Monthly State Let Construction Report For Corpus Christi District As Of Sep 15, 2014 Page 2 Of 2

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyREFUGIO
Highway US 77
From 3.036 MI N OF SH 239
To 7.183 MI S OF SH 239
CSJ 0371-02-068
Proj ID STP 2015(034)HES
Work Type INSTALL MEDIAN BARRIER
 
4.147 800470.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0371-02-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143034
Totals 800470.60 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 77
From ON US77 AT NORTH BU 77-T INTERS.
To .
CSJ 0371-04-059
Proj ID STP 1102(157)SB
Work Type GRADE, BASE, SURF, STRS
 
1.000 9914522.85 607298.52 9580328.59 98.7
Work Order 09-27-11
Work Began 12-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 269
Addl Days Granted 84
Working Days Charged 545
Percent Time Used 154
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0371-04-059
HIGHWAY BARRICADES AND SERVICES, LLC (0.26%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.02%)
S & S BRIDGE PAINTING, INC.(0.06%)
STAR OPERATIONS, INC.(1.89%)
F & W ELECTRICAL CONTRACTORS, INC. (0.32%)
WRANGLER CONTRACTING (0.84%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.36%)
HIGHWAY TECHNOLOGIES, INC. (0.63%)
PENNTEX MILLING, LLC (0.05%)
TROUT TRUCKING_COMPANY INC.(8.69%)
SOIL-TECH, INC.(1.16%)
W.S. CONSTRUCTION COMPANY(3.19%)
AARON CONCRETE CONTRACTORS, L.P. (0.86%)
NORTH TEXAS REBAR, LLC (0.18%)
PRIMATE CONSTRUCTION, INC. (0.06%)
Contract # 07113206
Totals 9914522.85 607298.52 9580328.59 98.7

CountyKLEBERG
Highway FM 2045
From AT SAN FERNANDO CREEK ON FM 2045
To 2.4 MILES EAST OF US77
CSJ 0383-05-017
Proj ID BR 2013(709)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.201 798976.76 0.00 766826.66 98.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-13
Work Began 09-24-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 130
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0383-05-017
GUERRA CONSTRUCTION COMPANY(5.76%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.49%)
DELTA SPECIALTIES SIGNS & SUPPLIES (0.39%)
JUST GROOVING, LTD.(0.18%)
FUQUAY, INC. (0.17%)
GARRETT CONSTRUCTION CO. (2.61%)
D & C CONCRETE CUTTING, INC. (0.27%)
SHINN & GREGORY, INC.(5.98%)
CERTIFIED PLACERS LLC(0.14%)
Contract # 05133024
Totals 798976.76 0.00 766826.66 98.9

CountyKARNES
Highway SH 239
From SH 72
To 1000 FT S. OF CR 129
CSJ 0516-01-015
Proj ID STP 1402(066)
Work Type GRADE, BASE, SURF, STRS
 
6.067 8525937.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-14
Work Began 00-00-00
Work Completed  
Time Computed 09-28-14
Contract Working Days 185
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0516-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143226
Totals 8525937.55 0.00 0.00 0.0

CountyNUECES
Highway SH 358
From .2 MI W OF FM 43
To .2 MI E OF FM 43
CSJ 0617-01-185
Proj ID STP 2014(982)HES
Work Type IMPORVE TRAFFIC SIGNAL
 
0.400 281111.29 0.00 0.00 0.0
CountyNUECES
Highway SH 358
From .2 MI W OF EVERHART
To .2 MI E OF EVERHART
CSJ 0617-01-186
Proj ID STP 2014(990)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.400 280827.44 0.00 0.00 0.0
CountyNUECES
Highway SH 358
From .4 MI W OF SS3
To .4 MI E OF SS3
CSJ 0617-01-187
Proj ID STP 2014(991)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.600 373871.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0617-01-185
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143057
Totals 935810.65 0.00 0.00 0.0

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN NUECES CO.
To .
CSJ 0916-00-069
Proj ID ITS 99(714)
Work Type ITS INTERGRATION
 
0.100 946694.00 3235.00 1041660.90 99.9
Work Order 06-28-13
Work Began 07-29-13
Work Completed  
Time Computed 07-14-13
Contract Working Days 204
Addl Days Granted 14
Working Days Charged 218
Percent Time Used 100
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-069
HIGHWAY BARRICADES AND SERVICES, LLC (4.62%)
J.C. COMMUNICATION ( 27.95%)
VICKERS CONSTRUCTION (7.15%)
J. CARROLL WEAVER, INC.(1.83%)
SPLICERS, INC. (5.13%)
Contract # 05133028
Totals 946694.00 3235.00 1041660.90 99.9

CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN KARNES CO.
To .
CSJ 0916-00-071
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 5181781.67 517.31 5184154.49 99.9
CountyNUECES
Highway VA
From AT VARIOUS LOCATIONS IN GOLIAD CO.
To .
CSJ 0916-00-072
Proj ID STP 2013(976)
Work Type INTERSECTION IMPROVEMENTS
 
0.100 2611106.96 56010.74 2379699.20 91.1
Work Order 10-22-13
Work Began 11-12-13
Work Completed  
Time Computed 11-07-13
Contract Working Days 160
Addl Days Granted 12
Working Days Charged 163
Percent Time Used 94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-00-071
D&S TEXAS ICON CONSTRUCTION, LLC (0.44%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.52%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.30%)
MURRAY CONSTRUCTION(0.51%)
STAR OPERATIONS, INC.(7.36%)
Contract # 08133248
Totals 7792888.63 56528.05 7563853.69 97.0

CountyBEE
Highway CR
From STR1 (AA0137001)CR536 @ BULLSHEAD C
To APPROX. 0.85 MI. SW OF US 181
CSJ 0916-25-018
Proj ID BR 1302(063)
Work Type BRIDGE REPLACEMENT
 
0.090 694394.73 0.00 0.00 0.0
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 08-07-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0916-25-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143007
Totals 694394.73 0.00 0.00 0.0

CountyGOLIAD
Highway PW
From AT GOLIAD SHS
To .
CSJ 0916-26-018
Proj ID C 916-26-18
Work Type SEAL COAT ROADS & LEVEL UP CAMPSITE
 
0.100 212182.44 142794.94 183620.82 87.0
Work Order 06-11-14
Work Began 07-21-14
Work Completed  
Time Computed 06-27-14
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 111
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0916-26-018
FLASHER EQUIPMENT COMPANY(1.45%)
HIGHWAY BARRICADES AND SERVICES, LLC (5.60%)
ROAD REPAIR, LLC ( 42.70%)
Contract # 05143040
Totals 212182.44 142794.94 183620.82 87.0

CountyLIVE OAK
Highway CR
From STR 1(AA0210001)GOOD HOPE @ ATASCOS
To APPROX 1.0 MI W OF US 281
CSJ 0916-29-012
Proj ID BR 2012(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 1340912.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 181
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0916-29-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143236
Totals 1340912.53 0.00 0.00 0.0

CountySAN PATRICIO
Highway SH 188
From FM 630
To US 77
CSJ 0994-01-030
Proj ID STP 2012(533)
Work Type REHAB
 
4.300 9223815.50 290698.25 8016686.15 86.9
Work Order 08-30-12
Work Began 02-22-13
Work Completed  
Time Computed 08-01-12
Contract Working Days 345
Addl Days Granted 0
Working Days Charged 231
Percent Time Used 66
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0994-01-030
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.49%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.94%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.14%)
KL DURHAM CONSTRUCTION, LLC(0.07%)
SCOTT DERR PAINTING CO, LLC(0.04%)
TERRY L. ELLIS BACKHOE (0.41%)
HIGHWAY TECHNOLOGIES, INC. (0.84%)
JMHP, INC. (0.58%)
W.S. CONSTRUCTION COMPANY( 20.52%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.89%)
ADVANCED PUMPING, LLC(0.06%)
STAR OPERATIONS, INC.(0.61%)
Contract # 06123226
Totals 9223815.50 290698.25 8016686.15 86.9

CountyKARNES
Highway FM 743
From .070 MI E. OF CR 139
To .085 MI E. OF FM 2443
CSJ 1095-03-016
Proj ID STP 2014(628)HES
Work Type PROVIDE ADDIT. PAVED SURFACE WIDTH
 
6.014 2619906.61 225346.40 247120.00 9.4
Work Order 06-16-14
Work Began 07-22-14
Work Completed  
Time Computed 07-02-14
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 36
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1095-03-016
ALTUS TRAFFIC MANAGEMENT LLC (0.35%)
MURRAY CONSTRUCTION(0.95%)
PAVEMENT MARKINGS INC. (1.32%)
ROADWAY SPECIALTIES, INC.(5.07%)
STAFF CONCRETE (6.48%)
Contract # 05143021
Totals 2619906.61 225346.40 247120.00 9.4

CountyKLEBERG
Highway FM 1356
From BU 77
To .4 MI EAST OF BU 77
CSJ 1446-02-019
Proj ID STP 2014(727)
Work Type REHAB AND WIDEN
 
0.400 639655.98 0.00 0.00 0.0
CountyKLEBERG
Highway FM 1717
From FM 1356 (GENERAL CAVAZOS BLVD.)
To .5 MILE SE
CSJ 1845-01-019
Proj ID STP 2014(727)
Work Type GRADE, BASE, SURF
 
0.500 1135345.42 0.00 0.00 0.0
Work Order 08-08-14
Work Began 00-00-00
Work Completed  
Time Computed 08-24-14
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1446-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143221
Totals 1775001.40 0.00 0.00 0.0

CountySAN PATRICIO
Highway FM 1069
From SH 361 IN INGLESIDE
To BS 35
CSJ 1549-03-017
Proj ID STP 1402(067)
Work Type GR, STRS, BASE, SURF & C & G
 
3.584 4902667.27 0.00 0.00 0.0
CountySAN PATRICIO
Highway FM 1069
From SH 361
To 8TH STREET
CSJ 1549-04-029
Proj ID STP 1402(067)
Work Type MILL, OVERLAY AND BASE REPAIR
 
2.274 1011236.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1549-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143045
Totals 5913903.69 0.00 0.00 0.0

CountyNUECES
Highway FM 43
From SH 286
To YORKTOWN BLVD.
CSJ 1557-01-037
Proj ID STP 2013(556)MM
Work Type GRADE, BASE, SURF, STRS
 
1.884 9863126.39 674935.37 4448047.71 45.0
Work Order 08-02-13
Work Began 01-27-14
Work Completed  
Time Computed 06-03-13
Contract Working Days 317
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 45
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1557-01-037
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.20%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.42%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.22%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.22%)
SOIL-TECH, INC.(0.33%)
D & C CONCRETE CUTTING, INC. (0.11%)
BEDO CONSTRUCTION PRODUCTS, INC. (1.98%)
PRIMATE CONSTRUCTION, INC. (0.05%)
DELTA PRIME SPECIALTY SERVICES, INC. (0.06%)
ADVANCED PUMPING, LLC(0.10%)
Contract # 04133202
Totals 9863126.39 674935.37 4448047.71 45.0

CountyNUECES
Highway SH 361
From AVE. G IN PORT ARANSAS
To BEACH ACCESS 1
CSJ 2263-03-029
Proj ID C 2263-3-29
Work Type GRD, BASE, STRS, STORM SEWER, C & G, SIDE
 
2.621 12988210.75 0.00 79300.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-23-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133021
Totals 12988210.75 0.00 79300.00 0.6

CountyNUECES
Highway SH 361
From ACCESS RD1A
To MARINERS DR.
CSJ 2263-03-035
Proj ID STP 2014(610)
Work Type LANDSCAPE IMPROVEMENTS
 
4.570 143796.00 25580.40 107520.90 74.7
Work Order 05-09-14
Work Began 06-11-14
Work Completed  
Time Computed 05-25-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 48
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2263-03-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.73%)
Contract # 04143023
Totals 143796.00 25580.40 107520.90 74.7

CountyNUECES
Highway FM 2444
From SH 286
To OSO PARKWAY INTERSECTION
CSJ 2343-01-036
Proj ID STP 2013(936)MM
Work Type GRADE, BASE, SURF, STRTS
 
4.051 24447530.97 0.00 1238087.96 5.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2343-01-036
AARON CONCRETE CONTRACTORS, L.P. (0.33%)
MURRAY CONSTRUCTION(0.19%)
SOIL-TECH, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.57%)
STAR OPERATIONS, INC.(1.63%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.95%)
PENNTEX MILLING, LLC (0.30%)
Contract # 08133005
Totals 24447530.97 0.00 1238087.96 5.0

page 1 | page 2