Monthly State Let Construction Report For Corpus Christi District As Of Jun 15, 2016 Page 2 Of 4

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyARANSAS
Highway SH 35
From 549 FT. S OF PR13
To 1 MI. N. OF PR13
CSJ 0180-03-035
Proj ID STP 1102(113)
Work Type GR, BS, SURF
 
1.000 5196117.40 7732.96 8749180.85 99.9
CountyARANSAS
Highway SH 35
From N OF COPANO BAY CAUSEWAY
To S OF COPANO BAY CAUSEWAY
CSJ 0180-04-083
Proj ID BR 1102(114)
Work Type REPLACE EXISTING BRIDGE & REWK APRO
 
2.087 92966472.65 520130.67 83306908.33 89.6
Work Order 06-15-11
Work Began 08-03-11
Work Completed  
Time Computed 11-14-11
Contract Working Days 968
Addl Days Granted 455
Working Days Charged 1,303
Percent Time Used 91
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-03-035
HAAS - ANDERSON CONSTRUCTION, INC. (0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.21%)
SCOTT DERR PAINTING CO (0.28%)
STAR OPERATIONS, INC.(0.45%)
A.Z. REBAR CONSTRUCTION, INC.(5.74%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
ROADWAY SPECIALTIES, INC.(0.16%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.15%)
ROADWAY CONSTRUCTION, INC. (0.77%)
ARROW DIRECTIONAL DRILLING, INC. (0.00%)
Contract # 05113234
Totals 98162590.05 527863.63 92056089.18 93.7

CountyLIVE OAK
Highway US 281
From US 59 IN GEORGE WEST
To APPROX. 5.3 MI SOUTH (CB)
CSJ 0254-01-134
Proj ID NH 1602(068)
Work Type SPOT BASE REPAIR AND OVERALY
 
5.284 5606795.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163203
Totals 5606795.34 0.00 0.00 0.0

CountyLIVE OAK
Highway US 281
From O.447 MI N. SH 72
To W TULLOS ST.
CSJ 0254-01-141
Proj ID NH 2015(888)
Work Type BASE, SURF
 
1.360 1411480.04 7222.57 1486074.58 99.9
Work Order 10-21-15
Work Began 02-15-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 80
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0254-01-141
FLASHER EQUIPMENT COMPANY(2.64%)
SCR CONSTRUCTION CO., INC. (1.34%)
SOIL-TECH, INC.(1.95%)
Contract # 09153230
Totals 1411480.04 7222.57 1486074.58 99.9

CountyJIM WELLS
Highway US 281
From FM 2508
To SH 141
CSJ 0255-01-081
Proj ID NH 2016(698)
Work Type REHAB ROADWAY
 
6.770 1764248.12 0.00 0.00 0.0
Work Order 03-14-16
Work Began 04-13-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 83
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-01-081
FOREMOST PAVING, INC.(3.96%)
Contract # 02163017
Totals 1764248.12 0.00 0.00 0.0

CountyNUECES
Highway SH 286
From SH 357
To 1 MI S OF FM 43
CSJ 0326-01-052
Proj ID NH 2013(795)
Work Type GRADE, BASE, SURF, STRS
 
2.755 45818725.52 1013668.33 28524079.52 62.2
Work Order 09-05-13
Work Began 03-05-14
Work Completed  
Time Computed 08-01-13
Contract Working Days 687
Addl Days Granted 19
Working Days Charged 459
Percent Time Used 65
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0326-01-052
LARGE & SONS_FOUNDATION DRILLING,INC.(0.20%)
MURRAY CONSTRUCTION(0.20%)
SOIL-TECH, INC.(0.35%)
MASTERPIECE GRINDING & GROOVING, LLC (0.07%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.72%)
TEXAS BOMANITE (0.21%)
TERRY L. ELLIS BACKHOE (0.05%)
TROUT TRUCKING_COMPANY INC.(2.72%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.70%)
JHABORES CONSTRUCTION CO, INC. (2.92%)
CROSSROADS MILLING, LLC(0.24%)
CABCOS CONTRACTORS LLC (5.62%)
AARON CONCRETE CONTRACTORS, L.P. (1.86%)
STAR OPERATIONS, INC.(2.06%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.65%)
MCL CONTRACTING, LLC (0.49%)
HAYWARD BAKER, INC.(0.15%)
PERFORMANCE EQUIPMENT SERVICE(0.30%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
Contract # 06133001
Totals 45818725.52 1013668.33 28524079.52 62.2

CountyNUECES
Highway SH 286
From LAREDO ST..
To GOLLIHAR OVERPASS
CSJ 0326-03-091
Proj ID NH 2015(889)
Work Type NOVACHIP ROADWAY
 
2.310 4244327.43 0.00 4216696.27 99.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 02-17-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 20
Working Days Charged 60
Percent Time Used 84
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0326-03-091
HIGHWAY BARRICADES AND SERVICES, LLC ( 11.15%)
CHEROKEE SERVICES(1.26%)
FUQUAY, INC. (0.20%)
Contract # 10153219
Totals 4244327.43 0.00 4216696.27 99.3

CountyKARNES
Highway SH 80
From FM 1354
To .865 MI S OF FM1354
CSJ 0348-03-025
Proj ID STP 1502(574)
Work Type OVERLAY ROADWAY & SPOT BASE REPAIR
 
0.870 755079.04 136594.53 451359.17 59.7
CountyKARNES
Highway SH 80
From WILSON COUNTY LINE
To .854 MI S OF FM 1354 (CONTROL BR)
CSJ 0348-03-029
Proj ID STP 1502(575)HES
Work Type GRADE, BASE, SURF
 
15.599 4931107.44 52160.93 2210963.67 44.8
CountyKARNES
Highway SH 80
From .865 MI S OF FM 1354 INTERS.
To SH 123
CSJ 0348-04-045
Proj ID STP 1502(576)
Work Type OVERLAY ROADWAY & SPOT BASE REPAIR
 
9.010 7065596.01 54121.00 546767.11 7.7
CountyKARNES
Highway SH 80
From .854 MI S OF FM1354 (CONTROL BREAK)
To SH 123
CSJ 0348-04-050
Proj ID STP 1502(577)HES
Work Type GRADE, BASE, SURF
 
9.553 2276766.39 0.00 246107.86 10.8
Work Order 11-12-15
Work Began 01-18-16
Work Completed  
Time Computed 10-01-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 22
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-03-025
D&S TEXAS ICON CONSTRUCTION(1.82%)
FLASHER EQUIPMENT COMPANY(0.22%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.13%)
THE LEVY COMPANY, L.P. (0.05%)
MURRAY CONSTRUCTION(0.38%)
ROADWAY SPECIALTIES, INC.(0.80%)
TEXAS CUTTING & CORING, INC. (0.13%)
Contract # 08153205
Totals 15028548.88 242876.46 3455197.81 22.9

CountyKARNES
Highway FM 99
From US 181
To ATASCOSA COUNTY LINE
CSJ 0348-06-023
Proj ID STP 1502(061)
Work Type PAVEMENT REPAIR AND RESURFACE
 
13.676 8219037.30 537353.12 4292320.93 52.2
Work Order 05-21-15
Work Began 09-15-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 167
Addl Days Granted 2
Working Days Charged 150
Percent Time Used 88
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0348-06-023
FLASHER EQUIPMENT COMPANY(1.46%)
MURRAY CONSTRUCTION(0.83%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.89%)
DANCO TRANSPORT INC. ( 10.13%)
Contract # 04153052
Totals 8219037.30 537353.12 4292320.93 52.2

CountyREFUGIO
Highway SH 239
From SH 35
To FM 774
CSJ 0350-01-017
Proj ID STP 1502(241)HES
Work Type GARDE, BASE, SURF
 
4.318 1996043.76 31435.29 1396378.69 69.9
CountyREFUGIO
Highway FM 2040
From FM 774
To ARANSAS COUNTY LINE
CSJ 0350-03-015
Proj ID STP 1502(242)HES
Work Type GRADE, BASE, SURF
 
5.535 2626977.96 404613.43 1249967.36 47.5
CountyARANSAS
Highway FM 2040
From REFUGIO COUNTY LINE
To 0.842 MI S OF ARANSAS C/L
CSJ 0350-04-011
Proj ID STP 1502(243)HES
Work Type GRADE, BASE, SURF
 
0.847 424378.21 105394.27 229927.34 54.1
CountyREFUGIO
Highway FM 774
From 7 MI W. OF SH 35
To 5 MI W. OF SH 35
CSJ 0447-05-068
Proj ID STP 1502(244)HES
Work Type GRADE, BASE, SURF
 
2.000 1064191.27 48030.06 146795.46 13.7
Work Order 07-16-15
Work Began 10-19-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 176
Addl Days Granted 12
Working Days Charged 121
Percent Time Used 64
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0350-01-017
FUQUAY, INC. (0.10%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.11%)
Contract # 06153056
Totals 6111591.20 589473.05 3023068.85 49.4

CountyREFUGIO
Highway US 77
From VICTORIA COUNTY LINE
To 7 MI N. OF REFUGIO CITY LIMITS
CSJ 0371-02-069
Proj ID NH 1602(069)
Work Type MILL, SEAL AND OVERLAY
 
12.946 5008823.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163036
Totals 5008823.01 0.00 0.00 0.0

CountyREFUGIO
Highway US 77
From 4.5 MI N OF FM 774
To .1 MI N OF UPPR INTERS.(CONTROL BR)
CSJ 0371-02-071
Proj ID STP 1502(434)HES
Work Type TRADE, BASE, SURF
 
1.676 1612106.37 5679.27 5679.27 0.3
CountyREFUGIO
Highway US 77
From .1 MI N OF UPRR INTERS.(CONTROL BR)
To 2.7 MI N OF FM 774
CSJ 0371-03-117
Proj ID STP 1502(435)HES
Work Type GRADE, BASE, SURF
 
0.204 704322.77 7241.99 7241.99 1.0
Work Order 02-03-16
Work Began 00-00-00
Work Completed  
Time Computed 11-02-15
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 8
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-071
COWBELL TRAFFIC SERVICES, INC. (0.66%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47%)
JMHP, INC. (6.30%)
LONE STAR EROSION CONTROL(0.13%)
MURRAY CONSTRUCTION(0.61%)
PAVEMENT MARKINGS INC. (1.20%)
PRIMATE CONSTRUCTION, INC. (1.28%)
Contract # 09153035
Totals 2316429.14 12921.26 12921.26 0.5

CountyREFUGIO
Highway US 77
From VICTORIA COUNTY LINE
To 7 MI N OF REFUGIO CITY LIMITS
CSJ 0371-02-072
Proj ID NH 1602(070)
Work Type MILL, SEAL AND OVERLAY
 
13.454 4610259.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163023
Totals 4610259.16 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 77
From ARANSAS RIVER BRIDGE
To BU 77T
CSJ 0371-04-061
Proj ID NH 1502(578)
Work Type OVERLAY ROADWAY
 
5.379 3883042.09 0.00 0.00 0.0
Work Order 09-22-15
Work Began 00-00-00
Work Completed  
Time Computed 10-01-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 1
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0371-04-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153049
Totals 3883042.09 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 77
From COOPER RD.
To IH 37
CSJ 0372-01-096
Proj ID NH 2016(803)
Work Type MILL, SEAL AND OVERLAY
 
3.831 2636291.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0372-01-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163216
Totals 2636291.70 0.00 0.00 0.0

CountyNUECES
Highway SH 44
From FM 666 (IN BANQUETE, TX)
To CONCHO ST. (IN ROBSTOWN)
CSJ 0373-02-090
Proj ID NH 2016(457)
Work Type LEVEL UP, UNDERSEAL AND OVERLAY
 
7.226 4937118.64 248288.24 4881623.82 98.8
Work Order 01-29-16
Work Began 03-02-16
Work Completed  
Time Computed 01-01-16
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 25
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0373-02-090
SCR CONSTRUCTION CO., INC. (0.39%)
MURRAY CONSTRUCTION(1.93%)
DUSTROL, INC.(3.46%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.15%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.29%)
WEST TEXAS RUMBLE STRIP(0.24%)
D & C CONCRETE CUTTING, INC. (0.32%)
Contract # 11153026
Totals 4937118.64 248288.24 4881623.82 98.8

CountyNUECES
Highway SH 44
From CONCHO ST.
To SS 22 (BAUER ST.)
CSJ 0373-02-092
Proj ID NH 2016(267)
Work Type NOVACHIP ROADWAY
 
1.600 771547.13 0.00 11209.13 1.4
CountyNUECES
Highway FM 624
From I 69E
To FM 1889 (END OF C&G SECTION)
CSJ 0989-02-050
Proj ID NH 2016(267)
Work Type NOVACHIP ROADWAY
 
1.700 959270.88 0.00 0.00 0.0
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 01-01-16
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0373-02-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153039
Totals 1730818.01 0.00 11209.13 0.6

CountyKLEBERG
Highway SH 141
From .2 MI W OF ARMSTRONG
To .2 MI E OF 10TH STREET
CSJ 0383-04-055
Proj ID STP 2016(115)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.400 783875.25 75209.87 81779.47 10.4
Work Order 11-24-15
Work Began 05-23-16
Work Completed  
Time Computed 12-01-15
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 18
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0383-04-055
GREEN LIGHT IN THE GROUND(4.02%)
Contract # 10153019
Totals 783875.25 75209.87 81779.47 10.4

CountyBEE
Highway SH 202
From CR 425
To REFUGIO COUNTY LINE
CSJ 0447-03-039
Proj ID STP 1502(436)
Work Type SPOT BASE REPAIR AND OVERLAY
 
0.100 8641470.29 882262.68 2187136.08 25.3
Work Order 08-24-15
Work Began 03-08-16
Work Completed  
Time Computed 09-01-15
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 33
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0447-03-039
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.34%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.09%)
D&S TEXAS ICON CONSTRUCTION(0.96%)
Contract # 07153013
Totals 8641470.29 882262.68 2187136.08 25.3

CountyREFUGIO
Highway FM 774
From AT MELON CREEK STR 33 ON FM 774
To APPROX 3.45 MI E OF US 77
CSJ 0447-05-061
Proj ID BR 1502(037)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.135 2333640.42 52586.79 543039.67 23.2
CountyREFUGIO
Highway FM 774
From AT ALAMEDA CREEK ON FM 774
To APPOX. 8.8 MI E. OF US 77
CSJ 0447-05-067
Proj ID BR 1502(037)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.021 1890284.15 13306.34 587475.59 31.0
Work Order 08-26-15
Work Began 02-17-16
Work Completed  
Time Computed 09-01-15
Contract Working Days 195
Addl Days Granted 15
Working Days Charged 25
Percent Time Used 11
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0447-05-061
STAR OPERATIONS, INC (SAN ANTONIO) (3.40%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.46%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.04%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.35%)
JMHP, INC. (3.01%)
MESA ROD BUSTERS, INC. (0.39%)
D & C CONCRETE CUTTING, INC. (0.17%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.21%)
Contract # 06153248
Totals 4223924.57 65893.13 1130515.26 26.7

CountySAN PATRICIO
Highway FM 631
From US 77
To FM 2512
CSJ 0507-02-053
Proj ID STP 1502(150)HES
Work Type GRADE, BASE, SURF
 
8.950 1714386.35 0.00 1905815.53 99.9
CountySAN PATRICIO
Highway FM 1944
From FM 1074
To FM 631
CSJ 1208-03-021
Proj ID STP 1502(151)HES
Work Type GRADE, BASE, SURF
 
3.822 1418998.35 7619.00 1369682.84 96.5
Work Order 07-07-15
Work Began 09-01-15
Work Completed  
Time Computed 08-07-15
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 100
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0507-02-053
HIGHWAY BARRICADES AND SERVICES, LLC (3.46%)
SOIL-TECH, INC.(0.28%)
TERRY L. ELLIS BACKHOE (0.00%)
Contract # 05153242
Totals 3133384.70 7619.00 3275498.37 99.9