Monthly State Let Maintenance Report For Dallas District As Of Jul 14, 2017 Page 1 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6175-73-001
Proj IDRMC - 617573001
Work TypeSWEEPING, AGGREGATE AND DEBRIS REMOVAL
 
0.001247147.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6175-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07084004
Totals247147.950.000.000.0

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL AND
ToCOLLIN COUNTIES
CSJ6179-66-001
Proj IDRMC - 617966001
Work TypeVEGETATION MANAGEMENT
 
0.001138484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABH TREE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6179-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11094014
Totals138484.000.000.000.0

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-98-001
Proj IDRMC - 626398001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001481998.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154005
Totals481998.500.000.000.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6264-18-001
Proj IDRMC - 626418001
Work TypeGENERAL PAVEMENT REPAIR
 
0.0106473250.004580858.4670.7
Work Order05-12-14
Work Began05-19-14
Work Completed
Time Computed05-19-14
Contract Working Days730
Addl Days Granted548
Working Days Charged1,128
Percent Time Used88
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03144029
Totals6473250.000.004580858.4670.7

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS COUNTY
ToMAINTENANCE SECTION
CSJ6276-62-001
Proj IDRMC - 627662001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001533147.4556358.2110.5
Work Order04-16-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days365
Addl Days Granted730
Working Days Charged787
Percent Time Used71
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02154216
Totals533147.454161.7256358.2110.5

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATIONS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6276-71-001
Proj IDRMC - 627671001
Work TypePOTHOLE REPAIR
 
0.0012875000.00866106.1030.1
Work Order05-11-15
Work Began05-18-15
Work Completed
Time Computed05-18-15
Contract Working Days730
Addl Days Granted365
Working Days Charged771
Percent Time Used70
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154012
Totals2875000.0037697.20866106.1030.1

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToKAUFMAN COUNTY
CSJ6276-80-001
Proj IDRMC - 627680001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.001568906.90489388.7886.0
Work Order05-06-15
Work Began05-13-15
Work Completed
Time Computed05-13-15
Contract Working Days730
Addl Days Granted263
Working Days Charged776
Percent Time Used78
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6276-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154213
Totals568906.9019200.00489388.7886.0

CountyDENTON
HighwayIH0035W
FromIH, US, SH, LP, AND BU ROADWAYS IN THE
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6277-58-001
Proj IDRMC - 627758001
Work TypePERFORMANCE BASED VEGETATION MANAGEMENT
 
0.1001853000.001222912.8065.9
Work Order03-09-15
Work Began03-09-15
Work Completed
Time Computed03-16-15
Contract Working Days1,096
Addl Days Granted0
Working Days Charged835
Percent Time Used76
Contractor(s)
MANN ROBINSON & SON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01154012
Totals1853000.0029030.401222912.8065.9

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY
CSJ6280-68-001
Proj IDRMC - 628068001
Work TypeFLEXIBLE PVMT STRUCTURE REPAIR & OVERLAY
 
0.0014787375.003349239.6269.9
Work Order04-24-15
Work Began05-04-15
Work Completed
Time Computed05-04-15
Contract Working Days365
Addl Days Granted730
Working Days Charged784
Percent Time Used71
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6280-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154209
Totals4787375.000.003349239.6269.9

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6280-74-001
Proj IDRMC - 628074001
Work TypeCALL OUT REFLECTORIZED PAVMENT MARKINGS
 
0.001893845.00205172.8222.9
Work Order06-09-15
Work Began06-15-15
Work Completed
Time Computed06-16-15
Contract Working Days730
Addl Days Granted172
Working Days Charged737
Percent Time Used81
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154010
Totals893845.000.00205172.8222.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6282-57-001
Proj IDRMC - 628257001
Work TypePOTHOLE REPAIR & EDGE REPAIR
 
0.001651630.00445142.4268.3
Work Order08-12-15
Work Began08-24-15
Work Completed
Time Computed08-24-15
Contract Working Days730
Addl Days Granted0
Working Days Charged675
Percent Time Used92
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154204
Totals651630.0024202.51445142.4268.3

CountyDALLAS
HighwayIH0030
FromNEAR ERVAY ST
ToNORTHWEST DRIVE
CSJ6285-62-001
Proj IDRMC - 628562001
Work TypePERFORM BASE O & M OF HOV LANE & BTM
 
11.10010595000.004830678.5045.5
Work Order09-23-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days1,460
Addl Days Granted0
Working Days Charged634
Percent Time Used43
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6285-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154010
Totals10595000.00220312.504830678.5045.5

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToROCKWALL COUNTY
CSJ6285-83-001
Proj IDRMC - 628583001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.001376732.00270296.8571.7
Work Order09-21-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged634
Percent Time Used86
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6285-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154008
Totals376732.0012563.20270296.8571.7

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAITNENANCE SECTION
CSJ6290-32-001
Proj IDRMC - 629032001
Work TypeSWEEPING/DEBRIS REMOVAL
 
0.0011810867.00357193.0019.7
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged248
Percent Time Used33
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6290-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164005
Totals1810867.0050594.04357193.0019.7

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN_THE
ToELLIS COUNTY_MAINTENANCE SECTION
CSJ6290-53-001
Proj IDRMC - 629053001
Work TypeGUARDRAIL UPGRADE/REPAIR
 
0.001584050.00475522.5081.4
Work Order03-08-16
Work Began03-15-16
Work Completed
Time Computed03-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged467
Percent Time Used63
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164012
Totals584050.0037000.00475522.5081.4

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6292-16-001
Proj IDRMC - 629216001
Work TypeRETROREFLECT PAVEMENT MARKINGS
 
0.001760061.04308348.0540.5
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged201
Percent Time Used55
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164209
Totals760061.0457633.91308348.0540.5

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE DALLAS COUNTY
ToMAINTENANCE SECTIONS
CSJ6292-51-001
Proj IDRMC - 629251001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001874836.10362958.5541.4
Work Order06-08-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted123
Working Days Charged360
Percent Time Used73
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6292-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164011
Totals874836.1038732.11362958.5541.4

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE
ToDALLAS DISTRICT
CSJ6292-93-001
Proj IDRMC - 629293001
Work TypeNON-SITE SPEC SIGN REPLACEMENT & REFURB
 
0.001628889.99171427.7727.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-16
Work Began08-03-16
Work Completed
Time Computed08-03-16
Contract Working Days730
Addl Days Granted0
Working Days Charged296
Percent Time Used40
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164013
Totals628889.990.00171427.7727.2

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-56-001
Proj IDRMC - 629356001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001425785.7069653.8416.3
Work Order05-26-16
Work Began05-31-16
Work Completed
Time Computed06-02-16
Contract Working Days365
Addl Days Granted215
Working Days Charged391
Percent Time Used67
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6293-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164012
Totals425785.706965.5269653.8416.3

CountyCOLLIN
HighwayFM1827
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6293-57-001
Proj IDRMC - 629357001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0011434042.501471730.5099.9
Work Order09-09-16
Work Began09-16-16
Work Completed
Time Computed09-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged284
Percent Time Used77
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6293-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164212
Totals1434042.500.001471730.5099.9