STP 1502(432)HES
Work Type GRADE, BASE, SURF
 
16.054 2071173.91 718276.69 1537856.53 74.2
Work Order 11-02-15
Work Began 12-01-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 54
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0087-03-030
D & S TEXAS ICON CONSTRUCTION, LLC.(2.47%)
HIGHWAY BARRICADES AND SERVICES, LLC (4.82%)
Contract # 07153233
Totals 4114174.91 1247798.59 3084107.22 74.9

CountyGOLIAD
Highway US 59 ETC
From VICTORIA COUNTY LINE
To BEGIN DIVIDED SECTION
CSJ 0088-03-040
Proj ID NH 2016(882)
Work Type HOT RUBBER SEAL
 
37.545 3511638.12 0.00 0.00 0.0
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 04-01-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BLACKTOPPER TECHNOLOGY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-03-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163242
Totals 3511638.12 0.00 0.00 0.0

CountyKARNES
Highway US 181
From FM 1144
To CONTROL BREAK AT (2MI NO OF CR368)
CSJ 0100-05-075
Proj ID NH 1502(571)
Work Type REHAB ROADWAY
 
2.020 5184264.93 0.00 3198930.92 61.7
CountyKARNES
Highway US 181
From CONTROL BREAK (.2MI N OF CR 638)
To US 181-G
CSJ 0100-06-062
Proj ID NH 1502(571)
Work Type REHAB ROADWAY
 
4.500 6800161.93 0.00 2798188.07 41.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-15
Work Began 02-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 284
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 19
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-075
CHEROKEE SERVICES(0.13%)
COWBELL TRAFFIC SERVICES, INC. (0.18%)
COX PAVING COMPANY OF TEXAS, INC.(6.30%)
LONE STAR EROSION CONTROL(0.18%)
MURRAY CONSTRUCTION(0.13%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.51%)
ROADWAY SPECIALTIES, INC.(1.56%)
PERFORMANCE EQUIPMENT SERVICE(0.18%)
Contract # 08153010
Totals 11984426.86 0.00 5997118.99 50.0

CountyBEE
Highway US 181
From SH 359
To 1 MI SOUTH (CONTROL BREAK)
CSJ 0101-01-066
Proj ID STP 2015(886)
Work Type GRADE, BASE, SURF
 
0.965 58120.86 26540.99 71897.17 99.9
CountyBEE
Highway US 181
From 1 MI SOUTH SH 359 (CONTROL BREAK)
To SAN PATRICIO COUNTY LINE
CSJ 0101-02-035
Proj ID STP 2015(886)
Work Type MILL, SEAL AND OVERLAY, BASE REPAIR
 
10.370 4030242.82 30229.58 4222844.98 99.9
Work Order 05-21-15
Work Began 10-19-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 89
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-01-066
D&S TEXAS ICON CONSTRUCTION, LLC (0.06%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.22%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.46%)
SCR CONSTRUCTION CO., INC. (0.30%)
WEST TEXAS RUMBLE STRIP(0.21%)
Contract # 04153006
Totals 4088363.68 56770.57 4294742.15 99.9

CountySAN PATRICIO
Highway US 181
From SH 89
To BEE COUNTY LINE
CSJ 0101-03-087
Proj ID NH 2016(961)
Work Type OVERLAY ROADWAY
 
5.800 1972141.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0101-03-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163006
Totals 1972141.73 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 181
From FM 893
To NUECES BAY CAUSEWAY (CO.LINE)
CSJ 0101-05-035
Proj ID NH 1502(060)
Work Type OVERLAY ROADWAY
 
2.379 1689178.70 974200.29 1149908.89 68.0
CountySAN PATRICIO
Highway SH 361
From END OF DIVIDED SECTION
To FM 1069
CSJ 0180-10-076
Proj ID NH 1502(060)
Work Type MILL, OVERLAY, BASE REPAIR
 
0.200 325780.10 2684.97 238895.68 73.3
CountyREFUGIO
Highway US 77
From REFUGIO S. CITY LIMITS
To 0.362 M. N OF FM 2441
CSJ 0371-03-116
Proj ID NH 1502(060)
Work Type MILL, SEAL AND OVERLAY
 
0.100 1247999.10 1276.63 1485580.04 99.9
CountySAN PATRICIO
Highway US 77
From 0.68 M SOUTH OF BS 77T
To 0.65 MI. N OF SH 188
CSJ 0371-04-060
Proj ID NH 1502(060)
Work Type GRADE, BASE, SURF
 
1.800 2030820.25 0.00 2102025.35 99.9
Work Order 04-10-15
Work Began 09-29-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 119
Addl Days Granted 9
Working Days Charged 100
Percent Time Used 78
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-05-035
HIGHWAY BARRICADES AND SERVICES, LLC (3.42%)
SCR CONSTRUCTION CO., INC. (0.55%)
TEX OP CONSTRUCTION, LP(3.06%)
WEST TX RUMBLE STRIP (0.11%)
D S TEXAS ICON CONSTRUCTION, LLC (0.04%)
Contract # 03153236
Totals 5293778.15 978161.89 4976409.96 94.0

CountyNUECES
Highway US 181
From AT US 181 NUECES BAY CAUSEWAY
To .
CSJ 0101-06-110
Proj ID BR 1502(572)
Work Type CONCRETE STRUCTURE REPAIR
 
0.200 1496152.32 91729.50 408950.44 27.3
Work Order 09-11-15
Work Began 02-29-16
Work Completed  
Time Computed 10-11-15
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 27
Contractor(s)
IHS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-06-110
HIGHWAY BARRICADES AND SERVICES, LLC (0.32%)
NATIONAL MARINE DIVING SERVICES( 22.93%)
Contract # 08153045
Totals 1496152.32 91729.50 408950.44 27.3

CountyNUECES
Highway SH 44
From W. END OF CLARKWOOD RELIEF ROUTE
To WEST OF FM 3386
CSJ 0102-01-106
Proj ID NH 2013(751)
Work Type GRADE, BASE, S URF, STRS
 
1.146 16390152.96 1596244.39 4649954.68 28.3
Work Order 09-11-15
Work Began 01-04-16
Work Completed  
Time Computed 09-01-15
Contract Working Days 356
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 19
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-01-106
HIGHWAY BARRICADES AND SERVICES, LLC (0.59%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.07%)
WEBBER BARRIER SERVICES, LLC.(0.89%)
SCOTT DERR PAINTING CO, LLC(0.20%)
K.L. DURHAM CONSTRUCTION, LLC(0.41%)
STAR OPERATIONS, INC.(2.14%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.97%)
D & S TEXAS ICON CONSTRUCTION, LLC.(0.62%)
CABCOS CONTRACTORS LLC (2.53%)
MCL CONTRACTING, LLC (0.05%)
Contract # 07153007
Totals 16390152.96 1596244.39 4649954.68 28.3

CountyNUECES
Highway US 77
From FM 892
To S OF CR 28
CSJ 0102-02-096
Proj ID C 102-2-96
Work Type GRADE, BASE, SURF, STRS
 
4.039 38721708.43 810940.10 8070129.48 20.8
Work Order 12-17-13
Work Began 01-04-16
Work Completed  
Time Computed 09-01-13
Contract Working Days 527
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 12
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-096
IOC COMPANY LLC(5.78%)
PANTHER CREEK TRANSPORTATION, INC. (3.94%)
K.L. DURHAM CONSTRUCTION, LLC(0.25%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.45%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.71%)
LAYFIELD CONSTRUCTION, INC (0.47%)
ACTION CONSTRUCTORS( 32.85%)
SHINN & GREGORY, INC.(0.85%)
Contract # 07133202
Totals 38721708.43 810940.10 8070129.48 20.8

CountyKLEBERG
Highway SH 285
From US 77
To BROOKS COUNTY LINE
CSJ 0102-06-030
Proj ID STP 2015(495)
Work Type MILL, FILL MAINLANES, SC FULL WIDTH
 
12.100 11207164.46 381243.74 7133764.69 63.6
CountyKLEBERG
Highway SH 285
From 4.9 MI E OF FM 2191
To 0.3 MI W OF US 77
CSJ 0102-06-031
Proj ID STP 2015(638)HES
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
11.800 79213.98 0.00 0.00 0.0
Work Order 03-18-15
Work Began 04-28-15
Work Completed  
Time Computed 04-03-15
Contract Working Days 162
Addl Days Granted 120
Working Days Charged 222
Percent Time Used 78
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-06-030
HIGHWAY BARRICADES AND SERVICES, LLC (2.31%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.89%)
DUSTROL, INC.(3.53%)
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
TREV-CORT TRUCKING INC (1.45%)
Contract # 01153216
Totals 11286378.44 381243.74 7133764.69 63.2

CountyNUECES
Highway SH 44
From BS 44D
To MANNING RD.
CSJ 0102-15-002
Proj ID NH 2016(266)
Work Type PLANE, SEAL AND OVERLAY
 
2.250 1821533.80 0.00 0.00 0.0
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-15-002
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153220
Totals 1821533.80 0.00 0.00 0.0

CountyGOLIAD
Highway US 183
From FRANKLIN ST.
To SH 239
CSJ 0155-04-051
Proj ID STP 2015(887)
Work Type MILL AND INLAY
 
44.041 4784121.15 1063932.07 2283947.48 47.7
Work Order 10-21-15
Work Began 01-07-16
Work Completed  
Time Computed 11-01-15
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 35
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-04-051
ALL MATERIALS CONSTRUCTION, LLC(0.71%)
CHEROKEE SERVICES(0.32%)
COX PAVING COMPANY OF TEXAS, INC.( 17.51%)
FUQUAY, INC. (0.07%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.36%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.19%)
Contract # 09153214
Totals 4784121.15 1063932.07 2283947.48 47.7

CountyREFUGIO
Highway US 183
From 4 MILES N OF SH 202
To US 77
CSJ 0155-05-039
Proj ID STP 1502(433)
Work Type GRADE, BASE SURF
 
1.700 6324506.65 0.00 0.00 0.0
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-05-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153030
Totals 6324506.65 0.00 0.00 0.0