Monthly State Let Construction Report For El Paso District As Of Dec 10, 2014 Page 1 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From NM STATE LINE
To SH 20 MESA
CSJ 0001-01-058
Proj ID CM 2014(902)
Work Type TRAFFIC OPERATION
 
11.100 1133585.95 0.00 60452.25 5.3
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-01-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143219
Totals 1133585.95 0.00 60452.25 5.3

CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-074
Proj ID NH 2011(327)
Work Type INTERSECTION IMPROVEMENTS AND REHAB
 
0.875 5607003.00 0.00 6826648.27 99.9
CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-082
Proj ID RW 2-1-82
Work Type ROW ACQUISITION
 
1.472 1053076.70 0.00 1228957.67 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-11
Work Began 01-23-12
Work Completed  
Time Computed 01-23-12
Contract Working Days 240
Addl Days Granted 128
Working Days Charged 368
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-074
TRI STATE ELECTRIC, LTD. ( 12.27%)
A BROTHERS (1.06%)
ROAD MARKINGS INC. (0.90%)
THREE C"S CONTRACTORS, INC.(0.42%)
DH UNDERGROUND, INC. (0.30%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(6.50%)
RNJ CONCRETE, INC. (2.70%)
PMI PAVEMENT MARKING, INC. (0.92%)
Contract # 09113026
Totals 6660079.70 0.00 8055605.94 99.9

CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-090
Proj ID C 2-1-90
Work Type ROADWAY IMPROVEMENTS
 
0.700 9768518.24 1007989.51 7702168.93 78.8
CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-092
Proj ID RW 2-1-92
Work Type ADJUSTMENT OF UTILITIES
 
0.700 706816.30 50133.00 483923.30 68.4
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-20-14
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 72
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-090
A BROTHERS (OLD PRIME) (0.90%)
BORDER DEMOLITION & ENVIRONMENTAL INC. (1.06%)
D"AMBRA STEEL SERVICES, INC. (HUB) (3.74%)
FALC ENTERPRISES, LLC(0.00%)
PALO VERDE CONSTRUCTORS(1.13%)
PRIME IRRIGATION & LANDSCAPE, INC. (2.72%)
QUARRY HILLS, LTD. (0.57%)
SANCHEZ CONSTRUCTION & LANDSCAPING (2.83%)
SATARAIN CONSTRUCTION, INC.(4.66%)
TRAFFIC BARRICADE SERVICE, INC.(0.83%)
TRI STATE ELECTRIC, LTD. ( 15.64%)
HARDY HOLE DRILLING(0.36%)
PMI PAVEMENT MARKING, INC. (0.56%)
Contract # 08133020
Totals 10475334.54 1058122.51 8186092.23 78.1

CountyEL PASO
Highway SH 20
From 0.06 MI N OF HORIZON BLVD
To 0.07 MI S OF HORIZON BLDV
CSJ 0002-02-050
Proj ID STP 2013(147)
Work Type RECONSTRUCT INTERSECTION
 
0.229 1129305.88 0.00 6800.00 0.6
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-001
Proj ID STP 2009(791)
Work Type RECONSTRUCTING AND WIDENING
 
1.190 4596242.98 2339.43 1687317.03 36.7
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-003
Proj ID RW 8056-24-3
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.190 1779757.14 0.00 733982.28 41.2
Work Order 11-09-12
Work Began 07-08-13
Work Completed  
Time Computed 11-25-12
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 36
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 8056-24-001
HAWK CONSTRUCTION(5.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.59%)
TRI STATE ELECTRIC, LTD. (6.42%)
ALLIED PAVING CO.(0.10%)
PRIME IRRIGATION & LANDSCAPE, INC. (4.38%)
A BROTHERS MILLING, LLC(0.43%)
GREATER EL PASO SANDBLASTING (0.28%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.49%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%)
DH UNDERGROUND, INC. (2.04%)
Contract # 09123021
Totals 7505306.00 2339.43 2428099.31 32.3

CountyEL PASO
Highway SH 20
From AT INGLEWOOD
To .
CSJ 0002-02-052
Proj ID STP 2013(978)
Work Type INTERSECTION IMPROVEMENTS
 
1.000 235144.68 18895.55 255556.85 99.9
Work Order 03-25-14
Work Began 04-10-14
Work Completed  
Time Computed 04-10-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 95
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-02-052
HARDY HOLE DRILLING(0.33%)
HAWK CONSTRUCTION( 20.27%)
PMI PAVEMENT MARKING, INC. (4.24%)
BORDER DRILLING LLC(0.65%)
Contract # 02143030
Totals 235144.68 18895.55 255556.85 99.9

CountyHUDSPETH
Highway IH 10
From 0.23 MI E OF FM 34
To 8.38 MI W OF FM 1111
CSJ 0002-06-051
Proj ID IM 0101(266)
Work Type INSTALL MEDIAN BARRIER
 
69.455 4277160.00 17500.00 4284980.53 100.0
Work Order 10-17-13
Work Began 11-11-13
Work Completed 11-03-14
Time Computed 11-02-13
Contract Working Days 160
Addl Days Granted 30
Working Days Charged 180
Percent Time Used 94
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-051
HARDY HOLE DRILLING(1.99%)
LONE STAR HIGHWAY PRODUCTS, INC. ( 28.64%)
Contract # 09133041
Totals 4277160.00 17500.00 4284980.53 100.0

CountyEL PASO
Highway FM 258
From 0.14 MI W OF SH 20 INTERSECTION
To 0.56 MI W OF SH 20 INTERSECTION
CSJ 0002-14-040
Proj ID STP 2013(941)
Work Type REPLACE STRUCTURE
 
0.420 322477.50 128388.41 212505.00 65.8
Work Order 09-10-13
Work Began 00-00-00
Work Completed  
Time Computed 09-26-13
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 34
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133229
Totals 322477.50 128388.41 212505.00 65.8

CountyEL PASO
Highway US 54
From AT LP 375
To .
CSJ 0167-01-106
Proj ID STP 1102(033)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 359618.50 0.00 376379.56 99.9
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER ST)
CSJ 2552-01-036
Proj ID STP 1102(031)
Work Type CONSTRUCT MAIN LANES AND INTERCHANG
 
1.875 36214322.88 66871.70 40837268.54 99.9
CountyEL PASO
Highway LP 375
From 1 M WEST OF US 54
To US 54 (GATEWAY BLVD SOUTH)
CSJ 2552-01-038
Proj ID NH 1102(032)
Work Type CONSTRUCTION OF UNDERPASS MAINLANES
 
0.846 11122609.24 7800.00 9679645.74 87.0
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER STREET)
CSJ 2552-01-040
Proj ID NH 2011(936)
Work Type ROW ACQ & UTL ADJ
 
3.220 1970294.50 34778.50 1569920.52 79.6
Work Order 05-25-11
Work Began 12-12-11
Work Completed  
Time Computed 06-10-11
Contract Working Days 504
Addl Days Granted 120
Working Days Charged 600
Percent Time Used 96
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-036
A BROTHERS MILLING, LLC(0.25%)
DANRIDGE CONSTRUCTION, LLC.(0.51%)
UNINTECH CONSULTING ENGINEERS, INC.(0.08%)
SATARAIN CONSTRUCTION, INC.(0.92%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.36%)
THREE C"S CONTRACTORS, INC.(0.16%)
HARDY HOLE DRILLING(1.40%)
HENRY TRUJILLO, INC. (0.32%)
SOUTH TEXAS PAINTING COMPANY (0.37%)
RIVER CITIES SAWING LLC(0.20%)
ROAD MARKINGS INC. (0.35%)
TRI STATE ELECTRIC, LTD. ( 10.22%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(4.42%)
STEEL EFFECTS(0.64%)
FORET COMPANIES(0.07%)
ACCURATE CORING, INC.(0.03%)
EARTH REINFORCEMENT SPECIALISTS(1.75%)
STAR CITY SEALANTS (0.01%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.31%)
BORDER DRILLING LLC(0.02%)
PAVEMENT MARKINGS INC. (0.07%)
ACCENT LANDSCAPE CONTRACTORS, INC. (0.00%)
Contract # 04113201
Totals 49666845.12 109450.20 52463214.36 99.9

CountyEL PASO
Highway US 54
From LP 375 (BORDER HIGHWAY)
To MCCOMBS
CSJ 0167-01-108
Proj ID CM 2014(024)
Work Type ALTERNATE ROUTES, PHASE II
 
14.000 1898217.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133221
Totals 1898217.38 0.00 0.00 0.0

CountyEL PASO
Highway LP 478
From 260 FT N OF KEMP AVE
To ELLERTHORPE AVE
CSJ 0167-02-055
Proj ID STP 2014(136)TE
Work Type PEDESTRIAN ENHANCEMENTS
 
0.449 160820.00 7200.00 164249.70 99.9
CountyEL PASO
Highway LP 478
From PERSHING DR
To FRED WILSON AVE
CSJ 0167-02-056
Proj ID NH 2014(865)
Work Type CONSTRUCTION / REHAB SIDEWALKS FY2014
 
1.913 84340.00 7000.00 87710.30 99.9
Work Order 08-13-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 98
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143017
Totals 245160.00 14200.00 251960.00 99.9

CountyCULBERSON
Highway US 62
From 8.683 MI E OF SH 54 JUNCTION
To 19.302 MI E OF SH 54 JUNCTION
CSJ 0233-01-045
Proj ID NH 2014(850)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
33.019 6441134.87 0.00 35100.00 0.5
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143044
Totals 6441134.87 0.00 35100.00 0.5

CountyEL PASO
Highway US 62
From 0.663 MI W OF YARBROUGH DR INTERSEC
To 0.473 MI E OF LP 375 INTERSECTION
CSJ 0374-02-094
Proj ID C 374-2-94
Work Type WIDEN ROADWAY FROM 4 TO 6 LANE
 
5.008 5714604.40 604314.24 2799990.70 48.9
Work Order 12-03-13
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 160
Addl Days Granted 23
Working Days Charged 113
Percent Time Used 61
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-094
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.19%)
HARDY HOLE DRILLING(2.69%)
PRIME IRRIGATION & LANDSCAPE, INC. (4.92%)
TRI STATE ELECTRIC, LTD. ( 24.32%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(1.79%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.25%)
E. G. L. CONSTRUCTION, INC.(1.99%)
VERTEX CONTRACTORS, LLC(2.38%)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.83%)
HAWK CONSTRUCTION(0.07%)
BORDER DRILLING LLC(0.75%)
HARDY HOLE DRILLING(0.08%)
PASO DEL NORTE MATERIALS, LLC( 13.89%)
Contract # 08133025
Totals 5714604.40 604314.24 2799990.70 48.9

CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-001
Proj ID STP 2012(390)MM
Work Type GR, STRS, ACP, SIGN & DEL
 
2.198 12311210.24 5305.00 12107156.95 98.3
CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-002
Proj ID STP 1102(539)MM
Work Type ROW ACQ. & UTIL ADJUST.
 
1.608 660927.00 0.00 857598.51 99.9
Work Order 10-18-12
Work Began 01-02-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 576
Addl Days Granted 0
Working Days Charged 421
Percent Time Used 73
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0608-01-001
SATARAIN CONSTRUCTION, INC.(4.87%)
HARDY HOLE DRILLING(0.61%)
TRI STATE ELECTRIC, LTD. ( 16.69%)
ACCENT LANDSCAPE CONTRACTORS, INC. (3.41%)
A BROTHERS (OLD PRIME) (0.16%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.15%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.18%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
HENRY TRUJILLO, INC. (1.29%)
BORDER DRILLING LLC(0.02%)
WESTERN DEWATERING INC.(0.13%)
CONTRACTORS SOURCE, INC._(CSI) (0.00%)
HARDY HOLE DRILLING(0.02%)
Contract # 08123205
Totals 12972137.24 5305.00 12964755.46 99.9

CountyEL PASO
Highway FM 76
From 0.3 MI W OF THE CITY LIMITS
To 0.28 MI E OF FM 1281 (HORIZON BLVD)
CSJ 0674-01-037
Proj ID STP 2012(183)
Work Type GR, STRS & SURF
 
2.850 17477183.46 66106.07 3000998.93 17.1
CountyEL PASO
Highway FM 76
From 0.3 MILES WEST OF THE CITY LIMITS
To 0.28 MILES E. OF FM 1281 (HORIZON B
CSJ 0674-01-058
Proj ID RW 674-1-58
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1317086.00 0.00 0.00 0.0
Work Order 01-31-12
Work Began 07-02-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 25
Contractor(s)
CF JORDAN CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0674-01-037
D"AMBRA STEEL SERVICES, INC. (HUB) (8.20%)
A BROTHERS (0.24%)
PRIME IRRIGATION & LANDSCAPE, INC. (0.89%)
SANCHEZ CONSTRUCTION & LANDSCAPING (1.98%)
TRI STATE ELECTRIC, LTD. ( 11.87%)
RNJ CONCRETE, INC. (5.82%)
PALO VERDE CONSTRUCTORS(3.03%)
C & C ROAD CONSTRUCTION, INC.(1.19%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
Contract # 12113202
Totals 18794269.46 66106.07 3000998.93 15.9

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-065
Proj ID STP 2013(862)
Work Type SIGNING PROJECT
 
62.000 656177.04 69253.97 437610.18 66.6
Work Order 01-06-14
Work Began 09-22-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 44
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-065
HARDY HOLE DRILLING(2.50%)
Contract # 07133020
Totals 656177.04 69253.97 437610.18 66.6

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-083
Proj ID STP 2015(545)
Work Type BRIDGE MAINTENANCE PROGRAM FY 2015
 
1.000 1351434.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143031
Totals 1351434.00 0.00 0.00 0.0

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-086
Proj ID STP 2013(863)
Work Type METAL BEAM GUARD FENCE / SGT UPGRADES
 
3.282 1408923.00 0.00 573860.78 40.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 11-14-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 78
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133012
Totals 1408923.00 0.00 573860.78 40.7

CountyEL PASO
Highway VA
From BRIDGE MAINTENANCE
To (DISTRICTWIDE)
CSJ 0924-00-093
Proj ID STP 2014(573)
Work Type BRIDGE MAINTENANCE PROJECTS
 
1.000 1390036.00 144288.00 263154.25 18.9
Work Order 05-13-14
Work Began 05-29-14
Work Completed  
Time Computed 05-29-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 13
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143022
Totals 1390036.00 144288.00 263154.25 18.9

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-094
Proj ID STP 2014(733)
Work Type SIGN REPLACEMENT
 
1.000 212389.42 41055.00 388666.42 99.9
CountyEL PASO
Highway VA
From DISTRICTWIDE
To (STATE FUNDED)
CSJ 0924-00-095
Proj ID C 924-00-095
Work Type SIGN REPLACEMENT
 
1.000 6339.94 0.00 4614.94 72.7
Work Order 06-10-14
Work Began 08-06-14
Work Completed  
Time Computed 06-26-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 110
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-094
CARRERA CONSTRUCTION, INC. ( 84.21%)
Contract # 05143215
Totals 218729.36 41055.00 393281.36 99.9

CountyEL PASO
Highway CS
From DESERT SOUTH
To RESLER
CSJ 0924-06-432
Proj ID HP 2013(961)
Work Type PASEO DEL NORTE IMPROVEMENTS
 
0.576 1279752.30 70552.29 1306533.96 99.9
Work Order 01-06-14
Work Began 02-03-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 100
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-432
PMI PAVEMENT MARKING, INC. (1.31%)
PRIME IRRIGATION & LANDSCAPE, INC. (1.08%)
TAPIA"S GENERAL CONTRACTING, INC.(1.66%)
TRAFFIC BARRICADE SERVICE, INC.(1.18%)
HARDY HOLE DRILLING(1.24%)
TRI STATE ELECTRIC, LTD. ( 67.67%)
HAWK CONSTRUCTION(0.32%)
ZTEX CONSTRUCTION, INC.(3.91%)
Contract # 08133220
Totals 1279752.30 70552.29 1306533.96 99.9